7/1/2025 9:16:17 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
6/5/2025 2:29:18 PM
|
Submission request sent to Applicant
|
6/5/2025 11:20:32 AM
|
Request for Review Comments returned by County Attorney - Water
|
6/5/2025 11:17:39 AM
|
Request for Review Comments returned by EPC Fire and Wildfire Program Manager
|
6/4/2025 8:54:20 AM
|
Request for Review Comments email resent for Project Canyon Creek Ranch for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
|
6/4/2025 8:33:22 AM
|
Request for Review Comments returned by EPC Fire and Wildfire Program Manager
|
6/3/2025 3:54:08 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/3/2025 3:53:16 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/3/2025 2:30:02 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/3/2025 9:57:09 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/3/2025 9:34:02 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
|
6/3/2025 9:21:33 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
6/3/2025 9:21:32 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
5/30/2025 8:51:57 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/22/2025 8:27:10 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/21/2025 9:20:35 AM
|
Request for Review Comments returned by EPC Environmental Services
|
5/20/2025 8:19:32 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by on behalf of Pikes Peak Regional Building Department
|
5/20/2025 8:19:31 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/20/2025 8:19:30 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
5/20/2025 8:19:29 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
5/20/2025 8:19:27 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
5/20/2025 8:19:26 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Glenn Reese on behalf of EPC Stormwater Review
|
5/20/2025 8:19:25 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Christina Prete on behalf of EPC Stormwater Review
|
5/20/2025 8:19:24 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/20/2025 8:19:23 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Lori Seago on behalf of County Attorney - Water
|
5/20/2025 8:19:22 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Erika Keech on behalf of County Attorney - Water
|
5/20/2025 8:19:21 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by April Willie on behalf of County Attorney - Water
|
5/20/2025 8:19:20 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Lori Seago on behalf of County Attorney - Development Review
|
5/20/2025 8:19:19 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Erika Keech on behalf of County Attorney - Development Review
|
5/20/2025 8:19:18 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by April Willie on behalf of County Attorney - Development Review
|
5/20/2025 8:19:16 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Justin Kilgore on behalf of PCD Project Manager
|
5/20/2025 8:19:13 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/20/2025 8:19:13 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Engineering Manager on behalf of PCD Engineering Division
|
5/20/2025 8:17:20 AM
|
Submission Triaged
|
5/19/2025 5:18:22 PM
|
Submission received from Applicant
|
2/7/2025 3:31:31 PM
|
Submission request sent to Applicant
|
2/7/2025 12:15:55 PM
|
Request for Review Comments returned by County Attorney - Water
|
2/5/2025 7:09:41 AM
|
Submission request sent to Applicant
|
2/4/2025 11:18:40 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/31/2025 12:25:14 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/31/2025 10:52:26 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/30/2025 5:21:53 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/30/2025 3:50:27 PM
|
Request for Review Comments returned by RBD Floodplain
|
1/30/2025 3:48:57 PM
|
Request for Review Comments email resent for Project Canyon Creek Ranch for review by Keith Curtis on behalf of RBD Floodplain
|
1/30/2025 3:44:45 PM
|
Request for Review Comments returned by RBD Floodplain
|
1/30/2025 3:41:52 PM
|
Request for Review Comments email resent for Project Canyon Creek Ranch for review by Keith Curtis on behalf of RBD Floodplain
|
1/30/2025 9:56:25 AM
|
Request for Review Comments returned by RBD Floodplain
|
1/30/2025 9:37:33 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Keith Curtis on behalf of RBD Floodplain
|
1/27/2025 9:35:28 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/21/2025 9:05:53 AM
|
Request for Review Comments returned by EPC Environmental Services
|
1/13/2025 12:48:47 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
1/10/2025 4:58:16 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by on behalf of Black Forest Fire Protection District
|
1/10/2025 4:58:15 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by on behalf of Pikes Peak Regional Building Department
|
1/10/2025 4:58:14 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
1/10/2025 4:58:13 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
1/10/2025 4:58:12 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/10/2025 4:58:11 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/10/2025 4:58:10 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Christina Prete on behalf of EPC Stormwater Review
|
1/10/2025 4:58:09 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Kathy Andrew on behalf of EPC Environmental Services
|
1/10/2025 4:58:08 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Lori Seago on behalf of County Attorney - Development Review
|
1/10/2025 4:58:07 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Erika Keech on behalf of County Attorney - Development Review
|
1/10/2025 4:58:06 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by April Willie on behalf of County Attorney - Development Review
|
1/10/2025 4:58:04 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Justin Kilgore on behalf of PCD Project Manager
|
1/10/2025 4:58:01 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/10/2025 4:58:00 PM
|
Request for Review Comments email sent for Project Canyon Creek Ranch for review by Engineering Manager on behalf of PCD Engineering Division
|
1/10/2025 4:55:49 PM
|
Submission Triaged
|
1/10/2025 2:20:27 PM
|
Submission received from Applicant
|
1/2/2025 9:27:56 AM
|
File # Assigned: SF2440
|
1/2/2025 9:26:42 AM
|
File # Assigned: SF2436
|
12/17/2024 4:53:01 PM
|
Submission request sent to Applicant
|
12/12/2024 10:55:37 AM
|
Submission request sent to Applicant
|
12/12/2024 10:55:06 AM
|
Project reopened for Review Comments
|
12/12/2024 10:54:40 AM
|
File # Assigned: SF2434
|
12/12/2024 10:01:25 AM
|
Set Applicant to William Guman & Associates, Ltd.
|
12/4/2024 7:41:17 AM
|
Project Closed
|
12/4/2024 7:41:17 AM
|
Project Cancelled: 12/4/2024
|
8/11/2023 3:05:51 PM
|
Submission request sent to Applicant
|
3/10/2023 1:33:54 PM
|
Request for Review Comments returned by EPC Health Department
|
3/6/2023 4:21:16 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
3/2/2023 4:32:57 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
3/1/2023 11:13:09 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
2/28/2023 2:59:26 PM
|
Submission request sent to Applicant
|
2/28/2023 2:49:30 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/28/2023 11:05:03 AM
|
Request for Review Comments returned by PCD Engineering Division
|
2/25/2023 9:13:31 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
2/23/2023 1:31:18 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
2/23/2023 9:19:58 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
2/22/2023 12:50:58 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/21/2023 12:14:56 PM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
2/16/2023 4:34:08 PM
|
Request for Review Comments returned by Parks Advisory Board
|
2/16/2023 4:33:16 PM
|
Request for Review Comments returned by EPC Parks Department
|
2/13/2023 3:17:38 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
2/13/2023 7:43:30 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
2/10/2023 1:11:13 PM
|
Request for Review Comments returned by Colorado State Forest Service
|
2/7/2023 12:32:00 PM
|
Request for Review Comments returned by EPC Environmental Services
|
2/3/2023 7:40:31 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
2/2/2023 7:30:18 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by General Email on behalf of Mountain View Electric Association, Inc.
|
2/2/2023 7:30:16 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
2/2/2023 7:30:15 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Supervisor Bob Swatek on behalf of Black Hills Energy-Aquila
|
2/2/2023 7:30:13 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
2/2/2023 7:30:11 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
2/2/2023 7:30:09 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
2/2/2023 7:30:07 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
2/2/2023 7:30:05 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
2/2/2023 7:30:03 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
2/2/2023 7:30:01 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
|
2/2/2023 7:29:59 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
2/2/2023 7:29:57 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
2/2/2023 7:29:56 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
2/2/2023 7:29:54 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
2/2/2023 7:29:50 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
2/2/2023 7:29:48 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
2/2/2023 7:29:46 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by on behalf of Parks Advisory Board
|
2/2/2023 7:29:45 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
2/2/2023 7:29:43 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by on behalf of EPC Parks Department
|
2/2/2023 7:29:41 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Catherine McGarvy on behalf of EPC Health Department
|
2/2/2023 7:29:36 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Kathy Andrew on behalf of EPC Environmental Services
|
2/2/2023 7:29:34 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Edi Anderson on behalf of County Attorney - Water
|
2/2/2023 7:29:32 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Lori Seago on behalf of County Attorney - Development Review
|
2/2/2023 7:29:30 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Ryan Howser on behalf of PCD Project Manager
|
2/2/2023 7:29:28 AM
|
Request for Review Comments email sent for Project Canyon Creek Ranch MS for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/26/2023 10:01:34 AM
|
Fees paid: 1/26/2023 (Receipt: 1007366)
|
12/28/2022 3:00:51 PM
|
Payment Request sent: 12/28/2022
|
12/28/2022 3:00:51 PM
|
File # Assigned: MS2213
|
12/28/2022 3:00:46 PM
|
Submission Triaged
|
12/22/2022 11:49:00 AM
|
Submission received from Applicant
|
12/17/2021 3:36:03 PM
|
Submission request sent to Applicant
|
4/2/2021 11:56:21 AM
|
EA Assigned: EA20126
|
3/24/2021 2:14:22 PM
|
Project Manager Assigned: Ryan Howser
|
12/9/2020 10:07:52 AM
|
Submission request sent to Applicant
|
12/7/2020 4:58:42 PM
|
Project Manager Assigned: Nina Ruiz
|
11/5/2020 10:20:10 AM
|
Project Manager Assigned: Rad Dickson
|
11/5/2020 10:20:10 AM
|
Project Created
|