Project Review Comments

Back to List


Project Name
Judge Orr Fabric Building PPR
Description
Location
Parcels
4305006003 4305006003
Applicant
Hammers Construction
Anthony Mezzetta ( anthony.mezzetta@metronet.com )
000-0000
Anthony Mezzetta ( anthony.mezzetta@metronet.com )
000-0000
EA Number
EA23101
File Number
PPR2529
Project Manager
Joe Letke
Status
Active
Created
11/8/2023 7:10:27 AM

View: Project Documents



Review Comments (25)

Link Agency Comment
View EPC Health Department
11/3/2025 9:24:53 AM
11/3/2025 9:24:53 AM
El Paso County Conservation Dist
10/30/2025 4:56:28 PM
No comments at this time. 10/30/2025 4:56:28 PM
View County Attorney - Development Review
10/30/2025 1:13:22 PM
See edits to DMA.

Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
10/30/2025 1:13:22 PM
Mountain View Electric Association, Inc.
10/29/2025 2:52:18 PM
MVEA has no objection. 10/29/2025 2:52:18 PM
View EPC Stormwater Review
10/28/2025 7:20:39 AM
SWMP Checklist 10/28/2025 7:20:39 AM
View EPC Stormwater Review
10/28/2025 7:20:18 AM
SWMP comments 10/28/2025 7:20:18 AM
View EPC Stormwater Review
10/28/2025 7:20:00 AM
PCM Applicability Form 10/28/2025 7:20:00 AM
View EPC Stormwater Review
10/28/2025 7:19:35 AM
O&M comments 10/28/2025 7:19:35 AM
View EPC Stormwater Review
10/28/2025 7:19:15 AM
GEC Checklist 10/28/2025 7:19:15 AM
View EPC Stormwater Review
10/28/2025 7:18:33 AM
GEC comments 10/28/2025 7:18:33 AM
View EPC Stormwater Review
10/28/2025 7:18:03 AM
FAE comments 10/28/2025 7:18:03 AM
View EPC Stormwater Review
10/28/2025 7:17:44 AM
ESQCP comments 10/28/2025 7:17:44 AM
View EPC Stormwater Review
10/28/2025 7:17:20 AM
Drainage Report comments 10/28/2025 7:17:20 AM
View PCD Project Manager
10/27/2025 4:15:01 PM
-V1 Letter of Intent 10/27/2025 4:15:01 PM
View PCD Project Manager
10/27/2025 4:13:20 PM
-V1 Site Development Plan 10/27/2025 4:13:20 PM
PCD Engineering Division
10/27/2025 3:58:19 PM
EPC Engineering Review 1: Comments have been provided on the following documents:

- Drainage Report (to be uploaded by SW Engineer)
- GEC Plans (to be uploaded by SW Engineer)
- Letter of Intent (to be uploaded by PM)
- Site Development Plan (to be uploaded by PM)

Reviewed by:

Jalal Saleh, PE
jalalsaleh@elpasoco.com

Charlene Durham, PE
charlenedurham@elpasoco.com
10/27/2025 3:58:19 PM
EPC Fire and Wildfire Program Manager
10/27/2025 3:20:03 PM
Provide the fire flow at 20psi for the two hydrants shown on site. Do the existing hydrants have collision protection or will it be added? What method is used for calculating the required fire flow for the purposed structure and what is the required fire flow?

Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
rolandpeterson@elpasoco.com
10/27/2025 3:20:03 PM
View PCD Project Manager
10/27/2025 2:30:37 PM
-V1 Landscape Plan 10/27/2025 2:30:37 PM
View PCD Project Manager
10/27/2025 2:30:02 PM
-V1 Lighting Plan 10/27/2025 2:30:02 PM
EPC Stormwater Review
10/27/2025 4:10:22 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- PCM O&M Manual
- PCM Applicability Form
- SWMP
- SWMP Checklist

Please provide the following documents upon resubmittal (the planner will send an upload request):
- PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal)
- PCM - MHFD Detention Calcs or SDI Form

Reviewed by:
Mikayla Hartford, P.E.
Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
10/27/2025 4:10:22 PM
Upper Black Squirrel Creek GWMD
10/24/2025 3:29:31 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. 10/24/2025 3:29:31 PM
Pikes Peak Regional Building Department
10/24/2025 9:15:24 AM
1. Plans for the conversion of the existing fabric building can be submitted under the existing address 12827 Judge Orr Rd.
2. No further comment.

Thank you,

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
10/24/2025 9:15:24 AM
PCD Project Manager
10/27/2025 4:16:31 PM
Planning has comments on the following version one documents:

-Letter of Intent
-Site Development Plan
-Landscape Drawings
-Lighting Plan

DPW Stormwater will upload additional review comments.

Joe Letke
Planner
JoeLetke@elpasoco.com
10/27/2025 4:16:31 PM
View Falcon Fire Protection District
10/20/2025 8:39:54 AM
10/20/2025 8:39:54 AM
RBD Floodplain
10/14/2025 7:45:05 AM
parcel 4305006003 is not in the floodplain, no further comment 10/14/2025 7:45:05 AM