4/17/2025 3:10:12 PM
|
Project Closed
|
4/17/2025 3:10:12 PM
|
Project Approved: 4/17/2025
|
3/18/2025 10:27:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/17/2025 5:12:56 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/17/2025 1:08:35 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/17/2025 1:08:34 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/17/2025 1:08:33 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Christina Prete on behalf of EPC Stormwater Review
|
3/17/2025 12:58:41 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/11/2025 9:15:08 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Justin Kilgore on behalf of PCD Project Manager
|
3/11/2025 9:15:06 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/11/2025 9:15:04 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Engineering Manager on behalf of PCD Engineering Division
|
3/11/2025 9:14:39 AM
|
Submission Triaged
|
3/11/2025 7:38:03 AM
|
Submission received from Applicant
|
2/25/2025 1:18:15 PM
|
Submission request sent to Applicant
|
2/25/2025 1:17:35 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/24/2025 6:04:42 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/24/2025 5:22:01 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/12/2025 10:04:07 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/12/2025 10:04:06 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/12/2025 10:04:05 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Christina Prete on behalf of EPC Stormwater Review
|
2/12/2025 10:04:03 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Justin Kilgore on behalf of PCD Project Manager
|
2/12/2025 10:04:01 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/12/2025 10:03:59 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Engineering Manager on behalf of PCD Engineering Division
|
2/12/2025 10:02:56 AM
|
Submission Triaged
|
2/12/2025 9:56:22 AM
|
Submission received from Applicant
|
2/10/2025 2:20:04 PM
|
Submission request sent to Applicant
|
2/10/2025 2:19:26 PM
|
Submission Triaged
|
2/10/2025 1:41:32 PM
|
Submission received from Applicant
|
1/31/2025 10:45:09 AM
|
Submission request sent to Applicant
|
1/31/2025 10:44:45 AM
|
Submission Triaged
|
1/31/2025 9:31:29 AM
|
Submission received from Applicant
|
1/3/2025 5:46:58 PM
|
Request for Review Comments returned by EPC Health Department
|
12/19/2024 12:39:20 PM
|
Request for Review Comments returned by PCD Administrative
|
12/18/2024 3:51:21 PM
|
Submission request sent to Applicant
|
12/18/2024 3:50:42 PM
|
Submission Triaged
|
12/18/2024 3:39:24 PM
|
Submission received from Applicant
|
12/18/2024 2:28:24 PM
|
Submission request sent to Applicant
|
12/18/2024 2:25:48 PM
|
Submission request sent to Applicant
|
12/18/2024 2:25:07 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/18/2024 11:24:20 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/17/2024 12:28:48 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
12/16/2024 11:39:55 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Tracey Garcia on behalf of PCD Administrative
|
12/16/2024 11:39:53 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Admin on behalf of PCD Administrative
|
12/16/2024 11:39:51 AM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Elena Krebs on behalf of PCD Administrative
|
12/16/2024 11:26:50 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/12/2024 12:10:40 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/10/2024 1:15:00 PM
|
Request for Review Comments returned by EPC Parks Department
|
12/10/2024 10:50:29 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
12/9/2024 2:25:14 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/5/2024 2:59:05 PM
|
Request for Review Comments returned by EPC Environmental Services
|
12/4/2024 12:41:25 PM
|
Request for Review Comments returned by Falcon School District 49
|
12/4/2024 8:41:10 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
12/3/2024 3:43:15 PM
|
Request for Review Comments returned by RBD Floodplain
|
12/3/2024 3:39:36 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by General Email on behalf of Mountain View Electric Association, Inc.
|
12/3/2024 3:39:34 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Evelyn galanephillips on behalf of Falcon School District 49
|
12/3/2024 3:39:32 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Trent Harwig on behalf of Falcon Fire Protection District
|
12/3/2024 3:39:30 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
12/3/2024 3:39:28 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:26 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:25 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Katie Miller on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:23 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Erica Carter on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:21 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:19 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:17 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:15 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Billy Richard on behalf of El Paso County Conservation Dist
|
12/3/2024 3:39:13 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Jeff Munger on behalf of Cherokee Metro Dist
|
12/3/2024 3:39:11 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Brandon Zembles on behalf of Cherokee Metro Dist
|
12/3/2024 3:39:09 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by on behalf of Central CO Conservation District
|
12/3/2024 3:39:07 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
12/3/2024 3:39:05 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
12/3/2024 3:39:03 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
12/3/2024 3:39:01 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Keith Curtis on behalf of RBD Floodplain
|
12/3/2024 3:38:59 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by on behalf of Pikes Peak Regional Building Department
|
12/3/2024 3:38:57 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
12/3/2024 3:38:55 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
12/3/2024 3:38:53 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/3/2024 3:38:51 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/3/2024 3:38:49 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Christina Prete on behalf of EPC Stormwater Review
|
12/3/2024 3:38:47 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
12/3/2024 3:38:46 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
12/3/2024 3:38:44 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
12/3/2024 3:38:42 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by on behalf of EPC Parks Department
|
12/3/2024 3:38:40 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Mike McCarthy on behalf of EPC Health Department
|
12/3/2024 3:38:38 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Catherine McGarvy on behalf of EPC Health Department
|
12/3/2024 3:38:36 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by HEAEH LandUse on behalf of EPC Health Department
|
12/3/2024 3:38:34 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Kathy Andrew on behalf of EPC Environmental Services
|
12/3/2024 3:38:32 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Justin Kilgore on behalf of PCD Project Manager
|
12/3/2024 3:38:28 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/3/2024 3:38:26 PM
|
Request for Review Comments email sent for Project Antelope Ridge PUD Amendment for review by Engineering Manager on behalf of PCD Engineering Division
|
12/3/2024 12:45:25 PM
|
Fees paid: 12/3/2024 (Receipt: 1009895)
|
11/21/2024 10:45:23 AM
|
Payment Request sent: 11/21/2024
|
11/21/2024 10:45:22 AM
|
File # Assigned: PUD243
|
11/21/2024 10:45:17 AM
|
Submission Triaged
|
11/20/2024 6:56:23 PM
|
Submission received from Applicant
|
10/25/2024 3:17:55 PM
|
Submission request sent to Applicant
|
10/25/2024 3:15:17 PM
|
Project Manager Assigned: Ashlyn Mathy
|
10/25/2024 3:15:17 PM
|
Project Created
|