Project Review Comments
- Project Name
- Falcon Baptist Church Minor Site Dev Plan Addition
- Description
- Attached expansion (3435 sq. ft.) on the north and west of the existing main chapel building.
- Location
- Parcels
- 5313002016 5313002016
- Applicant
-
Nelson-Ross Architects
Lowell Ross ( lross@jpnarch.com )
(719) 600-7288 Lowell Ross ( lross@jpnarch.com )
(719) 600-7288 - File Number
- PPR2516
- Project Manager
- Miranda Benson
- Status
- Active
- Created
- 9/5/2024 8:53:43 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
Mountain View Electric Association, Inc.
5/15/2025 3:53:33 PM |
Please see attached comment | 5/15/2025 3:53:33 PM |
Falcon School District 49
5/13/2025 8:10:53 AM |
District 49 does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 5/13/2025 8:10:53 AM | |
View |
PCD Project Manager
5/12/2025 4:15:41 PM |
V1_PBMP Applicability Form_COMMENTS | 5/12/2025 4:15:41 PM |
View |
PCD Project Manager
5/12/2025 4:15:28 PM |
V1_Landscape Plan_COMMENTS | 5/12/2025 4:15:28 PM |
View |
PCD Project Manager
5/12/2025 4:15:13 PM |
V1_Site Development Plan_COMMENTS | 5/12/2025 4:15:13 PM |
View |
PCD Project Manager
5/12/2025 4:14:59 PM |
V1_Letter of Intent_COMMENTS | 5/12/2025 4:14:59 PM |
PCD Project Manager
5/12/2025 4:13:50 PM |
V1_ Planning Review complete. Planning comments were added (in green) to the following documents: Letter of Intent Site Development Plan Landscaping Plan Thank you, Miranda Benson mirandabenson2@elpasoco.com |
5/12/2025 4:13:50 PM | |
EPC Stormwater Review
5/12/2025 1:13:29 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM: - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
5/12/2025 1:13:29 PM | |
View |
PCD Engineering Division
5/12/2025 2:32:24 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents LOI_V1 SDP_V1 A drainage letter will be required with next submittal to address detention and WQ. A Driveway access permit is required. Submit through EDARP. Guide is attached. EPC Road Impact fee are applicable for the new extension. To be paid at time of building permit. https://publicworks.elpasoco.com/road-impact-fees/ Institutional Rate $2371 per 1000sqft Thank you. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 edwardschoenheit@elpasoco.com https://planningdevelopment.elpasoco.com/ |
5/12/2025 2:32:24 PM |
Pikes Peak Regional Building Department
5/12/2025 8:29:09 AM |
Enumerations has the following comments: 1. The address for this church building is 11185 Eggar Dr. Any building plans submitted for this project need to use this address. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
5/12/2025 8:29:09 AM | |
View |
Falcon Fire Protection District
5/7/2025 2:37:22 PM |
5/7/2025 2:37:22 PM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/30/2025 11:06:09 AM |
See attached CSU review with gas comments on site development plan. | 4/30/2025 11:06:09 AM |