Project Review Comments
- File Number
- PPR2537
- Project Name
- 8110 Opportunity View - Minor Site Development Review
- Description
- Add one modular building with basement to existing site. Review drainage letter.
- Parcels
- 5300000176 5300000176
- Applicant
-
M&S Civil Consultants
Virgil Sanchez ( virgils@mscivil.com )
(719) 491-0818 Virgil Sanchez ( virgils@mscivil.com )
(719) 491-0818 - File Number
- PPR2537
- Project Manager
- Lisa Elgin
- Status
- Active
- Created
- 11/19/2025 10:03:55 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
PCD Project Manager
1/28/2026 3:24:20 PM |
3 | Review 2 Site Development Plan Comments | 1/28/2026 3:24:20 PM |
|
EPC DPW Development Services - Engineering
1/28/2026 1:39:52 PM |
2 |
PPR2537: 8110 Opportunity View - Minor Site Development Review EPC DPW DS- Engineering Review 2. DPW Engineering has no comment on this proposed development with regard to the drainage letter. Please submit the executed drainage letter if you have NO stormwater comments. Review by Jalal Saleh, PE jalalsaleh@elpasoco.com 719-520-7550 |
1/28/2026 1:39:52 PM | |
|
PCD Project Manager
1/27/2026 4:42:09 PM |
2 | See comments on Site Plan Drawing to be uploaded by project engineer. | 1/27/2026 4:42:09 PM | |
|
Colorado Springs Public Works
1/13/2026 3:25:30 PM |
1 |
EDRD has no comments on this item. Reviewed by Hao Vo, P.E. hao.vo@coloradosprings.gov |
1/13/2026 3:25:30 PM | |
|
Colorado Springs Planning & Community Development
1/7/2026 6:06:39 PM |
1 | City Planning has no comment. | 1/7/2026 6:06:39 PM | |
|
Colorado Springs Public Works
1/5/2026 9:21:10 AM |
1 |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
1/5/2026 9:21:10 AM | |
| View |
EPC DPW Development Services - Engineering
12/31/2025 11:45:20 AM |
1 | RIF acknowledgement form comments | 12/31/2025 11:45:20 AM |
| View |
EPC DPW Development Services - Engineering
12/31/2025 10:57:35 AM |
1 | Drainage Letter comments | 12/31/2025 10:57:35 AM |
| View |
EPC DPW Development Services - Engineering
12/31/2025 10:49:41 AM |
1 | Site Development Plan comments | 12/31/2025 10:49:41 AM |
|
EPC DPW Development Services - Engineering
12/31/2025 1:19:35 PM |
1 |
Review 1 comments on the following documents will be uploaded: -Site Development Plan -Drainage Letter -RIF acknowledgement form reviewed by: Daniel Torres danieltorres@elpasoco.com and Jalal Saleh JalalSaleh@elpasoco.com |
12/31/2025 1:19:35 PM | |
|
EPC DPW Stormwater
12/30/2025 8:56:48 AM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM: - Drainage Letter Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
12/30/2025 8:56:48 AM | |
|
PCD Project Manager
12/29/2025 4:10:44 PM |
1 | See comments on Site Plan Drawing to be uploaded by project engineer. | 12/29/2025 4:10:44 PM |
EDARP