Project Review Comments
- Project Name
- Gardens at North Carefree Metro District
- Description
- New Metropolitan District
- Location
- Parcels
- 5329400012 5329400012 5329411002 5329411002
- Applicant
-
susemihl, mcdermott & cowan, p.c.
Peter Susemihl ( psusemihl@smmclaw.com )
(719) 579-6500 Peter Susemihl ( psusemihl@smmclaw.com )
(719) 579-6500 - EA Number
- EA198
- File Number
- ID191
- Project Manager
- Nina Ruiz
- Status
- Closed
- Created
- 1/31/2019 10:51:53 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC County Attorney's Office
8/1/2019 11:05:06 AM |
No comment. CAO |
8/1/2019 11:05:06 AM | |
View |
EPC Health Department
5/1/2019 5:22:05 PM |
5/1/2019 5:22:05 PM | |
View |
PCD Engineering Division
4/29/2019 2:56:28 PM |
Review 3: One remaining engineering comment to the service plan document is unresolved (attached). Reviewed by: Gilbert LaForce, P.E. Engineer II gilbertlaforce@elpasoco.com |
4/29/2019 2:56:28 PM |
PCD Project Manager
4/18/2019 12:20:48 PM |
comments not addressed. please review previous comments. If the resubmission is made in a timely manner, and the comments addressed, staff anticipates your item being on the 05/21 PC hearing date. |
4/18/2019 12:20:48 PM | |
View |
EPC Parks Department
4/17/2019 4:19:19 PM |
4/17/2019 4:19:19 PM | |
View |
PCD Engineering Division
4/17/2019 2:51:30 PM |
Review 2: Engineering comments to the service plan documents were not addressed. See attached for review comments. Reviewed by: Gilbert LaForce, P.E. Engineer II gilbertlaforce@elpasoco.com |
4/17/2019 2:51:30 PM |
View |
EPC Parks Department
4/3/2019 1:17:56 PM |
El Paso County Community Services / Parks Preliminary Comments - Please see attached document (To be presented to Park Advisory Board for endorsement on 04/10/2019) | 4/3/2019 1:17:56 PM |
View |
PCD Project Manager
4/3/2019 7:44:30 AM |
Model Service Plan Redlines | 4/3/2019 7:44:30 AM |
PCD Project Manager
4/3/2019 7:43:58 AM |
1. The documents as submitted indicate that water and wastewater is to be provided via the District. However, the documents previously provided state that water and sanitation is to be provided by Cherokee Metro District. 2. The model service plan contains aspects that are not applicable to your district. In these instances please remove. For example, in the table of contents you are not proposing extraterritorial services. 3. please ADD ALL EXHIBITS AS CALLED FOR IN THE MODEL SERVICE PLAN. 4. The development summary does not meet the requirements of the model plan. |
4/3/2019 7:43:58 AM | |
View |
PCD Engineering Division
3/27/2019 12:06:38 PM |
Review 1 comments to the Infrastructure Capital Costs Exhibit is attached. | 3/27/2019 12:06:38 PM |
View |
PCD Engineering Division
3/27/2019 11:33:34 AM |
Review 1 comments to the Service Plan is attached. | 3/27/2019 11:33:34 AM |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/21/2019 4:11:14 PM |
Hey Nina, CSU has no comments. Let me know if you need anything further from me. Thanks, Ryne |
3/21/2019 4:11:14 PM | |
EPC Environmental Services
3/19/2019 4:07:58 PM |
Environmental has no further comment | 3/19/2019 4:07:58 PM | |
Central CO Conservation District
3/11/2019 12:37:54 PM |
The Central Colorado Conservation District board of supervisors have no comments at this time. Thank you |
3/11/2019 12:37:54 PM |