Project Review Comments

Back to List


File Number
U262
Project Name
6365 E Platte Ave - Conversion to Fire District Bldg
Description
Applicants are proposing a conversion of the building from a private office/warehouse development to a governmental Fire Marshal Division & Fire Training Center.
Parcels
5418001005 5418001005
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
File Number
U262
Project Manager
Lacey Dean
Status
Active
Created
10/1/2026 10:23:34 AM

View: Project Documents



Review Comments (14)

Link Agency Review # Comment
EPC DPW Development Services - Engineering
10/21/2026 9:09:15 AM
2 Engineering Review Ver.2

No further engineering comments on the Approval of location.
A traffic conformance memo will be needed with the pending Site Development Plan application

Note EPC Road Impact fees will be applicable to the new use.
Previous EPC RIF fees paid for the Warehouse use were $19,964.46
New use will be Institutional $2371/1000sqft EPC RIF $40,307.00
A credit is given for the prior fees paid.
EPC RIF fees to be paid prior to SDP approval will be $20,612.54

Thank you.


Edward Schoenheit, Engineer
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
edwardschoenheit@elpasoco.com
https://publicworks.elpasoco.com/department-public-works/county-engineer/
10/21/2026 9:09:15 AM
View Cherokee Metro District
10/20/2026 2:30:50 PM
1 The utility plans for this development have been approved and construction is finished.

No conflict with Cherokee Metro District in having this converted to Fire District building
10/20/2026 2:30:50 PM
PCD Project Manager
10/20/2026 11:55:53 AM
2 Review 2: EPC Planning Division has no more comments.

Staff will prepare reports and presentations for Planning Commission hearing on 11/5.

The applicant is encouraged to prepare a presentation as well.

Reviewed by:
Lacey Dean, Planner
laceydean2@elpasoco.com
10/20/2026 11:55:53 AM
View PCD Project Manager
10/14/2026 8:05:00 PM
1 V2_Plot Plan Drawings_comments 10/14/2026 8:05:00 PM
View PCD Project Manager
10/14/2026 8:04:23 PM
1 V2_Letter of Intetn_comments 10/14/2026 8:04:23 PM
View PCD Project Manager
10/14/2026 8:03:20 PM
1 V1_Application-Petition Form_comments 10/14/2026 8:03:20 PM
PCD Project Manager
10/14/2026 8:02:18 PM
1 Review 1: EPC Planning Division has comments in green text boxes on the following documents.

- Application/Petition Form
- Letter of Intent
- Plot Plan Drawings

Reviewed by:
Lacey Dean, Planner
laceydean2@elpasoco.com
10/14/2026 8:02:18 PM
EPC DPW Stormwater
10/14/2026 8:27:11 AM
1 Review 1: EPC DPW Stormwater has no comments on this approval of location application. With the subsequent PPR, please at that time address the site changes and if that will have any impact on the existing sand filter basin and overall site water quality.

Project Manager: no re-review necessary

Reviewed by:
Mikayla Hartford, P.E.
Senior Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
10/14/2026 8:27:11 AM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/14/2026 8:25:56 AM
1 See uploaded document for comments 10/14/2026 8:25:56 AM
View Colorado Department of Transportation - Pueblo Office
10/13/2026 7:23:08 AM
1 Comment letter attached 10/13/2026 7:23:08 AM
Colorado Springs Public Works
10/12/2026 9:36:26 AM
1 EDRD has no comments on this item.

Reviewed by Hao Vo,
hao.vo@coloradosprings.gov
10/12/2026 9:36:26 AM
View EPC Environmental Services
10/9/2026 12:14:46 PM
1 10/9/2026 12:14:46 PM
Colorado Springs Public Works
10/8/2026 10:45:57 AM
1 Traffic Engineering has no comments on this item.

Zaker Alazzeh, P.E.
Traffic Engineering Manager/Deputy City Traffic Engineer
City of Colorado Springs
(719) 385-5468
Zaker.Alazzeh@coloradosprings.gov
10/8/2026 10:45:57 AM
EPC DPW Development Services - Engineering
10/7/2026 2:04:02 PM
1 Engineering Review Ver.1

Please see comments on the following review documents

LOI_V1

Note EPC Road Impact fees will be applicable to the new use.
Previous EPC RIF fees paid for the Warehouse use were $19,964.46
New use will be Institutional $2371/1000sqft EPC RIF $40,307.00
A credit is given for the prior fees paid.
EPC RIF fees to be paid prior to SDP approval will be $20,612.54

Thank you.


Edward Schoenheit, Engineer
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
edwardschoenheit@elpasoco.com
https://publicworks.elpasoco.com/department-public-works/county-engineer/