Project Review Comments
- Project Name
- Bar X FAWWA Segment 2 Pipeline
- Description
- Construct an approximate 4.8 mile long, 8 and 24-inch diameter water transmission line connecting Bar X Segment A1 to Winsome well site.
- Location
- Parcels
- 5100000524 5100000524 5200000366 5200000366 5212000002 5212000002
- Applicant
-
RESPEC - JDS-Hydro Consultants, Inc.
Troy Montague ( troy.montague@respec.com ) Troy Montague ( troy.montague@respec.com ) - File Number
- CDR248
- Project Manager
- Engineering Manager
- Status
- Active
- Created
- 9/30/2024 8:47:05 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Engineering Division
10/30/2024 6:08:52 PM |
LOI_V1 | 10/30/2024 6:08:52 PM |
View |
PCD Engineering Division
10/30/2024 6:08:39 PM |
GEC Plan_V1 | 10/30/2024 6:08:39 PM |
View |
PCD Engineering Division
10/30/2024 6:08:22 PM |
FAE_V1 | 10/30/2024 6:08:22 PM |
PCD Engineering Division
10/30/2024 6:08:02 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents LOI_V1 FAE_V1 GEC Plan_V1 A work in the ROW permit will be required for crossing Hodgen Rd. Please provide additional information on the staging and laydown yard area and if a site dev plan was submitted for this area and disturbance. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
10/30/2024 6:08:02 PM | |
View |
EPC Stormwater Review
10/30/2024 12:57:37 PM |
SWMP Checklist | 10/30/2024 12:57:37 PM |
View |
EPC Stormwater Review
10/30/2024 12:57:22 PM |
SWMP | 10/30/2024 12:57:22 PM |
View |
EPC Stormwater Review
10/30/2024 12:56:52 PM |
PBMP Applicability | 10/30/2024 12:56:52 PM |
View |
EPC Stormwater Review
10/30/2024 12:56:36 PM |
GEC Checklist | 10/30/2024 12:56:36 PM |
View |
EPC Stormwater Review
10/30/2024 12:56:02 PM |
ESQCP | 10/30/2024 12:56:02 PM |
EPC Stormwater Review
10/30/2024 12:54:46 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - ESQCP - FAE........................(to be uploaded with Development Services comments) - GEC Plan...............(to be uploaded with Development Services comments) - GEC Checklist - Letter of Intent........(to be uploaded with Development Services comments) - PBMP Applicability Form - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
10/30/2024 12:54:46 PM | |
Colorado Springs Public Works
10/29/2024 9:26:47 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
10/29/2024 9:26:47 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/28/2024 11:17:40 AM |
Good morning Kari, Proposed pipeline segment A2 for CDR248 is outside of Colorado Springs Utilities service area. Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Utilities Development Services | Colorado Springs Utilities 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
10/28/2024 11:17:40 AM | |
Pikes Peak Regional Building Department
10/25/2024 11:59:12 AM |
If there are new proposed meters, contact Enumerations for an address. Email me directly with the meter location. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
10/25/2024 11:59:12 AM | |
Mountain View Electric Association, Inc.
10/22/2024 2:29:30 PM |
MVEA has existing facilities near and within this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 10/22/2024 2:29:30 PM | |
Colorado Springs Public Works
10/17/2024 7:47:30 PM |
Traffic Engineering has no comments on this item. Brian Shevock Public Works/Traffic Engineering Traffic Engineer City of Colorado Springs brian.shevock@coloradosprings.gov (719) 385-7620 |
10/17/2024 7:47:30 PM | |
RBD Floodplain
10/16/2024 8:57:54 AM |
any adjustments to existing grade for subterranean pipeline though floodplain would require a local floodplain permit. | 10/16/2024 8:57:54 AM |