Project Review Comments

Back to List


File Number
PAV265
Project Name
Rising Moon Filing No. 1
Description
phase 1 of final plat post preliminary plan. preliminary plan must be approved first.
Parcels
5503101010 5503101010
Applicant
Classic Consulting Engineers & Surveyors, LLC
Keith Cerjan ( kcerjan@classicconsulting.net )
(719) 785-2804
Keith Cerjan ( kcerjan@classicconsulting.net )
(719) 785-2804
File Number
PAV265
Project Manager
Bret Dilts
Status
Active
Created
4/20/2026 1:56:11 PM

View: Project Documents



Review Comments (1)

Link Agency Review # Comment
EPC DPW Development Services - Engineering
4/28/2026 9:17:02 AM
1 PAV265: Rising Moon Filing No. 1
EPC DPW DS- Engineering
Review 1


Engineering Comments have been provided on the following documents (to be uploaded by Project Manager):


V1 - Deviation Request
V1 – Pavement Report

Applicant Notes:


The applicant must upload the revised and missing items indicated below with his/her resubmittal:

V2 – Pavement Report

FYI:
1. The Deviation request will be signed by the ECM Administrator.
2. The Pavements Report will be signed after DS comments are addressed.
3. DS will inform you and will inform the Inspection Team after items 1 and 2 above are completed and at that time we will allow the Developer to start paving under the construction permit which was issued for the project (no additional permits will be required).

Reviewed by:


Jalal Saleh, PE, MBA, Senior Engineer
EPC DPW DS-Engineering
jalalsaleh@elpasoco.com

Bret Dilts, Senior Engineer
EPC DPW DS-Engineering
BretDilts@elpasoco.com
4/28/2026 9:17:02 AM