Project Review Comments

Back to List


Project Name
Falcon Baptist Church Minor Site Dev Plan Addition
Description
Attached expansion (3435 sq. ft.) on the north and west of the existing main chapel building.
Location
Parcels
5313002016 5313002016
Applicant
Nelson-Ross Architects
Lowell Ross ( lross@jpnarch.com )
(719) 600-7288
Lowell Ross ( lross@jpnarch.com )
(719) 600-7288
File Number
PPR2516
Project Manager
Miranda Benson
Status
Active
Created
9/5/2024 8:53:43 AM

View: Project Documents



Review Comments (12)

Link Agency Comment
View Mountain View Electric Association, Inc.
5/15/2025 3:53:33 PM
Please see attached comment 5/15/2025 3:53:33 PM
Falcon School District 49
5/13/2025 8:10:53 AM
District 49 does not have any comments at this time but respectfully reserves the right to comment on any future submittals. 5/13/2025 8:10:53 AM
View PCD Project Manager
5/12/2025 4:15:41 PM
V1_PBMP Applicability Form_COMMENTS 5/12/2025 4:15:41 PM
View PCD Project Manager
5/12/2025 4:15:28 PM
V1_Landscape Plan_COMMENTS 5/12/2025 4:15:28 PM
View PCD Project Manager
5/12/2025 4:15:13 PM
V1_Site Development Plan_COMMENTS 5/12/2025 4:15:13 PM
View PCD Project Manager
5/12/2025 4:14:59 PM
V1_Letter of Intent_COMMENTS 5/12/2025 4:14:59 PM
PCD Project Manager
5/12/2025 4:13:50 PM
V1_ Planning Review complete. Planning comments were added (in green) to the following documents:

Letter of Intent
Site Development Plan
Landscaping Plan

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
5/12/2025 4:13:50 PM
EPC Stormwater Review
5/12/2025 1:13:29 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM:
- PBMP Applicability Form

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
5/12/2025 1:13:29 PM
View PCD Engineering Division
5/12/2025 2:32:24 PM
Engineering Review Ver.1

Please see engineering review comments on the following documents

LOI_V1
SDP_V1
A drainage letter will be required with next submittal to address detention and WQ.

A Driveway access permit is required. Submit through EDARP. Guide is attached.
EPC Road Impact fee are applicable for the new extension. To be paid at time of building permit.
https://publicworks.elpasoco.com/road-impact-fees/
Institutional Rate $2371 per 1000sqft

Thank you.

Edward Schoenheit, Engineer
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
edwardschoenheit@elpasoco.com
https://planningdevelopment.elpasoco.com/
5/12/2025 2:32:24 PM
Pikes Peak Regional Building Department
5/12/2025 8:29:09 AM
Enumerations has the following comments:

1. The address for this church building is 11185 Eggar Dr. Any building plans submitted for this project need to use this address.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
5/12/2025 8:29:09 AM
View Falcon Fire Protection District
5/7/2025 2:37:22 PM
5/7/2025 2:37:22 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/30/2025 11:06:09 AM
See attached CSU review with gas comments on site development plan. 4/30/2025 11:06:09 AM