2/26/2025 2:06:20 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/21/2025 2:47:23 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
2/19/2025 1:29:41 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Justin Kilgore on behalf of PCD Project Manager
|
2/19/2025 1:29:19 PM
|
Submission Triaged
|
2/19/2025 7:05:15 AM
|
Request for Review Comments email resent for Project 3405 Hay Creek Rezone for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
2/18/2025 4:58:44 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
2/18/2025 4:01:01 PM
|
Request for Review Comments email resent for Project 3405 Hay Creek Rezone for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
2/18/2025 3:51:43 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
2/18/2025 2:07:21 PM
|
Submission received from Applicant
|
2/18/2025 1:46:48 PM
|
Submission request sent to Applicant
|
2/18/2025 7:12:45 AM
|
Request for Review Comments email resent for Project 3405 Hay Creek Rezone for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
2/14/2025 2:14:49 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/14/2025 11:11:21 AM
|
Fees paid: 2/14/2025 (Receipt: 1010169)
|
2/14/2025 9:35:29 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
2/13/2025 4:45:13 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/13/2025 3:06:36 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/13/2025 1:33:26 PM
|
Request for Review Comments returned by USAFA Base Planner
|
2/6/2025 1:48:45 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
1/30/2025 2:33:01 PM
|
Request for Review Comments returned by EPC Parks Department
|
1/30/2025 2:09:24 PM
|
Request for Review Comments returned by EPC Environmental Services
|
1/28/2025 10:45:33 AM
|
Payment Request sent: 1/28/2025
|
1/28/2025 8:47:39 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
1/27/2025 9:24:07 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
1/24/2025 2:05:11 PM
|
Project Manager Assigned: Joe Letke
|
1/24/2025 1:34:11 PM
|
Project Manager Assigned: Kylie Bagley
|
1/24/2025 12:12:31 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Sabrina Untal on behalf of USAFA Base Planner
|
1/24/2025 12:12:30 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Matthew Fitzsimmons on behalf of USAFA Base Planner
|
1/24/2025 12:12:29 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Amy Kelley on behalf of USAFA Base Planner
|
1/24/2025 12:12:28 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by on behalf of USAFA Base Planner
|
1/24/2025 12:12:27 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
1/24/2025 12:12:26 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
1/24/2025 12:12:25 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
|
1/24/2025 12:12:24 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Vicki Wood on behalf of Lewis Palmer 38
|
1/24/2025 12:12:23 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Melissa Andrews on behalf of Lewis Palmer 38
|
1/24/2025 12:12:22 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Brett Ridgway on behalf of Lewis Palmer 38
|
1/24/2025 12:12:20 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Mike Till on behalf of Colorado State Forest Service
|
1/24/2025 12:12:19 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
1/24/2025 12:12:18 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
1/24/2025 12:12:17 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
1/24/2025 12:12:16 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
|
1/24/2025 12:12:15 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/24/2025 12:12:14 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/24/2025 12:12:13 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Christina Prete on behalf of EPC Stormwater Review
|
1/24/2025 12:12:12 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by on behalf of EPC Parks Department
|
1/24/2025 12:12:11 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
1/24/2025 12:12:10 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Justin Kilgore on behalf of PCD Project Manager
|
1/24/2025 12:12:09 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/24/2025 12:12:08 PM
|
Request for Review Comments email sent for Project 3405 Hay Creek Rezone for review by Engineering Manager on behalf of PCD Engineering Division
|
1/24/2025 12:11:35 PM
|
Request for Review Comments sent for Project 3405 Hay Creek Rezone for review by on behalf of PCD Administrative Notice
|
1/24/2025 10:39:24 AM
|
Fees paid: 1/24/2025 (Receipt: 1010083)
|
10/8/2024 10:37:14 AM
|
Payment Request sent: 10/8/2024
|
10/8/2024 10:37:14 AM
|
File # Assigned: P2413
|
10/8/2024 10:37:10 AM
|
Submission Triaged
|
10/8/2024 8:26:36 AM
|
Submission received from Applicant
|
8/1/2024 11:29:34 AM
|
Submission request sent to Applicant
|
8/1/2024 10:31:24 AM
|
Submission request sent to Applicant
|
8/1/2024 10:30:36 AM
|
EA Assigned: EA23128
|
8/1/2024 10:30:36 AM
|
Project Created
|