Project Review Comments

Back to List


Project Name
Offsite Water Line Trails at Aspen Ridge
Description
Location
Parcels
5500000015 5500000015
Applicant
Matrix Design Group, Inc.
Jason Alwine ( jason_alwine@matrixdesigngroup.com )
(719) 457-5609
Jason Alwine ( jason_alwine@matrixdesigngroup.com )
(719) 457-5609
File Number
CDR252
Project Manager
Stormwater Glenn Reese
Status
Active
Created
4/10/2025 11:14:14 AM

View: Project Documents



Review Comments (7)

Link Agency Comment
View EPC DPW Stormwater
4/23/2025 10:45:30 AM
FAE_v1 4/23/2025 10:45:30 AM
View EPC DPW Stormwater
4/23/2025 10:45:15 AM
SWMP Checklist_v1 4/23/2025 10:45:15 AM
View EPC DPW Stormwater
4/23/2025 10:44:56 AM
SWMP_v1 4/23/2025 10:44:56 AM
View EPC DPW Stormwater
4/23/2025 10:44:35 AM
GEC Checklist_v1 4/23/2025 10:44:35 AM
View EPC DPW Stormwater
4/23/2025 10:44:13 AM
GEC_v1 4/23/2025 10:44:13 AM
EPC DPW Stormwater
4/23/2025 8:23:23 AM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- GEC Plan...............(uploaded with Development Services comments)
- GEC Checklist
- SWMP
- SWMP Checklist

Please submit the following documents for review:
- PCM Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Manager
719.520.6877
ChristinaPrete@elpasoco.com
4/23/2025 8:23:23 AM
EPC DPW Development Services - Engineering
4/22/2025 1:17:24 PM
EPC Engineering Review 1 had comments on the following documents:

- GEC Plans (See Comments to be uploaded by Stormwater)
- FAE (See Comments to be uploaded by Stormwater)
- CDs (See Comments below)

1. Please provide standard County signature block on CD's.
2. Please verify vertical clearance is minimum of 1.5' with all storm facilities. (See Page 8).
3. A work in the ROW Permit will be required for work within Fontaine, Rolling View and Lonewood.

Reviewed by:
Charlene Durham, PE
charlenedurham@elpasoco.com