6/25/2026 9:28:57 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
6/24/2026 3:06:00 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
|
|
6/24/2026 3:05:59 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by William Vogl on behalf of El Paso County Conservation Dist
|
|
6/24/2026 3:05:58 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
|
6/24/2026 3:05:57 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Katie Miller on behalf of El Paso County Conservation Dist
|
|
6/24/2026 3:05:56 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by on behalf of El Paso County Conservation Dist
|
|
6/24/2026 3:05:55 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
|
6/24/2026 3:05:54 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Tom Joyce on behalf of Cimarron Hills Fire District
|
|
6/24/2026 3:05:53 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
|
6/24/2026 3:05:52 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
|
|
6/24/2026 3:05:51 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
6/24/2026 3:05:50 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
6/24/2026 3:05:49 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
6/24/2026 3:05:49 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
6/24/2026 3:05:48 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
6/24/2026 3:05:47 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
6/24/2026 3:05:46 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
6/24/2026 3:05:44 PM
|
Request for Review Comments email sent for Project Wayfarer Vans Minor Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
|
6/24/2026 2:06:50 PM
|
Project Manager Assigned: Kylie Bagley
|
|
6/24/2026 1:52:37 PM
|
Fees paid: 6/24/2026 (Receipt: 1012231)
|
|
6/24/2026 1:48:20 PM
|
Payment Request sent: 6/24/2026
|
|
6/24/2026 1:48:19 PM
|
File # Assigned: PPR2618
|
|
6/24/2026 1:48:17 PM
|
Submission Triaged
|
|
6/24/2026 10:34:24 AM
|
Submission received from Applicant
|
|
6/24/2026 10:23:17 AM
|
Submission request sent to Applicant
|
|
6/24/2026 10:21:47 AM
|
Submission Triaged
|
|
6/24/2026 9:41:20 AM
|
Submission received from Applicant
|
|
3/3/2026 2:04:17 PM
|
Submission request sent to Applicant
|
|
3/3/2026 2:01:28 PM
|
Project Created
|