4/18/2025 10:42:50 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
4/7/2025 4:48:38 PM
|
Request for Review Comments returned by PCD Engineering Inspections
|
4/4/2025 10:42:15 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/31/2025 9:41:23 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Brad Walters on behalf of PCD Engineering Inspections
|
3/31/2025 9:41:22 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/31/2025 9:41:20 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
|
3/31/2025 9:39:31 AM
|
Submission Triaged
|
3/28/2025 3:42:05 PM
|
Submission received from Applicant
|
3/24/2025 10:50:25 AM
|
Submission request sent to Applicant
|
3/21/2025 2:45:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/17/2025 9:44:57 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/17/2025 9:44:55 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
|
3/17/2025 9:43:27 AM
|
Submission Triaged
|
3/13/2025 9:20:51 AM
|
Submission received from Applicant
|
3/12/2025 3:51:49 PM
|
Submission request sent to Applicant
|
3/12/2025 3:51:28 PM
|
Project reopened for Review Comments
|
3/6/2025 3:49:03 PM
|
Submission request sent to Applicant
|
2/25/2025 7:29:38 AM
|
Project Closed
|
2/25/2025 7:29:38 AM
|
Project Approved: 2/25/2025
|
2/24/2025 4:23:56 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/7/2025 3:39:50 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/6/2025 3:58:13 PM
|
Project reopened for Review Comments
|
2/4/2025 11:33:39 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/4/2025 11:33:37 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
|
2/4/2025 11:32:08 AM
|
Submission Triaged
|
2/3/2025 4:02:44 PM
|
Submission received from Applicant
|
2/3/2025 9:36:26 AM
|
Submission request sent to Applicant
|
12/5/2024 9:24:22 AM
|
Project Closed
|
12/5/2024 9:24:21 AM
|
Project Approved: 12/5/2024
|
12/4/2024 2:57:25 PM
|
Project Manager Assigned: Charlene Durham
|
9/30/2024 5:03:28 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/19/2024 5:21:46 PM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/19/2024 5:21:43 PM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
|
9/19/2024 5:21:16 PM
|
Submission Triaged
|
9/18/2024 11:48:53 AM
|
Submission received from Applicant
|
9/10/2024 4:52:30 PM
|
Submission request sent to Applicant
|
9/10/2024 11:37:31 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/3/2024 7:43:53 AM
|
Request for Review Comments returned by PCD Engineering Inspections
|
9/3/2024 7:37:19 AM
|
Submission Triaged
|
8/30/2024 9:48:08 AM
|
Submission received from Applicant
|
8/27/2024 5:19:14 PM
|
Submission request sent to Applicant
|
8/21/2024 10:03:27 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Brad Walters on behalf of PCD Engineering Inspections
|
8/21/2024 10:03:25 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
8/21/2024 10:03:23 AM
|
Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
|
8/21/2024 10:02:58 AM
|
Submission Triaged
|
8/19/2024 12:53:36 PM
|
Submission received from Applicant
|
8/19/2024 8:03:08 AM
|
Submission request sent to Applicant
|
8/19/2024 8:00:20 AM
|
Set Applicant to Classic Homes Construction
|
8/19/2024 7:59:03 AM
|
No Fees
|
8/19/2024 7:59:03 AM
|
File # Assigned: PAV2412
|
8/19/2024 7:59:02 AM
|
Project Manager Assigned: Brad Walters
|
8/19/2024 7:59:02 AM
|
Project Created. Parent Project: Retreat at TimberRidge Fil No. 3 (SF2241)
|