9/16/2026 11:42:02 AM
|
Payment Request sent: 9/16/2026
|
|
9/16/2026 11:41:27 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/16/2026 11:40:19 AM
|
Request for Review Comments email resent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Justin Kilgore on behalf of PCD Project Manager
|
|
9/16/2026 11:28:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/15/2026 9:11:57 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
9/14/2026 4:36:38 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
9/14/2026 2:53:05 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
9/14/2026 2:53:04 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
9/14/2026 2:53:03 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
9/14/2026 2:53:03 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
9/14/2026 2:53:02 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
9/14/2026 2:53:00 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
9/14/2026 2:52:59 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
9/14/2026 2:52:57 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Justin Kilgore on behalf of PCD Project Manager
|
|
9/14/2026 2:32:15 PM
|
Submission Triaged
|
|
9/10/2026 4:49:11 PM
|
Submission received from Applicant
|
|
6/24/2026 5:29:54 PM
|
Submission request sent to Applicant
|
|
6/24/2026 3:15:39 PM
|
Submission request sent to Applicant
|
|
6/24/2026 3:14:36 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
6/23/2026 4:18:22 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
6/23/2026 3:14:23 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
6/18/2026 4:00:37 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
6/18/2026 4:00:37 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
6/18/2026 4:00:36 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
6/18/2026 4:00:35 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
6/18/2026 4:00:34 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
6/18/2026 4:00:33 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
6/18/2026 4:00:32 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
6/18/2026 4:00:30 PM
|
Request for Review Comments email sent for Project 7113 Space Village Ave - Gravel compound addition to PPR233 for review by Justin Kilgore on behalf of PCD Project Manager
|
|
6/17/2026 2:27:09 PM
|
Fees paid: 6/17/2026 (Receipt: 1012184)
|
|
6/8/2026 8:35:13 AM
|
Payment Request sent: 6/8/2026
|
|
6/8/2026 8:35:13 AM
|
File # Assigned: COM2613
|
|
6/8/2026 8:35:10 AM
|
Submission Triaged
|
|
6/5/2026 9:45:35 AM
|
Submission received from Applicant
|
|
6/2/2026 10:19:38 AM
|
Submission request sent to Applicant
|
|
5/14/2026 10:27:36 AM
|
Submission request sent to Applicant
|
|
5/14/2026 10:19:32 AM
|
Project Manager Assigned: Lacey Dean
|
|
5/14/2026 10:19:32 AM
|
Project Created
|