Project Details

Search


File Number
CDR248
Project Name
Bar X FAWWA Segment 2 Pipeline
Description
Construct an approximate 4.8 mile long, 8 and 24-inch diameter water transmission line connecting Bar X Segment A1 to Winsome well site.
Parcels
5100000524 5100000524 5200000366 5200000366 5212000002 5212000002
Applicant
RESPEC - JDS-Hydro Consultants, Inc.
Troy Montague ( troy.montague@respec.com ) Troy Montague ( troy.montague@respec.com )
File Prefix
CDR - Construction Drawing Review
Year
2024
Project Manager
Edward Schoenheit
Status
Closed
Created
9/30/2024 8:47:05 AM

View: Review Comments


Approved Documents (7)

Link Document
View Grading & Erosion Control checklist
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Financial Assurance Forms
View PBMP Applicability Form
View SWMP checklist
View Grading & Erosion Control Plan
View Storm Water Management Plan (SWMP)


Review Documents (9)

Link Document Date
View Grading & Erosion Control checklist 2/6/2025 1:43:46 PM
View Legal Description (MS WORD Version required) 9/30/2024 1:45:03 PM
View Letter of Intent 1/22/2025 9:31:11 AM
View Erosion and Stormwater Quality Control Permit (ESQCP) 2/6/2025 1:43:45 PM
View Financial Assurance Forms 2/6/2025 1:43:43 PM
View PBMP Applicability Form 2/6/2025 1:43:46 PM
View SWMP checklist 1/22/2025 9:31:14 AM
View Grading & Erosion Control Plan 2/11/2025 3:29:20 PM
View Storm Water Management Plan (SWMP) 1/22/2025 9:31:12 AM



Events (74)

Date Comment
2/13/2025 4:55:28 PM Project Closed
2/13/2025 4:55:28 PM Project Approved: 2/13/2025
2/13/2025 11:09:44 AM Request for Review Comments returned by PCD Engineering Division
2/13/2025 9:49:42 AM Request for Review Comments returned by EPC Stormwater Review
2/11/2025 4:04:17 PM Submission Triaged
2/11/2025 3:29:25 PM Submission received from Applicant
2/11/2025 2:44:55 PM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/11/2025 2:44:54 PM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Glenn Reese on behalf of EPC Stormwater Review
2/11/2025 2:44:53 PM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Christina Prete on behalf of EPC Stormwater Review
2/11/2025 2:44:52 PM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Gilbert LaForce on behalf of PCD Engineering Division
2/11/2025 2:44:50 PM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Engineering Manager on behalf of PCD Engineering Division
2/11/2025 2:43:08 PM Submission request sent to Applicant
2/11/2025 2:41:44 PM Submission Triaged
2/6/2025 1:44:00 PM Submission received from Applicant
2/3/2025 2:03:41 PM Submission request sent to Applicant
2/3/2025 1:38:28 PM Request for Review Comments returned by PCD Engineering Division
2/3/2025 1:26:53 PM Request for Review Comments returned by EPC Stormwater Review
1/29/2025 8:31:27 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Mikayla Hartford on behalf of EPC Stormwater Review
1/29/2025 8:31:26 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Glenn Reese on behalf of EPC Stormwater Review
1/29/2025 8:31:25 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Christina Prete on behalf of EPC Stormwater Review
1/29/2025 8:31:24 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Gilbert LaForce on behalf of PCD Engineering Division
1/29/2025 8:31:22 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Engineering Manager on behalf of PCD Engineering Division
1/29/2025 8:26:39 AM Submission Triaged
1/27/2025 11:58:21 AM Submission received from Applicant
11/20/2024 10:51:33 AM Project Manager Assigned: Edward Schoenheit
11/12/2024 1:20:26 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
11/6/2024 3:58:56 PM Submission request sent to Applicant
10/30/2024 6:09:12 PM Request for Review Comments returned by PCD Engineering Division
10/30/2024 1:59:35 PM Request for Review Comments returned by EPC Stormwater Review
10/30/2024 9:14:27 AM Request for Review Comments returned by Colorado Springs Public Works
10/28/2024 11:17:48 AM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/25/2024 11:59:35 AM Request for Review Comments returned by Pikes Peak Regional Building Department
10/22/2024 2:29:46 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
10/21/2024 7:24:41 AM Request for Review Comments returned by PCD Project Manager
10/16/2024 8:58:03 AM Request for Review Comments returned by RBD Floodplain
10/16/2024 8:29:09 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by General Email on behalf of Mountain View Electric Association, Inc.
10/16/2024 8:29:07 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/16/2024 8:29:05 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/16/2024 8:29:03 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
10/16/2024 8:29:01 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Rae Carlson on behalf of Colorado Springs Public Works
10/16/2024 8:28:59 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Patrick Morris on behalf of Colorado Springs Public Works
10/16/2024 8:28:58 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by LaShunda Simpson on behalf of Colorado Springs Public Works
10/16/2024 8:28:56 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Jonathan Scherer on behalf of Colorado Springs Public Works
10/16/2024 8:28:54 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Joel Metzker on behalf of Colorado Springs Public Works
10/16/2024 8:28:52 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Joel Dagnillo on behalf of Colorado Springs Public Works
10/16/2024 8:28:50 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Jeff Bailey on behalf of Colorado Springs Public Works
10/16/2024 8:28:48 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Erin Powers on behalf of Colorado Springs Public Works
10/16/2024 8:28:47 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by General Email on behalf of Colorado Springs Public Works
10/16/2024 8:28:45 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Dana Davison on behalf of Colorado Springs Public Works
10/16/2024 8:28:43 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Brian Shevock on behalf of Colorado Springs Public Works
10/16/2024 8:28:41 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Clara Lucero on behalf of CIG Colorado Interstate Gas
10/16/2024 8:28:38 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
10/16/2024 8:28:37 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Bob Swatek on behalf of Black Hills Energy-Aquila
10/16/2024 8:28:35 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Adam Magoon on behalf of Black Hills Energy-Aquila
10/16/2024 8:28:33 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
10/16/2024 8:28:31 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Keith Curtis on behalf of RBD Floodplain
10/16/2024 8:28:29 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by on behalf of Pikes Peak Regional Building Department
10/16/2024 8:28:27 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Mikayla Hartford on behalf of EPC Stormwater Review
10/16/2024 8:28:25 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Glenn Reese on behalf of EPC Stormwater Review
10/16/2024 8:28:23 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Christina Prete on behalf of EPC Stormwater Review
10/16/2024 8:28:21 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by on behalf of EPC Public Works, County Engineer
10/16/2024 8:28:19 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by on behalf of EPC Public Works, County Engineer
10/16/2024 8:28:17 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Kari Parsons on behalf of PCD Project Manager
10/16/2024 8:28:13 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Gilbert LaForce on behalf of PCD Engineering Division
10/16/2024 8:28:11 AM Request for Review Comments email sent for Project Bar X FAWWA Segment 2 Pipeline for review by Engineering Manager on behalf of PCD Engineering Division
10/16/2024 8:24:23 AM Project Manager Assigned: Engineering Manager
10/16/2024 8:17:40 AM Project Manager Assigned: Kari Parsons
10/15/2024 2:56:31 PM Fees paid: 10/15/2024 (Receipt: 1009718)
10/14/2024 4:14:52 PM Payment Request sent: 10/14/2024
10/14/2024 4:14:51 PM File # Assigned: CDR248
10/14/2024 4:14:44 PM Submission Triaged
10/14/2024 1:03:00 PM Submission received from Applicant
9/30/2024 8:50:47 AM Submission request sent to Applicant
9/30/2024 8:47:16 AM Project Created