5/22/2025 1:21:55 PM
|
Project Manager Assigned: Kylie Bagley
|
4/28/2025 1:39:36 PM
|
Submission request sent to Applicant
|
2/13/2025 10:36:40 AM
|
Submission request sent to Applicant
|
12/3/2024 10:46:07 AM
|
Project Manager Assigned: Ashlyn Mathy
|
6/26/2024 12:53:19 PM
|
Submission request sent to Applicant
|
6/26/2024 11:03:29 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/24/2024 10:03:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/20/2024 9:35:02 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/20/2024 7:03:53 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/14/2024 8:34:37 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/12/2024 3:24:29 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
6/12/2024 3:24:27 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Katie Miller on behalf of El Paso County Conservation Dist
|
6/12/2024 3:24:25 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
6/12/2024 3:24:23 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by on behalf of Pikes Peak Regional Building Department
|
6/12/2024 3:24:21 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
6/12/2024 3:24:19 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
6/12/2024 3:24:17 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Glenn Reese on behalf of EPC Stormwater Review
|
6/12/2024 3:24:15 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Christina Prete on behalf of EPC Stormwater Review
|
6/12/2024 3:24:11 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Kari Parsons on behalf of PCD Project Manager
|
6/12/2024 3:24:08 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/12/2024 3:24:06 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Engineering Manager on behalf of PCD Engineering Division
|
6/12/2024 2:10:21 PM
|
Submission Triaged
|
6/12/2024 2:08:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/12/2024 1:56:04 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Kari Parsons on behalf of PCD Project Manager
|
6/12/2024 1:01:19 PM
|
Submission received from Applicant
|
6/5/2024 9:55:22 AM
|
Submission request sent to Applicant
|
5/14/2024 11:22:26 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/14/2024 10:45:52 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
5/13/2024 10:55:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/13/2024 10:14:36 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/9/2024 6:04:21 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
5/7/2024 12:39:24 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
5/2/2024 9:08:21 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/30/2024 2:17:30 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/29/2024 1:32:01 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/29/2024 1:31:59 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
4/29/2024 1:31:56 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Katie Miller on behalf of El Paso County Conservation Dist
|
4/29/2024 1:31:54 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
4/29/2024 1:31:52 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
4/29/2024 1:31:51 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
4/29/2024 1:31:49 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
4/29/2024 1:31:47 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by PJ Langmaid on behalf of Black Forest Fire Protection District
|
4/29/2024 1:31:45 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Black Forest Fire Chief on behalf of Black Forest Fire Protection District
|
4/29/2024 1:31:43 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
4/29/2024 1:31:40 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
4/29/2024 1:31:39 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
4/29/2024 1:31:36 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by on behalf of Pikes Peak Regional Building Department
|
4/29/2024 1:31:34 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
4/29/2024 1:31:33 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
4/29/2024 1:31:31 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Glenn Reese on behalf of EPC Stormwater Review
|
4/29/2024 1:31:29 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Christina Prete on behalf of EPC Stormwater Review
|
4/29/2024 1:31:25 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Kari Parsons on behalf of PCD Project Manager
|
4/29/2024 1:31:23 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/29/2024 1:31:21 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Engineering Manager on behalf of PCD Engineering Division
|
4/29/2024 1:31:19 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by on behalf of PCD Administrative Notice
|
4/29/2024 1:31:17 PM
|
Request for Review Comments email sent for Project 10765 KINCH CT - Stealth Tower for review by Miranda Benson on behalf of PCD Administrative Notice
|
4/12/2024 12:33:12 PM
|
Fees paid: 4/12/2024 (Receipt: 1008995)
|
4/12/2024 11:24:13 AM
|
Project Manager Assigned: Scott Weeks
|
4/12/2024 11:23:56 AM
|
Project Manager Assigned: Joe Letke
|
4/12/2024 11:23:45 AM
|
Project Manager Assigned: Lacey Dean
|
4/12/2024 11:22:35 AM
|
Payment Request sent: 4/12/2024
|
4/12/2024 11:22:35 AM
|
File # Assigned: AL244
|
4/12/2024 11:22:28 AM
|
Submission Triaged
|
4/12/2024 10:44:37 AM
|
Submission received from Applicant
|
2/8/2024 11:55:56 AM
|
Submission request sent to Applicant
|
2/8/2024 11:27:00 AM
|
Project Manager Assigned: Ashlyn Mathy
|
2/8/2024 11:27:00 AM
|
Project Created
|