- Project Name
- 7805 Burgess Road MVEA Radio Pole
- Description
- Existing MVEA Substation would like to add a 12" diameter, 78' tall wooden pole to accommodate a two-way radio system.
- Location
- Parcels
- 5221200009 5221200009
- Applicant
-
Mountain View Electric Association, Inc.
Nelson Yorke ( nelson.y@mvea.coop )
(719) 775-1305 Nelson Yorke ( nelson.y@mvea.coop )
(719) 775-1305 - File Number
- COM2517
- Project Manager
- Miranda Benson
- Status
- Active
- Created
- 7/30/2025 1:50:27 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC DPW Development Services - Engineering
8/12/2025 3:35:13 PM |
Engineering Review 1. Engineering comments on the following documents: - Site Plan Drawing The Road Impact Fee is not applicable to this land use application. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
8/12/2025 3:35:13 PM | |
EPC DPW Stormwater
8/12/2025 3:04:51 PM |
Since there is no disturbance proposed with this project, EPC DPW Stormwater has no comments. EPC Project Manager: no re-review necessary. Reviewed by: Zachary Jannusch Associate Engineer - Stormwater 719.500.3170 ZacharyJannusch@elpasoco.com |
8/12/2025 3:04:51 PM | |
View |
PCD Project Manager
8/12/2025 12:38:35 PM |
V1_PLANNING REVIEW CHECKLIST | 8/12/2025 12:38:35 PM |
PCD Project Manager
8/12/2025 12:08:44 PM |
V1_Planning review complete. I was unable to find the past Site Development Plan/Approval of Location file for information reference. The COM- needs to include the Site Plan checklist items sent via email A copy of that email is also being uploaded here. Thank you, Miranda Benson mirandabenson2@elpasoco.com |
8/12/2025 12:08:44 PM |