Project Review Comments

Back to List


Project Name
7805 Burgess Road MVEA Radio Pole
Description
Existing MVEA Substation would like to add a 12" diameter, 78' tall wooden pole to accommodate a two-way radio system.
Location
Parcels
5221200009 5221200009
Applicant
Mountain View Electric Association, Inc.
Nelson Yorke ( nelson.y@mvea.coop )
(719) 775-1305
Nelson Yorke ( nelson.y@mvea.coop )
(719) 775-1305
File Number
COM2517
Project Manager
Miranda Benson
Status
Active
Created
7/30/2025 1:50:27 PM

View: Project Documents



Review Comments (4)

Link Agency Comment
EPC DPW Development Services - Engineering
8/12/2025 3:35:13 PM
Engineering Review 1.

Engineering comments on the following documents:
- Site Plan Drawing

The Road Impact Fee is not applicable to this land use application.

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
8/12/2025 3:35:13 PM
EPC DPW Stormwater
8/12/2025 3:04:51 PM
Since there is no disturbance proposed with this project, EPC DPW Stormwater has no comments.

EPC Project Manager: no re-review necessary.

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
8/12/2025 3:04:51 PM
View PCD Project Manager
8/12/2025 12:38:35 PM
V1_PLANNING REVIEW CHECKLIST 8/12/2025 12:38:35 PM
PCD Project Manager
8/12/2025 12:08:44 PM
V1_Planning review complete. I was unable to find the past Site Development Plan/Approval of Location file for information reference. The COM- needs to include the Site Plan checklist items sent via email A copy of that email is also being uploaded here.

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
8/12/2025 12:08:44 PM