3/28/2025 7:38:07 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
3/26/2025 12:34:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/20/2025 8:36:45 AM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
3/20/2025 7:36:43 AM
|
Submission Triaged
|
3/19/2025 3:05:46 PM
|
Submission received from Applicant
|
3/14/2025 12:37:35 PM
|
Submission request sent to Applicant
|
3/14/2025 12:27:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/4/2025 9:47:43 AM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
3/4/2025 9:46:56 AM
|
Submission Triaged
|
3/2/2025 6:35:22 PM
|
Submission received from Applicant
|
4/17/2024 4:08:01 PM
|
Submission request sent to Applicant
|
4/15/2024 9:14:50 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/12/2024 10:05:50 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/10/2024 6:18:22 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/29/2024 4:26:30 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/29/2024 4:26:28 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/29/2024 4:26:26 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
3/29/2024 4:26:22 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Kari Parsons on behalf of PCD Project Manager
|
3/29/2024 4:26:20 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/29/2024 4:26:17 PM
|
Request for Review Comments email sent for Project Viewpoint Estates Filing No. 2 Preliminary Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
3/29/2024 4:23:23 PM
|
Submission Triaged
|
3/29/2024 2:52:15 PM
|
Submission received from Applicant
|
2/8/2024 3:50:57 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
2/1/2024 11:54:43 AM
|
Submission request sent to Applicant
|
2/1/2024 11:54:26 AM
|
Submission Triaged
|
1/26/2024 9:50:26 AM
|
Submission received from Applicant
|
1/23/2024 5:14:18 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
1/23/2024 5:14:16 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
1/23/2024 5:14:14 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
1/23/2024 5:14:12 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
1/19/2024 1:14:01 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
1/17/2024 4:28:50 PM
|
Submission request sent to Applicant
|
1/17/2024 4:26:04 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/17/2024 3:08:36 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/17/2024 10:43:50 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/10/2024 9:28:07 AM
|
Request for Review Comments returned by County Attorney - Water
|
1/8/2024 10:12:02 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
1/3/2024 1:37:42 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Mark Stanwood on behalf of Ellicott Fire Protection District
|
1/3/2024 1:37:40 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Michael Henley on behalf of Ellicott Fire Protection District
|
1/3/2024 1:37:38 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
1/3/2024 1:37:37 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
1/3/2024 1:37:34 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/3/2024 1:37:33 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/3/2024 1:37:31 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Christina Prete on behalf of EPC Stormwater Review
|
1/3/2024 1:37:29 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Lori Seago on behalf of County Attorney - Water
|
1/3/2024 1:37:27 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by April Willie on behalf of County Attorney - Water
|
1/3/2024 1:37:23 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/3/2024 1:37:19 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan (Minor) for review by Engineering Manager on behalf of PCD Engineering Division
|
1/3/2024 1:19:24 PM
|
Submission Triaged
|
1/3/2024 12:10:39 PM
|
Submission received from Applicant
|
4/21/2023 5:14:21 PM
|
Request for Review Comments returned by EPC Health Department
|
4/4/2023 9:30:15 AM
|
Submission request sent to Applicant
|
4/4/2023 9:29:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/4/2023 9:28:55 AM
|
Request for Review Comments email resent for Project Viewpoint Estates - Preliminary Plan for review by Ryan Howser on behalf of PCD Project Manager
|
4/3/2023 9:12:55 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/30/2023 7:28:02 AM
|
Submission request sent to Applicant
|
3/30/2023 7:26:48 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/29/2023 2:54:56 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/29/2023 11:28:14 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
3/29/2023 10:43:13 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Richard Cromwell on behalf of Ellicott Utilities (does area that was Sunset Metro)
|
3/21/2023 8:59:43 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/9/2023 1:29:05 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
3/8/2023 12:04:50 PM
|
Request for Review Comments returned by County Attorney - Water
|
3/8/2023 10:43:45 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Michael Henley on behalf of Ellicott Fire Protection District
|
3/8/2023 10:43:41 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/8/2023 10:43:39 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/8/2023 10:43:36 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
3/8/2023 10:43:27 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Edi Anderson on behalf of County Attorney - Water
|
3/8/2023 10:43:26 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Ryan Howser on behalf of PCD Project Manager
|
3/8/2023 10:43:24 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/8/2023 10:40:22 AM
|
Submission Triaged
|
3/7/2023 9:03:21 AM
|
Submission received from Applicant
|
1/12/2022 3:44:00 PM
|
Request for Review Comments returned by Parks Advisory Board
|
1/5/2022 6:03:57 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
1/4/2022 3:47:51 PM
|
Project Manager Assigned: Ryan Howser
|
1/3/2022 8:58:06 AM
|
Request for Review Comments returned by EPC Parks Department
|
1/3/2022 8:47:18 AM
|
Submission request sent to Applicant
|
1/3/2022 8:42:46 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/29/2021 12:02:05 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
12/26/2021 4:35:32 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
12/22/2021 3:06:37 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
12/22/2021 10:41:45 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/22/2021 10:03:01 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/22/2021 7:31:46 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/21/2021 12:35:04 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/20/2021 12:50:49 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
12/16/2021 3:59:26 PM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
12/6/2021 2:54:24 PM
|
Request for Review Comments returned by EPC Environmental Services
|
12/6/2021 8:56:12 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
12/3/2021 8:42:00 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/2/2021 1:04:51 PM
|
Request for Review Comments returned by County Attorney - Water
|
12/2/2021 12:41:57 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
12/2/2021 10:50:47 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
12/1/2021 11:52:02 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
12/1/2021 10:38:54 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
12/1/2021 10:38:52 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Lisa Johnson on behalf of Ellicott Town Center Metropolitan District
|
12/1/2021 10:38:50 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Chris Smith on behalf of Ellicott SD 22
|
12/1/2021 10:38:47 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Michael Henley on behalf of Ellicott Fire Protection District
|
12/1/2021 10:38:45 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
12/1/2021 10:38:43 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
12/1/2021 10:38:41 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/1/2021 10:38:36 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
12/1/2021 10:38:33 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
12/1/2021 10:38:30 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
12/1/2021 10:38:18 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
12/1/2021 10:38:14 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
12/1/2021 10:38:09 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
12/1/2021 10:37:56 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by on behalf of Parks Advisory Board
|
12/1/2021 10:37:53 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/1/2021 10:37:48 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
12/1/2021 10:37:45 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
12/1/2021 10:37:42 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by on behalf of EPC Parks Department
|
12/1/2021 10:37:40 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
12/1/2021 10:37:28 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
12/1/2021 10:37:26 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Edi Anderson on behalf of County Attorney - Water
|
12/1/2021 10:37:23 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
12/1/2021 10:37:20 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
12/1/2021 10:37:17 AM
|
Request for Review Comments email sent for Project Viewpoint Estates - Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/23/2021 9:56:17 AM
|
Fees paid: 11/23/2021 (Receipt: 1005422)
|
11/22/2021 9:20:42 PM
|
Project Manager Assigned: Mercedes Rivas
|
11/22/2021 9:20:25 PM
|
Payment Request sent: 11/22/2021
|
11/22/2021 9:20:25 PM
|
File # Assigned: SP215
|
11/22/2021 9:20:16 PM
|
Submission Triaged
|
11/19/2021 3:38:27 PM
|
Submission received from Applicant
|
11/16/2021 4:56:10 PM
|
Submission request sent to Applicant
|
11/16/2021 4:54:59 PM
|
Project Manager Assigned: Nina Ruiz
|
8/21/2020 4:50:54 PM
|
Submission request sent to Applicant
|
8/21/2020 4:38:35 PM
|
Submission request sent to Applicant
|
4/14/2020 4:21:47 PM
|
Submission request sent to Applicant
|
4/14/2020 4:06:58 PM
|
Submission request sent to Applicant
|
4/14/2020 3:11:38 PM
|
Project Manager Assigned: Gabe Sevigny
|
4/14/2020 3:11:38 PM
|
EA Assigned: EA19218
|
4/14/2020 3:11:38 PM
|
Project Created
|