7/15/2025 5:44:51 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
7/15/2025 5:43:42 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/11/2025 6:27:15 PM
|
Request for Review Comments returned by EPC Health Department
|
7/2/2025 4:46:27 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
7/2/2025 2:40:06 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
7/2/2025 2:08:11 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
7/2/2025 2:08:10 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
7/2/2025 2:08:07 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Justin Kilgore on behalf of PCD Project Manager
|
7/2/2025 2:00:08 PM
|
Submission Triaged
|
7/2/2025 11:25:17 AM
|
Submission received from Applicant
|
6/26/2025 2:18:29 PM
|
Fees paid: 6/26/2025 (Receipt: 1010703)
|
6/26/2025 2:10:40 PM
|
Submission request sent to Applicant
|
6/26/2025 2:09:18 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/24/2025 1:45:30 PM
|
Request for Review Comments returned by EPC Parks Department
|
6/23/2025 5:07:07 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
6/23/2025 10:41:08 AM
|
Payment Request sent: 6/23/2025
|
6/23/2025 10:40:49 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
6/23/2025 10:01:51 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
6/23/2025 8:50:12 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
6/19/2025 4:16:14 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/19/2025 2:08:13 PM
|
Request for Review Comments returned by EPC Fire and Wildfire Program Manager
|
6/9/2025 2:26:26 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
6/9/2025 11:00:58 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
6/9/2025 8:18:22 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
6/6/2025 3:14:11 PM
|
Request for Review Comments returned by EPC Environmental Services
|
6/4/2025 8:02:46 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
6/4/2025 8:02:44 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by on behalf of Pikes Peak Regional Building Department
|
6/4/2025 8:02:43 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
6/4/2025 8:02:42 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
6/4/2025 8:02:41 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
6/4/2025 8:02:40 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
6/4/2025 8:02:39 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Peter Chapman on behalf of Colorado Parks and Wildlife
|
6/4/2025 8:02:38 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
6/4/2025 8:02:37 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
|
6/4/2025 8:02:36 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
6/4/2025 8:02:35 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
6/4/2025 8:02:34 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
6/4/2025 8:02:33 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
6/4/2025 8:02:32 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by on behalf of EPC Parks Department
|
6/4/2025 8:02:30 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Mike McCarthy on behalf of EPC Health Department
|
6/4/2025 8:02:29 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Catherine McGarvy on behalf of EPC Health Department
|
6/4/2025 8:02:28 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by HEAEH LandUse on behalf of EPC Health Department
|
6/4/2025 8:02:27 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Kathy Andrew on behalf of EPC Environmental Services
|
6/4/2025 8:02:26 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
6/4/2025 8:02:25 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
6/4/2025 8:02:24 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Glenn Reese on behalf of EPC DPW Stormwater
|
6/4/2025 8:02:23 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Christina Prete on behalf of EPC DPW Stormwater
|
6/4/2025 8:02:22 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
6/4/2025 8:02:21 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
6/4/2025 8:02:19 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Justin Kilgore on behalf of PCD Project Manager
|
6/4/2025 8:02:17 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by on behalf of PCD Administrative Notice
|
6/4/2025 8:02:16 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 3A for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
|
6/3/2025 1:40:54 PM
|
Project Manager Assigned: Lacey Dean
|
6/2/2025 1:25:12 PM
|
Project Manager Assigned: Ryan Howser
|
6/2/2025 10:59:35 AM
|
Fees paid: 6/2/2025 (Receipt: 1010598)
|
5/30/2025 1:12:56 PM
|
Payment Request sent: 5/30/2025
|
5/30/2025 1:12:56 PM
|
File # Assigned: VR257
|
5/30/2025 1:12:53 PM
|
Submission Triaged
|
5/30/2025 11:49:19 AM
|
Submission received from Applicant
|
5/22/2025 11:29:15 AM
|
Submission request sent to Applicant
|
5/22/2025 11:19:58 AM
|
Project Created
|