3/21/2024 10:48:36 AM
|
Fees paid: 3/21/2024 (Receipt: 1008914)
|
3/21/2024 9:11:04 AM
|
Payment Request sent: 3/21/2024
|
10/16/2023 7:47:38 AM
|
Project Closed
|
10/16/2023 7:47:38 AM
|
Project Approved: 10/16/2023
|
10/9/2023 4:18:52 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
10/9/2023 4:08:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/9/2023 12:24:11 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/9/2023 7:10:23 AM
|
Submission Triaged
|
10/6/2023 9:37:19 AM
|
Submission received from Applicant
|
10/2/2023 11:36:11 AM
|
Submission request sent to Applicant
|
9/21/2023 10:02:44 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/21/2023 7:28:45 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/21/2023 7:28:42 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
9/21/2023 7:28:40 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
9/21/2023 7:28:40 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
9/21/2023 7:27:10 AM
|
Submission Triaged
|
9/20/2023 5:11:29 PM
|
Submission received from Applicant
|
9/6/2023 1:23:19 PM
|
Submission request sent to Applicant
|
9/6/2023 12:02:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
8/30/2023 1:08:51 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/15/2023 8:35:21 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by April Willie on behalf of County Attorney - Water
|
8/15/2023 8:33:46 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
8/15/2023 8:33:43 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
8/15/2023 8:33:42 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
8/15/2023 8:32:19 AM
|
Submission Triaged
|
8/15/2023 7:33:03 AM
|
Submission received from Applicant
|
6/21/2023 1:58:42 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
6/15/2023 12:30:31 PM
|
Request for Review Comments returned by County Attorney - Water
|
6/14/2023 4:30:08 PM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
6/8/2023 8:31:33 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/7/2023 4:07:54 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
6/6/2023 2:01:28 PM
|
Submission request sent to Applicant
|
6/6/2023 1:57:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/6/2023 1:55:37 PM
|
Request for Review Comments email resent for Project Copper Chase at Sterling Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
6/6/2023 1:41:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/6/2023 1:27:54 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/5/2023 8:12:56 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
6/2/2023 10:39:13 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
5/31/2023 1:28:56 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
5/30/2023 9:28:10 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/23/2023 3:03:48 PM
|
Request for Review Comments returned by Parks Advisory Board
|
5/23/2023 3:01:55 PM
|
Request for Review Comments returned by EPC Parks Department
|
5/18/2023 7:49:17 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/17/2023 2:21:22 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
5/17/2023 10:58:32 AM
|
Request for Review Comments returned by US Postal Service
|
5/16/2023 2:24:22 PM
|
Request for Review Comments returned by EPC Environmental Services
|
5/16/2023 9:36:16 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/16/2023 7:03:58 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
5/16/2023 6:21:12 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/15/2023 4:16:04 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
5/15/2023 4:16:03 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/15/2023 4:16:02 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
5/15/2023 4:15:59 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Melissa Andrews on behalf of Falcon School District 49
|
5/15/2023 4:15:58 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
5/15/2023 4:15:57 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/15/2023 4:15:53 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
5/15/2023 4:15:52 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
5/15/2023 4:15:49 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Airport Planner Tyler Hardman on behalf of Colorado Springs Airport Advisory Commission
|
5/15/2023 4:15:46 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/15/2023 4:15:45 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
5/15/2023 4:15:43 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
5/15/2023 4:15:42 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
5/15/2023 4:15:41 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
5/15/2023 4:15:40 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/15/2023 4:15:38 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/15/2023 4:15:37 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Rita Otega on behalf of US Postal Service
|
5/15/2023 4:15:36 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
5/15/2023 4:15:35 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
5/15/2023 4:15:33 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
5/15/2023 4:15:30 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
5/15/2023 4:15:27 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
5/15/2023 4:15:26 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of Parks Advisory Board
|
5/15/2023 4:15:24 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/15/2023 4:15:21 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
5/15/2023 4:15:20 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of EPC Parks Department
|
5/15/2023 4:15:19 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Catherine McGarvy on behalf of EPC Health Department
|
5/15/2023 4:15:15 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/15/2023 4:15:12 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Edi Anderson on behalf of County Attorney - Water
|
5/15/2023 4:15:09 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kari Parsons on behalf of PCD Project Manager
|
5/15/2023 4:15:07 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/15/2023 4:02:41 PM
|
Submission Triaged
|
5/15/2023 3:35:39 PM
|
Submission received from Applicant
|
1/6/2023 1:15:37 PM
|
Request for Review Comments returned by EPC Health Department
|
11/17/2022 11:03:17 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
11/15/2022 8:13:43 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
11/15/2022 7:48:05 AM
|
Submission request sent to Applicant
|
11/15/2022 7:42:44 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/14/2022 3:14:39 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
11/14/2022 1:44:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/9/2022 9:54:22 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
11/8/2022 8:11:30 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
11/7/2022 2:20:29 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/7/2022 11:57:45 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
11/7/2022 11:19:07 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/3/2022 2:59:59 PM
|
Request for Review Comments returned by County Attorney - Water
|
11/3/2022 8:13:17 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/25/2022 8:04:55 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/24/2022 3:11:02 PM
|
Request for Review Comments returned by EPC Environmental Services
|
10/24/2022 1:43:03 PM
|
Request for Review Comments returned by US Postal Service
|
10/19/2022 12:02:12 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/19/2022 11:07:22 AM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
10/19/2022 10:53:18 AM
|
Request for Review Comments returned by EPC Parks Department
|
10/19/2022 10:52:25 AM
|
Request for Review Comments returned by Parks Advisory Board
|
10/19/2022 6:49:01 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
10/19/2022 6:22:44 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/18/2022 4:29:26 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
10/18/2022 4:29:25 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by General Email on behalf of Mountain View Electric Association, Inc.
|
10/18/2022 4:29:23 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
10/18/2022 4:29:22 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Melissa Andrews on behalf of Falcon School District 49
|
10/18/2022 4:29:21 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/18/2022 4:29:20 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/18/2022 4:29:16 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
10/18/2022 4:29:15 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
10/18/2022 4:29:13 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Airport Planner Tyler Hardman on behalf of Colorado Springs Airport Advisory Commission
|
10/18/2022 4:29:11 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
10/18/2022 4:29:10 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
10/18/2022 4:29:09 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
10/18/2022 4:29:08 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
10/18/2022 4:29:06 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/18/2022 4:29:05 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/18/2022 4:29:03 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/18/2022 4:29:02 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Rita Otega on behalf of US Postal Service
|
10/18/2022 4:29:01 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
10/18/2022 4:28:59 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
10/18/2022 4:28:57 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
10/18/2022 4:28:54 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
10/18/2022 4:28:51 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
10/18/2022 4:28:50 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of Parks Advisory Board
|
10/18/2022 4:28:48 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/18/2022 4:28:46 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
10/18/2022 4:28:45 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of EPC Parks Department
|
10/18/2022 4:28:44 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Catherine McGarvy on behalf of EPC Health Department
|
10/18/2022 4:28:40 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/18/2022 4:28:38 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Edi Anderson on behalf of County Attorney - Water
|
10/18/2022 4:28:36 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kari Parsons on behalf of PCD Project Manager
|
10/18/2022 4:28:34 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/18/2022 4:25:30 PM
|
Submission Triaged
|
10/18/2022 4:03:18 PM
|
Submission received from Applicant
|
6/20/2022 3:14:43 PM
|
Submission request sent to Applicant
|
6/9/2022 3:34:35 PM
|
Request for Review Comments returned by Parks Advisory Board
|
6/9/2022 12:56:57 PM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of Parks Advisory Board
|
5/24/2022 4:18:30 PM
|
Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
5/3/2022 11:55:40 AM
|
Submission request sent to Applicant
|
5/3/2022 11:50:10 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/3/2022 11:27:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/3/2022 9:39:31 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
4/28/2022 4:51:47 PM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
4/27/2022 11:04:27 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/26/2022 1:10:40 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/25/2022 1:40:00 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/25/2022 10:00:46 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
4/25/2022 9:53:40 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/25/2022 8:15:52 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
4/19/2022 2:26:10 PM
|
Request for Review Comments returned by EPC Parks Department
|
4/15/2022 4:07:07 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
4/11/2022 9:55:10 AM
|
Request for Review Comments returned by EPC Environmental Services
|
4/11/2022 9:31:25 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
4/7/2022 4:16:32 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
4/7/2022 9:38:36 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
4/4/2022 3:07:01 PM
|
Fees paid: 4/4/2022 (Receipt: 1006105)
|
4/4/2022 1:12:04 PM
|
Request for Review Comments returned by US Postal Service
|
4/4/2022 12:40:25 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
4/4/2022 11:29:58 AM
|
Request for Review Comments returned by County Attorney - Water
|
4/4/2022 11:24:19 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
4/4/2022 11:24:17 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/4/2022 11:24:16 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
4/4/2022 11:24:15 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Melissa Andrews on behalf of Falcon School District 49
|
4/4/2022 11:24:14 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
4/4/2022 11:24:13 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
4/4/2022 11:24:11 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
4/4/2022 11:24:10 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
4/4/2022 11:24:08 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Airport Planner Tyler Hardman on behalf of Colorado Springs Airport Advisory Commission
|
4/4/2022 11:24:06 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
4/4/2022 11:24:03 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
4/4/2022 11:24:01 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
4/4/2022 11:24:00 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
4/4/2022 11:23:59 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
4/4/2022 11:23:58 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
4/4/2022 11:23:56 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
4/4/2022 11:23:55 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Rita Otega on behalf of US Postal Service
|
4/4/2022 11:23:53 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
4/4/2022 11:23:52 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
4/4/2022 11:23:51 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
4/4/2022 11:23:48 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
4/4/2022 11:23:47 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
4/4/2022 11:23:46 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/4/2022 11:23:45 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
4/4/2022 11:23:44 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by on behalf of EPC Parks Department
|
4/4/2022 11:23:42 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Catherine McGarvy on behalf of EPC Health Department
|
4/4/2022 11:23:38 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kathy Andrew on behalf of EPC Environmental Services
|
4/4/2022 11:23:37 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Edi Anderson on behalf of County Attorney - Water
|
4/4/2022 11:23:36 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Kari Parsons on behalf of PCD Project Manager
|
4/4/2022 11:23:35 AM
|
Request for Review Comments email sent for Project Copper Chase at Sterling Ranch I for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/4/2022 11:13:04 AM
|
Payment Request sent: 4/4/2022
|
4/4/2022 11:12:39 AM
|
Submission Triaged
|
4/4/2022 10:45:23 AM
|
Submission received from Applicant
|
4/4/2022 8:38:05 AM
|
Submission request sent to Applicant
|
4/4/2022 8:36:35 AM
|
Submission request sent to Applicant
|
4/4/2022 8:34:59 AM
|
File # Assigned: PUDSP222
|
4/4/2022 8:34:37 AM
|
Submission request sent to Applicant
|
4/4/2022 8:27:36 AM
|
Submission Triaged
|
4/4/2022 8:16:39 AM
|
Project Manager Assigned: Kari Parsons
|
4/1/2022 3:40:23 PM
|
Submission received from Applicant
|
3/22/2022 5:29:15 PM
|
Project Manager Assigned: John Green
|
3/22/2022 4:43:07 PM
|
Submission request sent to Applicant
|
3/1/2022 4:56:55 PM
|
Project Reopened
|
2/28/2022 3:21:06 PM
|
Project Deleted
|
11/16/2021 2:14:58 PM
|
Set Applicant to N.E.S.
|
10/15/2021 11:39:23 AM
|
Submission request sent to Applicant
|
10/12/2021 8:38:29 AM
|
Submission request sent to Applicant
|
10/12/2021 8:36:57 AM
|
Submission request sent to Applicant
|
10/12/2021 8:35:38 AM
|
Submission request sent to Applicant
|
7/27/2021 3:19:11 PM
|
Submission request sent to Applicant
|
7/27/2021 3:09:34 PM
|
Submission request sent to Applicant
|
11/18/2020 1:43:21 PM
|
Submission request sent to Applicant
|
11/18/2020 1:04:02 PM
|
Project Manager Assigned: Kari Parsons
|
11/18/2020 1:04:02 PM
|
Project Created
|