10/7/2025 8:20:06 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
10/3/2025 11:18:13 AM
|
Request for Review Comments returned by EPC Environmental Services
|
10/2/2025 10:01:21 AM
|
Fees paid: 10/2/2025 (Receipt: 1011150)
|
10/2/2025 7:29:52 AM
|
Payment Request sent: 10/2/2025
|
10/1/2025 4:17:40 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
10/1/2025 3:28:26 PM
|
Request for Review Comments returned by EPC Parks Department
|
9/30/2025 3:38:41 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Jackie Evans on behalf of Kiowa Conservation Dist
|
9/30/2025 3:38:40 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Evelyn galanephillips on behalf of Falcon School District 49
|
9/30/2025 3:38:39 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Trent Harwig on behalf of Falcon Fire Protection District
|
9/30/2025 3:38:38 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
9/30/2025 3:38:37 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Rebecca Hardekopf on behalf of Winsome Metropolitan District
|
9/30/2025 3:38:36 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/30/2025 3:38:35 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by on behalf of EPC Parks Department
|
9/30/2025 3:38:33 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Mike McCarthy on behalf of EPC Health Department
|
9/30/2025 3:38:33 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Catherine McGarvy on behalf of EPC Health Department
|
9/30/2025 3:38:31 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by HEAEH LandUse on behalf of EPC Health Department
|
9/30/2025 3:38:30 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/30/2025 3:38:29 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
9/30/2025 3:38:28 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
9/30/2025 3:38:27 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Glenn Reese on behalf of EPC DPW Stormwater
|
9/30/2025 3:38:26 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Christina Prete on behalf of EPC DPW Stormwater
|
9/30/2025 3:38:25 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
9/30/2025 3:38:24 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
9/30/2025 3:38:22 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by Justin Kilgore on behalf of PCD Project Manager
|
9/30/2025 3:38:20 PM
|
Request for Review Comments email sent for Project 10281 Alamar Way - Permanent Occupance of ALQ for review by on behalf of PCD Administrative Notice
|
9/26/2025 9:16:42 AM
|
Fees paid: 9/26/2025 (Receipt: 1011119)
|
9/24/2025 12:06:16 PM
|
Payment Request sent: 9/24/2025
|
9/24/2025 12:06:16 PM
|
File # Assigned: AL2525
|
9/24/2025 12:06:13 PM
|
Submission Triaged
|
9/23/2025 7:10:14 PM
|
Submission received from Applicant
|
8/20/2025 10:33:13 AM
|
Submission request sent to Applicant
|
8/19/2025 2:11:12 PM
|
Project Manager Assigned: Lacey Dean
|
8/19/2025 2:11:12 PM
|
Project Created
|