Project Review Comments

Back to List


Project Name
Whittemore Rd - Major Kennel
Description
40 acre property in A-35 housing more than 4 dogs in 3 shipping containers with indoor/outdoor kennels. Containers are conditioned with insulation, electrical, heat (plug in), and A/C (plug in). Property also contains 200 sq ft container that acts as an office as well as an RV that is used as an office/storage/shelter while caring for the dogs.
Location
Parcels
500000427 500000427
Applicant
Khaled Zaky
Khaled Zaky ( jbfransua@yahoo.com )
(720) 569-5959
Khaled Zaky ( jbfransua@yahoo.com )
(720) 569-5959
File Number
PPR2510
Project Manager
Lacey Dean
Status
Active
Created
1/23/2025 11:48:28 AM

View: Project Documents



Review Comments (16)

Link Agency Comment
View PCD Project Manager
3/24/2025 4:36:47 PM
V1_Site Development Plan_comments 3/24/2025 4:36:47 PM
View PCD Project Manager
3/24/2025 4:36:27 PM
V1_Lighting Plan_comments 3/24/2025 4:36:27 PM
View PCD Project Manager
3/24/2025 4:35:57 PM
V1_Letter of Intent_comments 3/24/2025 4:35:57 PM
View PCD Project Manager
3/24/2025 4:35:40 PM
V1_Legal Description_comments 3/24/2025 4:35:40 PM
View PCD Project Manager
3/24/2025 4:35:24 PM
V1_Landscape Plan Drawings_comments 3/24/2025 4:35:24 PM
View PCD Project Manager
3/24/2025 4:35:07 PM
V1_Floor Plans_comments 3/24/2025 4:35:07 PM
View PCD Project Manager
3/24/2025 4:34:53 PM
V1_Elevation for 4ft extension_comments 3/24/2025 4:34:53 PM
View PCD Project Manager
3/24/2025 4:34:23 PM
V1_Application-Petition Form_comments 3/24/2025 4:34:23 PM
PCD Engineering Division
3/24/2025 3:54:32 PM
Engineering Review 1.

Engineering comments (in blue) on the following documents (to be uploaded by project manager):
- Letter of Intent
- Floor Plans
- Landscape Drawings
- Site Development Plan

Feel free to call or email to discuss if any clarity is needed with addressing engineering comments.

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
3/24/2025 3:54:32 PM
EPC Code Enforcement
3/24/2025 11:41:03 AM
Code is concerned there is not measurements for the structures and they could be in the setbacks. Regarding the lighting plan there is no mention of shielding or down lighting to make sure the light rays stay on the property. 3/24/2025 11:41:03 AM
EPC Stormwater Review
3/24/2025 8:11:01 AM
Review 1: In the Letter of Intent, please state the total proposed soil disturbance to construct the project. Include footprint of shipping containers and any site prep/grading needed in the amount of disturbance. Also be sure to show and label the approximate limits of disturbance in the Site Development Plan.

Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- PCM/PBMP Applicability Form

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
3/24/2025 8:11:01 AM
Mountain View Electric Association, Inc.
3/18/2025 8:43:33 AM
This property is not within MVEA territory - its in SCPA territory 3/18/2025 8:43:33 AM
Pikes Peak Regional Building Department
3/18/2025 8:32:21 AM
Enumerations has no comment regarding the special use aspect of this residential project.

Becky Allen
beckya@pprbd.org
719-799-2707
3/18/2025 8:32:21 AM
Tri-County Fire Protection District
3/14/2025 12:05:15 PM
Please advise how you plan to comply with section 6.3.3. Fire Protection and Wildfire Mitigation and how you would provide a fire protection water supply. 3/14/2025 12:05:15 PM
PCD Project Manager
3/13/2025 5:27:16 PM
Review 1: EPC Planning Division has comments in green text boxes on the following documents:

- Letter of Intent
- Application Form
- Legal Description
- Lighting Plan
- Landscape Plan Drawings
- Elevation Plans with 4 ft extension
- Floor Plans
- Site Development Plan

**NOTE** Due to software issues with our review program, I am unable to save and upload at this time. Therefore, the documents listed above will be saved and uploaded by the Engineer when he is done with his review.

Reviewed by:
Lacey Dean, Associate Planner
laceydean2@elpasoco.com
3/13/2025 5:27:16 PM
View EPC Environmental Services
3/6/2025 12:49:20 PM
3/6/2025 12:49:20 PM