Project Review Comments
- File Number
- P262
- Project Name
- MA Subdivision Tract A Rezone to RM30
- Description
- Rezone of a portion of MA Subdivision Tract A to RM-30. Residential-Multi-dwelling 30 allows for up to 30 dwelling units per acre, if approved. Please click on public comments if you would like to submit a comment. Item scheduled for Planning Commission June 18th and BoCC July 23rd 2026.
- Parcels
- 6115011001 6115011001
- Applicant
-
Vertex Consulting Services
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 733-8606 x6606 Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 733-8606 x6606 - EA Number
- EA2537
- File Number
- P262
- Project Manager
- Kari Parsons
- Status
- Active
- Created
- 4/16/2025 8:56:07 AM
View: Project Documents | Submit/View Public Comment
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Project Manager
6/9/2026 12:03:02 PM |
4 | Provide signatures on TIS; Owner/Developer must sign TIS | 6/9/2026 12:03:02 PM | |
|
EPC DPW Development Services - Engineering
6/9/2026 11:21:27 AM |
4 |
DPW Engineering review 3: Engineering has no further comments. The TIS will be routed to the Engineering Manager for acceptance. Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
6/9/2026 11:21:27 AM | |
|
PCD Project Manager
5/28/2026 1:24:23 PM |
3 |
Please resubmit the TIS removing the deviation. Please upload a deferral of deviation to deviation slot. |
5/28/2026 1:24:23 PM | |
| View |
Colorado Department of Transportation - Pueblo Office
5/21/2026 9:49:24 AM |
2 | Please see attached comments | 5/21/2026 9:49:24 AM |
|
EPC DPW Development Services - Engineering
5/21/2026 3:49:15 PM |
2 |
DPW Engineering review 2 comments have been resolved on the following documents - Letter of Intent - Traffic Impact Study Please have the TIS signed by the developer and resubmitted. After review of the deviation request, the ECM Administrator has indicated he is unlikely to support the deviation request. Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
5/21/2026 3:49:15 PM | |
|
EPC Parks Department
5/12/2026 11:33:26 AM |
2 |
The El Paso County Parks Department has reviewed this rezone proposal and has no objections to this rezone. The 2022 Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. Regional park fees and impacts will be assessed upon review of the forthcoming platting action(s). Thank you! Ashlyn Mathy Parks Planner Park Planning Division El Paso County Parks Department Office: 719.520.6978 |
5/12/2026 11:33:26 AM | |
|
Tri-Lakes-Monument Fire Protection District
5/6/2026 1:36:12 PM |
2 | The adopted International Fire Code does not address zoning/rezoning. The fire department will comment at the site planning phase. | 5/6/2026 1:36:12 PM | |
| View |
PCD Project Manager
3/19/2026 3:37:38 PM |
1 | Traffic Report Summary comments review 1 | 3/19/2026 3:37:38 PM |
| View |
EPC DPW Development Services - Engineering
3/19/2026 3:31:09 PM |
1 | Traffic Impact Study | 3/19/2026 3:31:09 PM |
|
EPC DPW Development Services - Engineering
3/19/2026 3:01:47 PM |
1 |
DPW Engineering review 1 has comments on the following documents - Letter of Intent - Traffic Impact Study Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
3/19/2026 3:01:47 PM | |
| View |
PCD Project Manager
3/19/2026 1:50:41 PM |
1 | Review 1 Zoning Map comments | 3/19/2026 1:50:41 PM |
| View |
PCD Project Manager
3/19/2026 1:50:03 PM |
1 | Review 1 Letter of Intent Comments | 3/19/2026 1:50:03 PM |
|
Mountain View Electric Association, Inc.
3/11/2026 11:46:59 AM |
1 | MVEA has no objection to the rezone. | 3/11/2026 11:46:59 AM | |
|
El Paso County Conservation Dist
3/9/2026 7:44:36 PM |
1 | The El Paso County Conservation District has reviewed this project request for rezoning. Currently, we see no conservation related issues to comment on but will review and comment on any future development on this site in the future. | 3/9/2026 7:44:36 PM | |
|
Monument
3/6/2026 9:16:52 AM |
1 | While we have no significant comments at this time, just noting that the property is located within the recetly adopted Monument 3 Mile Annexation area | 3/6/2026 9:16:52 AM | |
| View |
Colorado Department of Transportation - Pueblo Office
3/6/2026 7:30:44 AM |
1 | Attached please find CDOT'S comments | 3/6/2026 7:30:44 AM |
|
EPC Parks Department
3/2/2026 10:10:24 AM |
1 |
The El Paso County Parks Department has reviewed this rezone proposal and has no objections to this rezone. The 2022 Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. Regional park fees and impacts will be assessed upon review of the forthcoming platting action(s). Thank you! Ashlyn Mathy Parks Planner Park Planning Division El Paso County Parks Department Office: 719.520.6999 |
3/2/2026 10:10:24 AM | |
|
Tri-Lakes-Monument Fire Protection District
2/27/2026 10:53:44 AM |
1 | Monument Fire has no comment of rezoning request. | 2/27/2026 10:53:44 AM | |
|
Black Hills Energy-Aquila
2/26/2026 4:56:42 PM |
1 | BHE will serve. Please call in locates before excavation. | 2/26/2026 4:56:42 PM |
EDARP