Project Details

Search | All Active Projects


File Number
PPR2140
Project Name
Rocky Top Site Development Plan
Description
Site Development Plan for VA185 approval of 60 RV sites & 8 tent sites. Existing legal non-conforming motel on site (15 units). Alternative roadway landscaping along Hwy 24. Lighting Plan included. Parking on SDP. Wildfire Management Plan in LOI.
Parcels
8309200011 8309200011
Applicant
G&D enterprises
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 433-2018
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 433-2018
EA Number
EA18250
File Prefix
PPR - Plot Plan Review
Year
2021
Project Manager
Miranda Benson
Status
Active
Created
3/2/2021 6:49:04 PM

View: Review Comments


Approved Documents (5)

Project pending final approval. Some approved documents are available prior to the overall Approval.

Link Document
View Application/Petition Form
View Letter of Intent
View Landscape Plan drawings
View Lighting Plan
View Site Development Plan


Additional Documents (10)

Link Document Comment
View CDOT RC_3-12-25_EPC_24_Rockytop Compground Site Development Plan
View Review Comment Response 01.21.2025 All Terrain responses to prelim drainage plan report
View Review Comment Response 04.03.2025 All Terrain responses to drainage comments
View Review Comment Response 05.15.2025 All Terrain responses to CDOT letter
View Review Comment Response 05.15.2025 All Terrain responses to final drainage report
View Review Comment Response 05.15.2025 All Terrain responses to gec plan
View Review Comment Response 05.15.2025 All Terrain responses to pcm applicability form
View Review Comment Response 05.16.2025 All Terrain responses to site dev plan comments
View VA185 BOCC STAFF REPORT
View VA185 BOCC RESOLUTION


Review Documents (29)

Link Document Date
View Application/Petition Form 8/2/2021 4:49:33 PM
View Grading & Erosion Control checklist 4/4/2025 1:00:09 PM
View Legal Description (MS WORD Version required) 7/14/2021 3:59:18 PM
View Letter of Intent 4/4/2025 1:02:33 PM
View O&M Manual 11/22/2022 8:28:26 AM
View Private Detention Basin/Stormwater Quality BMP Maintenance Agreement 8/12/2025 10:59:53 AM
View Title Commitment (Current within 30 days of submittal) 3/3/2023 12:28:58 PM
View Vicinity/Location Map 7/14/2021 3:59:18 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 8/12/2025 7:58:48 AM
View Financial Assurance Forms 7/22/2025 9:44:41 AM
View Floor Plans (24" x 36") 8/2/2021 4:49:34 PM
View MS4 Post Construction Form 12/27/2022 2:39:52 PM
View PBMP Applicability Form 6/4/2025 7:23:17 AM
View SWMP checklist 4/4/2025 1:00:10 PM
View Grading & Erosion Control Plan 6/4/2025 7:23:16 AM
View Landscape Plan drawings 6/13/2025 10:33:39 AM
View Lighting Plan 4/4/2025 1:02:34 PM
View Sign Plan 12/29/2021 4:13:34 PM
View Site Development Plan 7/22/2025 9:44:43 AM
View Storm Water Management Plan (SWMP) 4/4/2025 1:00:06 PM
View Drainage Report - Final 6/4/2025 7:23:15 AM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 4/4/2025 1:00:03 PM
View CDOT Access Permit 8/6/2025 4:23:21 PM
View Elevation Plans 8/13/2021 2:10:32 PM
View Inspection & Maintenance Plan 4/4/2025 1:00:11 PM
View Lighting Plan 4/4/2025 1:02:35 PM
View No Build Easement Exhibits 4/4/2025 1:00:16 PM
View Pond Agreement 12/27/2022 2:45:34 PM
View Traffic Memo 4/29/2025 8:09:26 AM



Events (241)

Date Comment
8/12/2025 12:38:03 PM Request for Review Comments returned by EPC Stormwater Review
8/12/2025 11:15:40 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Steve Murphy on behalf of GMF Chipita Park Fire Protection District
8/12/2025 11:15:36 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
8/12/2025 11:15:35 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
8/12/2025 11:15:34 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
8/12/2025 11:15:01 AM Submission Triaged
8/12/2025 11:00:00 AM Submission received from Applicant
8/12/2025 8:39:40 AM Submission request sent to Applicant
8/12/2025 8:26:15 AM Submission Triaged
8/12/2025 7:58:53 AM Submission received from Applicant
8/11/2025 4:30:00 PM Submission request sent to Applicant
8/11/2025 3:44:29 PM Request for Review Comments returned by County Attorney - Development Review
8/8/2025 11:46:10 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
8/7/2025 8:44:11 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
8/7/2025 8:44:10 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
8/7/2025 8:44:09 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
8/7/2025 8:44:08 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
8/7/2025 8:44:07 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
8/7/2025 8:44:06 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
8/7/2025 8:44:05 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
8/7/2025 8:44:04 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
8/7/2025 8:44:03 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
8/7/2025 8:44:02 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
8/7/2025 8:43:59 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
8/7/2025 8:43:58 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
8/7/2025 8:43:57 AM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
8/7/2025 8:34:18 AM Submission Triaged
8/6/2025 4:44:05 PM Submission received from Applicant
7/30/2025 4:03:04 PM Submission request sent to Applicant
7/30/2025 3:58:52 PM Request for Review Comments returned by PCD Project Manager
7/29/2025 1:47:12 PM Request for Review Comments returned by PCD Engineering Division
7/26/2025 8:54:21 AM Request for Review Comments returned by County Attorney - Development Review
7/22/2025 2:34:20 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
7/22/2025 2:34:19 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
7/22/2025 2:34:18 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
7/22/2025 2:34:17 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
7/22/2025 2:34:16 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
7/22/2025 2:34:15 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
7/22/2025 2:34:13 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
7/22/2025 2:34:12 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
7/22/2025 2:34:11 PM Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
7/22/2025 2:31:26 PM Submission Triaged
7/22/2025 9:45:13 AM Submission received from Applicant
7/1/2025 1:47:41 PM Submission request sent to Applicant
7/1/2025 1:35:30 PM Request for Review Comments returned by PCD Project Manager
7/1/2025 8:54:58 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
6/30/2025 2:14:55 PM Request for Review Comments returned by PCD Engineering Division
6/24/2025 3:41:41 PM Request for Review Comments returned by County Attorney - Development Review
6/16/2025 4:52:32 PM Request for Review Comments returned by EPC Stormwater Review
6/16/2025 12:15:25 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Steve Murphy on behalf of GMF Chipita Park Fire Protection District
6/16/2025 12:15:24 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
6/16/2025 12:15:23 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
6/16/2025 12:15:22 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
6/16/2025 12:15:21 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
6/16/2025 12:15:19 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
6/16/2025 12:15:19 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
6/16/2025 12:15:18 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
6/16/2025 12:15:16 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
6/16/2025 12:15:15 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
6/16/2025 12:15:14 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
6/16/2025 12:15:13 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
6/16/2025 12:15:12 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
6/16/2025 12:15:11 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
6/16/2025 12:15:10 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
6/16/2025 12:15:09 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
6/16/2025 12:15:08 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
6/16/2025 12:15:07 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
6/16/2025 12:15:04 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
6/16/2025 12:15:03 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
6/16/2025 12:15:02 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
6/13/2025 11:40:40 AM Submission Triaged
6/13/2025 10:33:46 AM Submission received from Applicant
6/12/2025 11:27:54 AM Submission request sent to Applicant
6/12/2025 11:27:21 AM Submission Triaged
6/11/2025 2:49:25 PM Submission received from Applicant
5/22/2025 3:59:48 PM Project Manager Assigned: Miranda Benson
5/21/2025 11:35:26 AM Submission request sent to Applicant
5/12/2025 3:33:29 PM Submission request sent to Applicant
5/12/2025 3:31:49 PM Request for Review Comments returned by PCD Project Manager
5/12/2025 3:22:36 PM Request for Review Comments email resent for Project Rockytop Campground Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
4/28/2025 3:59:20 PM Submission request sent to Applicant
4/18/2025 2:52:46 PM Submission request sent to Applicant
4/18/2025 11:27:40 AM Request for Review Comments returned by PCD Engineering Division
4/18/2025 11:21:41 AM Request for Review Comments returned by County Attorney - Development Review
4/18/2025 9:45:51 AM Request for Review Comments returned by PCD Project Manager
4/17/2025 3:59:28 PM Request for Review Comments returned by EPC Stormwater Review
4/4/2025 2:07:15 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
4/4/2025 2:07:14 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
4/4/2025 2:07:13 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
4/4/2025 2:07:12 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
4/4/2025 2:07:11 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
4/4/2025 2:07:10 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
4/4/2025 2:07:09 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
4/4/2025 2:07:08 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
4/4/2025 2:07:05 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
4/4/2025 2:07:04 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
4/4/2025 2:05:32 PM Submission Triaged
4/4/2025 1:02:54 PM Submission received from Applicant
2/12/2025 12:12:03 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
2/7/2025 12:59:01 PM Request for Review Comments returned by County Attorney - Development Review
2/6/2025 11:32:07 AM Submission request sent to Applicant
2/6/2025 11:30:59 AM Submission request sent to Applicant
2/6/2025 11:01:09 AM Request for Review Comments returned by PCD Engineering Division
2/4/2025 3:09:13 PM Request for Review Comments returned by PCD Project Manager
2/3/2025 5:04:58 PM Request for Review Comments returned by EPC Stormwater Review
1/21/2025 11:27:28 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
1/21/2025 11:27:27 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
1/21/2025 11:27:25 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
1/21/2025 11:27:24 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
1/21/2025 11:27:23 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
1/21/2025 11:27:22 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
1/21/2025 11:27:20 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
1/21/2025 11:27:19 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
1/21/2025 11:27:18 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
1/21/2025 11:27:17 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
1/21/2025 11:27:15 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
1/21/2025 11:27:14 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
1/21/2025 11:25:28 AM Submission Triaged
1/21/2025 11:19:28 AM Submission received from Applicant
1/21/2025 11:03:36 AM Submission request sent to Applicant
1/16/2025 1:46:44 PM Submission request sent to Applicant
4/17/2024 3:24:35 PM Project Manager Assigned: Ashlyn Mathy
1/23/2024 1:31:53 PM Submission request sent to Applicant
5/24/2023 2:10:12 PM Submission request sent to Applicant
5/24/2023 2:09:01 PM Submission request canceled
5/1/2023 10:36:44 AM Submission request sent to Applicant
3/14/2023 9:20:40 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
3/8/2023 3:50:16 PM Request for Review Comments returned by PCD Project Manager
3/8/2023 2:01:40 PM Submission request sent to Applicant
3/8/2023 12:37:06 PM Request for Review Comments email resent for Project Rockytop Campground Site Development Plan for review by Christian Haas on behalf of PCD Project Manager
3/8/2023 12:34:48 PM Submission Triaged
3/3/2023 12:31:12 PM Submission received from Applicant
3/3/2023 12:09:37 PM Submission request sent to Applicant
2/27/2023 8:06:11 AM Submission Triaged
2/20/2023 8:46:48 AM Submission received from Applicant
2/17/2023 3:53:06 PM Submission request sent to Applicant
2/17/2023 3:37:14 PM Submission request sent to Applicant
2/10/2023 2:52:36 PM Project Manager Assigned: Christian Haas
2/10/2023 2:52:15 PM Project Manager Assigned: Lekishia Bellamy
1/19/2023 3:24:38 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
1/18/2023 8:12:29 PM Request for Review Comments returned by PCD Project Manager
1/18/2023 5:33:54 PM Request for Review Comments returned by PCD Engineering Division
1/18/2023 3:21:37 PM Request for Review Comments returned by EPC Stormwater Review
1/12/2023 5:21:50 PM Request for Review Comments returned by County Attorney - Development Review
12/30/2022 5:36:28 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
12/30/2022 5:36:25 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
12/30/2022 5:36:24 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by HR Green EPC Consultant on behalf of PCD Project Manager
12/30/2022 5:36:22 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
12/30/2022 5:35:21 PM Submission Triaged
12/28/2022 7:45:18 AM Submission received from Applicant
12/12/2022 11:29:30 AM Submission request sent to Applicant
12/12/2022 11:23:20 AM Request for Review Comments returned by PCD Project Manager
12/10/2022 1:45:37 PM Request for Review Comments returned by Colorado Parks and Wildlife
12/8/2022 4:34:41 PM Request for Review Comments returned by PCD Engineering Division
12/8/2022 4:32:41 PM Request for Review Comments returned by EPC Stormwater Review
12/8/2022 12:45:48 PM Request for Review Comments returned by County Attorney - Development Review
12/8/2022 9:39:20 AM Request for Review Comments returned by Pikes Peak Regional Building Department
11/23/2022 8:19:35 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
11/23/2022 8:12:20 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
11/22/2022 5:24:01 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
11/22/2022 5:24:00 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
11/22/2022 5:23:59 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
11/22/2022 5:23:57 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
11/22/2022 5:23:56 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
11/22/2022 5:23:53 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
11/22/2022 5:23:52 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by HR Green EPC Consultant on behalf of PCD Project Manager
11/22/2022 5:23:50 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/22/2022 4:44:06 PM Submission Triaged
11/22/2022 8:53:05 AM Submission received from Applicant
11/9/2022 7:48:23 AM Submission request sent to Applicant
8/2/2022 8:28:43 PM Submission request sent to Applicant
7/26/2022 4:53:58 PM Submission request sent to Applicant
6/22/2022 4:51:17 PM Submission request sent to Applicant
6/22/2022 4:43:47 PM Request for Review Comments returned by PCD Project Manager
6/22/2022 9:52:03 AM Request for Review Comments returned by PCD Engineering Division
6/21/2022 11:24:33 AM Request for Review Comments returned by EPC Stormwater Review
6/1/2022 7:39:20 AM Project Manager Assigned: HR Green EPC Consultant
5/31/2022 9:14:16 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
5/31/2022 9:14:14 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
5/31/2022 9:14:12 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/31/2022 9:13:22 AM Submission Triaged
5/27/2022 3:54:51 PM Submission received from Applicant
4/12/2022 12:03:03 PM Project Manager Assigned: Ryan Howser
2/23/2022 5:30:16 PM Submission request sent to Applicant
2/23/2022 5:28:09 PM Request for Review Comments returned by PCD Project Manager
2/23/2022 5:24:49 PM Request for Review Comments email resent for Project Rockytop Campground Site Development Plan for review by John Green on behalf of PCD Project Manager
2/18/2022 9:55:37 AM Request for Review Comments returned by EPC Stormwater Review
2/17/2022 7:12:09 AM Request for Review Comments returned by PCD Project Manager
2/16/2022 10:22:01 PM Request for Review Comments returned by PCD Engineering Division
2/8/2022 12:03:18 PM Request for Review Comments returned by County Attorney - Development Review
2/1/2022 7:19:10 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
2/1/2022 7:19:06 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
2/1/2022 7:19:02 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
2/1/2022 7:19:00 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by John Green on behalf of PCD Project Manager
2/1/2022 7:18:56 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/1/2022 7:17:00 AM Submission Triaged
1/27/2022 6:58:31 PM Submission received from Applicant
10/1/2021 10:32:30 AM Submission request sent to Applicant
10/1/2021 10:31:17 AM Request for Review Comments returned by PCD Project Manager
10/1/2021 10:25:24 AM Request for Review Comments email resent for Project Rockytop Campground Site Development Plan for review by John Green on behalf of PCD Project Manager
9/30/2021 7:33:26 AM Request for Review Comments returned by EPC Stormwater Review
9/30/2021 7:24:49 AM Request for Review Comments returned by PCD Project Manager
9/29/2021 5:10:15 PM Request for Review Comments returned by PCD Engineering Division
9/28/2021 4:36:55 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
9/20/2021 11:39:45 AM Request for Review Comments returned by County Attorney - Development Review
9/15/2021 2:32:25 PM Request for Review Comments returned by Pikes Peak Regional Building Department
9/10/2021 4:39:27 PM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
9/7/2021 9:46:18 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by John Green on behalf of PCD Project Manager
9/7/2021 9:46:14 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/7/2021 8:55:36 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
9/3/2021 10:50:06 AM Request for Review Comments returned by Colorado Parks and Wildlife
9/1/2021 11:25:48 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
9/1/2021 9:23:42 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
9/1/2021 9:23:40 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Assistant Superintendent on behalf of Manitou Springs SD 14
9/1/2021 9:23:37 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Steve Murphy on behalf of GMF Chipita Park Fire Protection District
9/1/2021 9:23:35 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
9/1/2021 9:23:33 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
9/1/2021 9:23:30 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
9/1/2021 9:23:28 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
9/1/2021 9:23:26 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
9/1/2021 9:23:24 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
9/1/2021 9:23:20 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
9/1/2021 9:23:18 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
9/1/2021 9:23:10 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
9/1/2021 9:23:07 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by John Green on behalf of PCD Project Manager
9/1/2021 9:23:05 AM Request for Review Comments email sent for Project Rockytop Campground Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/19/2021 4:42:55 PM Fees paid: 8/19/2021 (Receipt: 1004969)
8/19/2021 4:13:24 PM Project Manager Assigned: John Green
8/19/2021 4:13:14 PM Payment Request sent: 8/19/2021
8/19/2021 4:13:14 PM File # Assigned: PPR2140
8/19/2021 4:13:07 PM Submission Triaged
8/19/2021 12:56:25 PM Submission received from Applicant
8/18/2021 8:28:49 PM Submission request sent to Applicant
8/18/2021 8:28:21 PM Submission Triaged
8/18/2021 7:44:07 PM Submission received from Applicant
3/3/2021 4:20:33 PM Submission request sent to Applicant
3/3/2021 9:08:22 AM Project Manager Assigned: Nina Ruiz
3/2/2021 6:50:46 PM Submission request sent to Applicant
3/2/2021 6:49:15 PM Project Manager Assigned: Tara Younger
3/2/2021 6:49:15 PM EA Assigned: EA18250
3/2/2021 6:49:15 PM Project Created