Project Details
Search |
All Active Projects
-
File Number
-
CON1942
-
Project Name
-
Monument Academy Site Development Plan
-
Description
-
Site Development Plan for proposed Charter School
-
Parcels
-
6100000245
6100000245
-
Applicant
-
JPS Engineering, Inc.
John Schwab ( john@jpsengr.com )
(719) 477-9429
John Schwab ( john@jpsengr.com )
(719) 477-9429
-
File Prefix
-
CON - Construction Permit
-
Year
-
2019
-
Project Manager
-
Spencer Pirzadeh
-
Status
-
Active
-
Created
-
8/12/2019 8:06:16 AM
View:
Review Comments
Additional Documents (3)
Link
|
Document
|
Comment
|
Date
|
View
|
Engineering Comments of As Built drawings. 3-23
|
|
3/14/2023 8:55:29 AM
|
View
|
Stormwater Punchlist PA
|
|
10/7/2024 2:39:54 PM
|
View
|
PA Punchlist
|
4/28/2025
|
4/28/2025 5:09:44 PM
|
Review Documents (14)
Link
|
Document
|
Date
|
View
|
Approved CD's
|
12/28/2020 11:11:30 AM
|
View
|
Approved Final Drainage Report
|
12/28/2020 11:11:27 AM
|
View
|
Approved GEC
|
2/3/2022 2:38:22 PM
|
View
|
Approved Pavement Design
|
12/28/2020 11:11:27 AM
|
View
|
Approved Sign & Striping
|
2/22/2021 4:10:14 PM
|
View
|
As Built
|
2/9/2023 5:06:57 PM
|
View
|
con permit
|
1/29/2020 9:34:16 AM
|
View
|
Email from JPS
|
8/13/2020 4:28:16 PM
|
View
|
FAE Reduction Request
|
4/13/2021 12:26:18 PM
|
View
|
Landscape Plans
|
12/28/2020 11:11:29 AM
|
View
|
Lighting Plans
|
12/28/2020 11:11:30 AM
|
View
|
Pond Cert
|
2/27/2023 10:23:08 AM
|
View
|
Pond Survey
|
2/9/2023 5:07:00 PM
|
View
|
Street Cert
|
3/21/2023 3:55:35 PM
|
Events (19)
Date
|
Comment
|
3/22/2023 8:22:38 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/21/2023 6:04:18 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/27/2023 10:24:58 AM
|
Request for Review Comments email sent for Project Monument Academy Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
2/27/2023 10:24:57 AM
|
Request for Review Comments email sent for Project Monument Academy Site Development Plan for review by Brad Walters on behalf of PCD Engineering Inspections
|
2/27/2023 10:24:55 AM
|
Request for Review Comments email sent for Project Monument Academy Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/13/2023 9:59:36 AM
|
Submission Triaged
|
2/9/2023 5:07:36 PM
|
Submission received from Applicant
|
1/4/2023 3:21:03 PM
|
Submission request sent to Applicant
|
1/4/2023 3:20:27 PM
|
Set Applicant to JPS Engineering, Inc.
|
1/4/2023 10:31:14 AM
|
Submission request sent to Applicant
|
1/4/2023 10:27:57 AM
|
Fees paid: 1/4/2023 (Receipt: 1007309)
|
11/16/2022 7:18:19 AM
|
Project Manager Assigned: Spencer Pirzadeh
|
8/31/2022 7:50:47 AM
|
Project Manager Assigned: Natasha Grimaldo
|
10/18/2021 1:56:25 PM
|
Project Manager Assigned: Alyssa Cumbie
|
11/10/2020 4:36:17 PM
|
Project Manager Assigned: Rick Spears
|
11/10/2020 4:36:05 PM
|
Project Manager Assigned: Brad Walters
|
8/12/2019 8:06:25 AM
|
File # Assigned: CON1942
|
8/12/2019 8:06:18 AM
|
Project Manager Assigned: Matt Arcidiacono
|
8/12/2019 8:06:18 AM
|
Project Created. Parent Project: Monument Academy Site Development Plan (PPR199)
|