Project Review Comments
- File Number
- CDR264
- Project Name
- Waterbury Sanitary Force Main
- Description
- Sanitary force main plans going from the lift station to the Woodmen Hills Metro District WWTP.
- Parcels
- 4200000368 4200000368
- Applicant
-
Terra Nova Engineering, Inc.
Luanne Ducette ( l@tnesinc.com )
(719) 635-6422 Luanne Ducette ( l@tnesinc.com )
(719) 635-6422 - File Number
- CDR264
- Project Manager
- Engineering Manager
- Status
- Active
- Created
- 3/3/2026 10:32:12 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
EPC DPW Stormwater
3/31/2026 9:29:24 AM |
1 | SWMP | 3/31/2026 9:29:24 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:29:10 AM |
1 | SWMP Checklist | 3/31/2026 9:29:10 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:28:55 AM |
1 | PCM Applicability Form | 3/31/2026 9:28:55 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:28:38 AM |
1 | LOI | 3/31/2026 9:28:38 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:28:27 AM |
1 | GEC Checklist | 3/31/2026 9:28:27 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:28:11 AM |
1 | FAE | 3/31/2026 9:28:11 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:27:48 AM |
1 | ESQCP Form | 3/31/2026 9:27:48 AM |
| View |
EPC DPW Stormwater
3/31/2026 9:27:34 AM |
1 | CDs | 3/31/2026 9:27:34 AM |
|
EPC DPW Stormwater
3/31/2026 9:29:54 AM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - CDs - ESQCP - GEC Checklist - PCM Applicability Form - SWMP - SWMP Checklist Reviewed by: Zachary Jannusch Associate Engineer - Stormwater 719.500.3170 ZacharyJannusch@elpasoco.com |
3/31/2026 9:29:54 AM | |
|
EPC DPW Development Services - Engineering
3/30/2026 10:33:07 AM |
1 |
DRAFT CDR264 Waterbury Sanitary Force Main EPC DPW DS- Engineering Review 1 Engineering Comments have been provided on the following documents (to be uploaded by Project Manager): - GEC Plan - FAE - Letter of Intent Applicant Notes: Please consider completing a response letter / plans with your next submittal explaining how each comment was addressed (please copy and paste all comments to your response letter and respond below each comment). Please do not use the words done, fixed, etc. instead explain how you addressed each comment and indicate the sheet number. Please email me at the email address indicated below for a TEAM’S RCR “Review Comment Resolution” meeting prior to resubmittal to make sure all comments are addressed, so that we can move this project forward to approval. The applicant must upload the revised and missing items indicated below with his/her resubmittal: - Letter of Intent - GEC Plan - FAE FYI: 1. Construction permits will be issued by DS. 2. Work in the ROW permit will be issued from Acres building. 3. The ECM Administrator will sign and date the plans, reports, and documents after you make your final submittal (make sure ALL comments are addressed before you make your final submittal and the plans, reports, and documents have no additional comments). Related project/s: PPR2539 (Being reviewed by BD &CD). Reviewed by: Jalal Saleh, PE, MBA, Senior Engineer EPC DPW DS-Engineering jalalsaleh@elpasoco.com |
3/30/2026 10:33:07 AM | |
|
RBD Floodplain
3/19/2026 9:42:27 AM |
1 | no comment on forced main passing under floodplain | 3/19/2026 9:42:27 AM |
EDARP