Project Details

Search | All Active Projects


File Number
P254
Project Name
Antler Range Rezone
Description
Rezone from A-35 to RR-2.5
Parcels
4218000022 4218000022
Applicant
Vertex Consulting Services
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 733-8606 x6606
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 733-8606 x6606
EA Number
EA24123
File Prefix
P - Rezoning to A-5; A-35; F-5; RR.5; RR2,5; and RR-2
Year
2025
Project Manager
Lisa Elgin
Status
Active
Created
11/7/2024 11:56:09 AM

View: Review Comments


Approved Documents (1)

Project pending final approval. Some approved documents are available prior to the overall Approval.

Link Document
View Traffic Impact Study


Additional Documents (9)

Link Document Comment
View PC Hearing Agenda Hearing Agenda for the Planning Commission hearing on 08/21/2025. JM
View Hearing Notice & Vicinity Map Hearing Notice for the Planning Commission hearing on 08/21/2025 and the Board of County Commissioners hearing on 09/11/2025. JM
View Mailing Labels - Hearing Notice Mailing Labels for the 44 surrounding property owners that received notices. PCD mailed the letters on 08/07/2025. Cost = $32.56. JM
View Selected Range - Hearing Notice Selected Range was 500 feet. JM
View PC & BOCC Poster Poster for the Planning Commission hearing on 08/21/2025 and the Board of County Commissioners hearing on 09/11/2025. JM
View Notarized Affidavit for Notice of Public Hearing
View Posters on Property
View Affidavit of Published Legal Advertisement P254 AFFIDAVIT FOR PUBLISHED LEGAL. Gazette 08-12-2025
View PC Staff Report - final with attachments Staff Report for the Planning Commission hearing on 08/21/2025. JM


Review Documents (10)

Link Document Date
View Application/Petition Form 5/16/2025 10:54:06 AM
View Legal Description (MS WORD Version required) 5/16/2025 10:58:46 AM
View Letter of Intent 6/30/2025 7:31:13 AM
View Mineral Rights Certification 3/20/2025 11:27:18 AM
View Traffic Impact Study 6/13/2025 11:20:41 AM
View Zoning Map 6/30/2025 7:28:53 AM
View LOI Response 6/13/2025 2:19:43 PM
View TIS Comment Response 6/13/2025 11:20:42 AM
View Title Commitment 2/3/2025 11:43:34 AM
View Zoning Map Response 6/13/2025 11:28:17 AM



Events (56)

Date Comment
7/9/2025 2:53:17 PM Request for Review Comments returned by PCD Project Manager
6/30/2025 8:54:56 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Justin Kilgore on behalf of PCD Project Manager
6/30/2025 8:39:00 AM Submission Triaged
6/30/2025 7:31:43 AM Submission received from Applicant
6/27/2025 3:55:28 PM Submission request sent to Applicant
6/27/2025 1:03:09 PM Request for Review Comments returned by PCD Engineering Division
6/27/2025 11:48:42 AM Request for Review Comments returned by PCD Project Manager
6/13/2025 4:37:52 PM Request for Review Comments email sent for Project Antlers Range Rezone for review by Justin Kilgore on behalf of PCD Project Manager
6/13/2025 4:37:51 PM Request for Review Comments email sent for Project Antlers Range Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
6/13/2025 4:37:50 PM Request for Review Comments email sent for Project Antlers Range Rezone for review by Engineering Manager on behalf of PCD Engineering Division
6/13/2025 4:25:45 PM Submission Triaged
6/13/2025 2:19:51 PM Submission received from Applicant
5/27/2025 1:43:54 PM Submission request sent to Applicant
3/28/2025 3:28:10 PM Request for Review Comments returned by EPC Health Department
3/20/2025 10:27:49 AM Submission request sent to Applicant
3/20/2025 10:26:02 AM Request for Review Comments returned by PCD Project Manager
3/17/2025 12:46:32 PM Request for Review Comments returned by PCD Engineering Division
3/17/2025 11:10:04 AM Request for Review Comments returned by Falcon School District 49
3/10/2025 12:12:16 PM Request for Review Comments returned by Falcon Fire Protection District
3/6/2025 8:53:11 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/4/2025 11:04:41 AM Request for Review Comments returned by EPC Parks Department
2/25/2025 7:51:06 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
2/24/2025 10:45:54 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
2/24/2025 10:45:53 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Trent Harwig on behalf of Falcon Fire Protection District
2/24/2025 10:45:52 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Curtis Kauffman on behalf of Falcon Fire Protection District
2/24/2025 10:45:51 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Harry Thomas on behalf of El Paso County Conservation Dist
2/24/2025 10:45:50 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Oliver Watkins on behalf of El Paso County Conservation Dist
2/24/2025 10:45:49 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Katie Miller on behalf of El Paso County Conservation Dist
2/24/2025 10:45:48 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Erica Carter on behalf of El Paso County Conservation Dist
2/24/2025 10:45:47 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by on behalf of El Paso County Conservation Dist
2/24/2025 10:45:46 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Mariah Hudson on behalf of El Paso County Conservation Dist
2/24/2025 10:45:45 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Cassie Olgren on behalf of El Paso County Conservation Dist
2/24/2025 10:45:44 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Billy Richard on behalf of El Paso County Conservation Dist
2/24/2025 10:45:42 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
2/24/2025 10:45:41 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
2/24/2025 10:45:40 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Bob Swatek on behalf of Black Hills Energy-Aquila
2/24/2025 10:45:39 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Adam Magoon on behalf of Black Hills Energy-Aquila
2/24/2025 10:45:38 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
2/24/2025 10:45:37 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by on behalf of Pikes Peak Regional Building Department
2/24/2025 10:45:36 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Evelyn galanephillips on behalf of Falcon School District 49
2/24/2025 10:45:35 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by on behalf of EPC Parks Department
2/24/2025 10:45:33 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Mike McCarthy on behalf of EPC Health Department
2/24/2025 10:45:32 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Catherine McGarvy on behalf of EPC Health Department
2/24/2025 10:45:31 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by HEAEH LandUse on behalf of EPC Health Department
2/24/2025 10:45:29 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Justin Kilgore on behalf of PCD Project Manager
2/24/2025 10:45:28 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
2/24/2025 10:45:27 AM Request for Review Comments email sent for Project Antlers Range Rezone for review by Engineering Manager on behalf of PCD Engineering Division
2/20/2025 8:34:32 AM Project Manager Assigned: Lisa Elgin
2/19/2025 4:10:57 PM Fees paid: 2/19/2025 (Receipt: 1010188)
2/19/2025 2:43:55 PM Payment Request sent: 2/19/2025
2/19/2025 2:43:55 PM File # Assigned: P254
2/19/2025 2:43:53 PM Submission Triaged
2/17/2025 1:57:00 PM Submission received from Applicant
11/13/2024 8:12:52 AM Submission request sent to Applicant
11/7/2024 11:56:13 AM EA Assigned: EA24123
11/7/2024 11:56:13 AM Project Created