12/16/2025 8:15:16 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
|
12/10/2025 12:33:21 PM
|
Meeting scheduled: 12/16/2025 3:00:00 PM
|
|
12/5/2025 1:32:56 PM
|
Request for Review Comments returned by EPC Parks Department
|
|
12/4/2025 1:19:17 PM
|
Meeting scheduled: 12/16/2025 3:00:00 PM
|
|
12/2/2025 3:02:41 PM
|
Project Manager Assigned: Jen Uhler
|
|
12/2/2025 2:53:16 PM
|
Request for Assignment email sent for Project Steve Kang for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
|
|
12/2/2025 2:53:15 PM
|
Request for Assignment sent to EPC Fire and Wildfire Program Manager
|
|
12/2/2025 2:53:15 PM
|
Request for Assignment email sent for Project Steve Kang for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
|
12/2/2025 2:53:05 PM
|
Request for Assignment sent to Colorado Springs Public Works
|
|
12/2/2025 2:53:05 PM
|
Request for Assignment email sent for Project Steve Kang for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
12/2/2025 2:53:01 PM
|
Request for Assignment sent to EPC DPW Stormwater
|
|
12/2/2025 2:53:00 PM
|
Request for Assignment email sent for Project Steve Kang for review by Catherine McGarvy on behalf of EPC Health Department
|
|
12/2/2025 2:52:57 PM
|
Request for Assignment sent to EPC Health Department
|
|
12/2/2025 2:52:56 PM
|
Request for Assignment email sent for Project Steve Kang for review by Drew Fox on behalf of Colorado Springs Planning & Community Development
|
|
12/2/2025 2:52:54 PM
|
Request for Assignment sent to Colorado Springs Planning & Community Development
|
|
12/2/2025 2:52:54 PM
|
Request for Assignment email sent for Project Steve Kang for review by Justin Kilgore on behalf of PCD Project Manager
|
|
12/2/2025 2:52:53 PM
|
Request for Assignment sent to PCD Project Manager
|
|
12/2/2025 2:52:52 PM
|
Request for Assignment email sent for Project Steve Kang for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
12/2/2025 2:52:50 PM
|
Request for Assignment sent to EPC DPW Development Services - Engineering
|
|
12/2/2025 2:52:46 PM
|
Fees paid: 12/2/2025 (Receipt: 1011396)
|
|
12/1/2025 8:58:09 AM
|
Payment Request sent: 12/1/2025
|
|
12/1/2025 8:58:02 AM
|
EA Assigned: EA25136
|
|
12/1/2025 8:58:02 AM
|
Project Created
|
|
12/1/2025 8:58:00 AM
|
Application Triaged/Accepted
|
|
11/26/2025 4:53:27 PM
|
Application submitted
|