- Description
- The owners of Lots 5-17 of Templeton Heights Subdivision request to have their dead-end road vacated.
- Parcels
- 6313001002 6313001002 6313001003 6313001003 6313001004 6313001004 6313001005 6313001005 6313001006 6313001006 6313001007 6313001007 6313001010 6313001010 6313001011 6313001011 6313001012 6313001012 6313001013 6313001013 6313001014 6313001014 6313001060 6313001060 6313001061 6313001061
- Applicant
-
Julie Michaud
John Fornander ( John@tnesinc.com )
(719) 635-6422 John Fornander ( John@tnesinc.com )
(719) 635-6422 - EA Number
- EA2524
- File Number
- V252
- Project Manager
- Joe Letke
- Status
- Active
- Created
- 3/7/2025 2:13:15 PM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Project Manager
5/19/2026 11:51:10 AM |
4 |
Planning has no further comments. This application is tentatively scheduled for the June 11th, 2026, BoCC meeting. Joe Letke Planner JoeLetke@elpasoco.com |
5/19/2026 11:51:10 AM | |
|
PCD Engineering Division
5/18/2026 4:40:42 PM |
4 |
DPW Engineering review 4 Comments have been resolved on the following - Deviation request Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
5/18/2026 4:40:42 PM | |
|
Colorado Springs Fire Department
4/30/2026 1:12:07 PM |
3 | Since CSFD is the primary response agency for this area, please provide a detailed drawing of the proposed gate intended to secure Apaloosa Drive once vacated. The gate must meet provisions of Section D103.5 of the 2021 International Fire Code as locally adopted. Additionally, approved Knox equipment keyed for CSFD must be provided in addition to any other equipment for other agencies or the residents. | 4/30/2026 1:12:07 PM | |
| View |
County Attorney - Development Review
4/21/2026 10:38:11 AM |
3 |
Edits to the Access and Maintenance Agreement are attached. Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com |
4/21/2026 10:38:11 AM |
| View |
County Attorney - Development Review
4/21/2026 10:37:21 AM |
3 |
See attached word document for additional comments. Reviewed by: Erika Keech, Sr. County Attorney, erikkeech2@elpasoco.com |
4/21/2026 10:37:21 AM |
| View |
PCD Project Manager
4/20/2026 8:51:23 AM |
3 | -V3 Vaction drawings comments | 4/20/2026 8:51:23 AM |
|
PCD Project Manager
4/20/2026 8:12:12 AM |
3 |
Planning has minor outstanding Version 1 and Version 2 comments on the Version 3 submittal: -Plat Drawing Joe Letke Planner JoeLetke@elpasoco.com |
4/20/2026 8:12:12 AM | |
| View |
PCD Engineering Division
4/17/2026 12:02:40 PM |
3 | Deviation Request | 4/17/2026 12:02:40 PM |
|
PCD Engineering Division
4/17/2026 12:00:27 PM |
3 |
DPW Engineering review 3 has comments on the following documents - Deviation request Comments have been resolved on the following - Vacation Drawing - Letter of Intent Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
4/17/2026 12:00:27 PM | |
|
Mountain View Electric Association, Inc.
12/31/2025 9:26:19 AM |
2 | See Comment Letter dated August 25, 2025 | 12/31/2025 9:26:19 AM | |
| View |
PCD Project Manager
12/22/2025 8:57:13 AM |
2 | -V2 LOI Comments | 12/22/2025 8:57:13 AM |
| View |
PCD Project Manager
12/22/2025 8:57:01 AM |
2 | -V2 Vacation Drawing Comments | 12/22/2025 8:57:01 AM |
|
Colorado Springs Public Works
12/22/2025 8:28:30 AM |
2 |
Traffic Engineering has no further comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
12/22/2025 8:28:30 AM | |
|
PCD Engineering Division
12/19/2025 11:17:55 AM |
2 |
DPW Engineering review 2 has comments on the following documents - Letter of Intent - Vacation Drawing Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
12/19/2025 11:17:55 AM | |
|
Colorado Springs Public Works
12/18/2025 12:49:31 PM |
2 |
EDRD has no additional comments. Reviewed by Hao Vo, P.E. hao.vo@coloradosprings.gov |
12/18/2025 12:49:31 PM | |
|
PCD Project Manager
12/17/2025 11:33:55 AM |
2 |
Planning has comments on the following version 2 documents: -V2 Vacation Drawing (Version 1 comment remain largely unaddressed) Joe Letke Planner JoeLetke@elpasoco.com |
12/17/2025 11:33:55 AM | |
| View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/15/2025 10:23:27 AM |
2 | Colorado Springs Utilities has no further comment on this Right-Of-Way Vacation application. | 12/15/2025 10:23:27 AM |
| View |
Mountain View Electric Association, Inc.
8/25/2025 2:01:03 PM |
1 | See attached Comment Letter | 8/25/2025 2:01:03 PM |
| View |
PCD Project Manager
8/14/2025 3:26:12 PM |
1 | -V1 Vacation Drawing | 8/14/2025 3:26:12 PM |
| View |
PCD Project Manager
8/14/2025 3:25:55 PM |
1 | -V1 Letter of Intent | 8/14/2025 3:25:55 PM |
|
PCD Engineering Division
8/14/2025 1:05:46 PM |
1 |
DPW Engineering review has comments on the following documents - Letter of Intent - Vacation Drawing Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
8/14/2025 1:05:46 PM | |
|
PCD Project Manager
8/13/2025 12:06:22 PM |
1 |
Planning has comments on the following version 1 documents: -V1 Letter of Intent -V1 Vacation Drawing In version 2, please provide/upload a maintenance agreement which details the future responsibility of maintenance, snow removal, gates, etc., of the private road. Joe Letke Planner JoeLetke@elpasoco.com |
8/13/2025 12:06:22 PM | |
|
EPC Stormwater Review
8/12/2025 3:31:47 PM |
1 |
Since there is no disturbance proposed with this project, EPC DPW Stormwater does not have any comments. EPC Project Manager: no re-review necessary. Reviewed by: Zachary Jannusch Associate Engineer - Stormwater 719.500.3170 ZacharyJannusch@elpasoco.com |
8/12/2025 3:31:47 PM | |
|
County Attorney - Development Review
8/11/2025 12:12:52 PM |
1 |
1. Please provide the Access and Maintenance Agreement for review. 2. Please depict or otherwise describe on the vacation plat a 60’ access easement to take the place of the public ROW. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com. |
8/11/2025 12:12:52 PM | |
| View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/8/2025 2:40:55 PM |
1 |
Please address the following comments on the ROW Vacation exhibit: Action Item: Show and label existing Gas Distribution Main: N24M10 located within Appaloosa Drive Action Item: Show and label all existing utilities, including size, material, private/public and project number if applicable. Use the following web link to access the Mapping Public Portal https://www.csu.org/building-development/gis-mapping-services Action Item: Add note “Fencing shall not stop access to utility lines or conflict with utility equipment.” Action Item: Add note stating type of gate locking mechanism. Action Item: Add note stating, "Applicant will work with CSU Operations Maintenance regarding gate access." |
8/8/2025 2:40:55 PM |
|
Colorado Springs Public Works
8/8/2025 12:46:01 PM |
1 |
EDRD will require that all public improvements be constructed in accordance with full City Standards if this site is selected for pre-annexation. Reviewed by Hao Vo, P.E. hao.vo@coloradosprings.gov |
8/8/2025 12:46:01 PM | |
| View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/7/2025 9:52:26 AM |
1 | Please include either a chord bearing or radial bearing for all non-tangent curves. | 8/7/2025 9:52:26 AM |
|
Colorado Springs Planning & Community Development
8/6/2025 8:54:36 AM |
1 | City Planning has no comment for the vacation of Apaloosa Drive. | 8/6/2025 8:54:36 AM | |
|
Colorado Springs Public Works
8/1/2025 11:06:15 AM |
1 |
Traffic Engineering will require all public improvements to be built to full City Standards if this site is chosen for pre-annexation. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |