5/16/2025 11:40:03 AM
|
Project Closed
|
5/16/2025 11:40:03 AM
|
Project Approved: 5/16/2025
|
5/1/2025 2:48:04 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/1/2025 2:46:56 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of Woodmoor Improvement Association
|
5/1/2025 2:46:55 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Peter Susemihl on behalf of Walden Metropolitan Districts 1 and 2
|
5/1/2025 2:46:53 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Justin Kilgore on behalf of PCD Project Manager
|
5/1/2025 2:46:07 PM
|
Submission Triaged
|
5/1/2025 2:40:01 PM
|
Submission received from Applicant
|
5/1/2025 2:33:34 PM
|
Submission request sent to Applicant
|
5/1/2025 2:32:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/1/2025 11:57:16 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/1/2025 11:47:17 AM
|
Request for Review Comments email resent for Project Cathedral Rock Church for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/30/2025 2:08:28 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/30/2025 11:37:06 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/24/2025 3:14:44 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Justin Kilgore on behalf of PCD Project Manager
|
4/24/2025 3:14:43 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/24/2025 3:14:42 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Engineering Manager on behalf of PCD Engineering Division
|
4/24/2025 3:10:39 PM
|
Submission Triaged
|
4/23/2025 5:10:57 PM
|
Submission received from Applicant
|
4/22/2025 12:57:01 PM
|
Submission request sent to Applicant
|
4/21/2025 4:29:24 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
4/21/2025 1:06:27 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/21/2025 9:31:44 AM
|
Request for Review Comments email resent for Project Cathedral Rock Church for review by Engineering Manager on behalf of PCD Engineering Division
|
4/21/2025 9:23:23 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/21/2025 8:32:14 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/18/2025 11:01:21 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/7/2025 2:40:22 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/7/2025 2:40:21 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
4/7/2025 2:40:20 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
4/7/2025 2:40:19 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Glenn Reese on behalf of EPC Stormwater Review
|
4/7/2025 2:40:18 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Christina Prete on behalf of EPC Stormwater Review
|
4/7/2025 2:40:17 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Lori Seago on behalf of County Attorney - Development Review
|
4/7/2025 2:40:16 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Erika Keech on behalf of County Attorney - Development Review
|
4/7/2025 2:40:15 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by April Willie on behalf of County Attorney - Development Review
|
4/7/2025 2:40:12 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Justin Kilgore on behalf of PCD Project Manager
|
4/7/2025 2:40:11 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/7/2025 2:40:10 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Engineering Manager on behalf of PCD Engineering Division
|
4/7/2025 2:25:27 PM
|
Submission Triaged
|
4/7/2025 1:40:01 PM
|
Submission received from Applicant
|
4/7/2025 10:31:00 AM
|
Submission request sent to Applicant
|
3/10/2025 12:58:09 PM
|
Submission request sent to Applicant
|
3/10/2025 12:53:44 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/7/2025 2:26:13 PM
|
Request for Review Comments returned by USAFA Base Planner
|
3/6/2025 3:40:29 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/6/2025 1:28:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/4/2025 12:03:24 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/3/2025 4:21:06 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/3/2025 9:53:15 AM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Lori Seago on behalf of County Attorney - Development Review
|
3/3/2025 9:53:14 AM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Erika Keech on behalf of County Attorney - Development Review
|
3/3/2025 9:53:13 AM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by April Willie on behalf of County Attorney - Development Review
|
2/26/2025 12:49:46 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
2/20/2025 4:02:12 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Sabrina Untal on behalf of USAFA Base Planner
|
2/20/2025 4:02:11 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Matthew Fitzsimmons on behalf of USAFA Base Planner
|
2/20/2025 4:02:10 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Amy Kelley on behalf of USAFA Base Planner
|
2/20/2025 4:02:09 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of USAFA Base Planner
|
2/20/2025 4:02:08 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
2/20/2025 4:02:07 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
2/20/2025 4:02:06 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by General Email on behalf of Mountain View Electric Association, Inc.
|
2/20/2025 4:02:04 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/20/2025 4:02:03 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/20/2025 4:02:02 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Christina Prete on behalf of EPC Stormwater Review
|
2/20/2025 4:02:00 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Justin Kilgore on behalf of PCD Project Manager
|
2/20/2025 4:01:59 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/20/2025 4:01:58 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Engineering Manager on behalf of PCD Engineering Division
|
2/20/2025 3:55:55 PM
|
Submission Triaged
|
2/17/2025 4:53:07 PM
|
Submission received from Applicant
|
12/3/2024 10:52:19 AM
|
Project Manager Assigned: Lisa Elgin
|
11/18/2024 10:54:13 AM
|
Request for Review Comments returned by USAFA Base Planner
|
11/15/2024 6:06:54 PM
|
Request for Review Comments returned by EPC Health Department
|
11/15/2024 5:08:38 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Rachel Martell on behalf of USAFA Base Planner
|
11/15/2024 5:08:37 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by matthew. fitzsimmons on behalf of USAFA Base Planner
|
11/15/2024 5:08:35 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Amy Kelley on behalf of USAFA Base Planner
|
11/15/2024 5:08:33 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of USAFA Base Planner
|
10/18/2024 11:00:41 AM
|
Submission request sent to Applicant
|
10/17/2024 3:49:58 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/16/2024 4:03:35 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/16/2024 2:44:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/15/2024 10:29:20 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/10/2024 10:28:01 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/9/2024 7:10:10 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
10/7/2024 1:45:00 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
10/4/2024 2:46:45 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
10/4/2024 2:34:39 PM
|
Request for Review Comments returned by USAFA Base Planner
|
10/3/2024 1:36:26 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/3/2024 11:26:43 AM
|
Request for Review Comments returned by EPC Environmental Services
|
10/3/2024 9:30:38 AM
|
Request for Review Comments returned by EPC Parks Department
|
10/3/2024 9:10:57 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/2/2024 2:40:17 PM
|
Project Manager Assigned: Scott Weeks
|
10/2/2024 2:39:11 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
10/2/2024 2:39:09 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jessie Shaffer on behalf of Woodmoor Water and Sanitation District
|
10/2/2024 2:39:07 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of Woodmoor Improvement Association
|
10/2/2024 2:39:05 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Peter Susemihl on behalf of Walden Metropolitan Districts 1 and 2
|
10/2/2024 2:39:02 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Rachel Martell on behalf of USAFA Base Planner
|
10/2/2024 2:39:01 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by matthew. fitzsimmons on behalf of USAFA Base Planner
|
10/2/2024 2:38:59 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Amy Kelley on behalf of USAFA Base Planner
|
10/2/2024 2:38:57 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of USAFA Base Planner
|
10/2/2024 2:38:55 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
10/2/2024 2:38:53 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
10/2/2024 2:38:51 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
|
10/2/2024 2:38:49 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by General Email on behalf of Mountain View Electric Association, Inc.
|
10/2/2024 2:38:46 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Jeff Hodge on behalf of Donala Water and San Dist
|
10/2/2024 2:38:45 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Christina Hawker on behalf of Donala Water and San Dist
|
10/2/2024 2:38:42 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
10/2/2024 2:38:41 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
10/2/2024 2:38:39 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
10/2/2024 2:38:36 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
10/2/2024 2:38:34 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
10/2/2024 2:38:32 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
10/2/2024 2:38:30 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of Pikes Peak Regional Building Department
|
10/2/2024 2:38:28 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/2/2024 2:38:26 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
10/2/2024 2:38:24 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
10/2/2024 2:38:22 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
10/2/2024 2:38:20 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
10/2/2024 2:38:18 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
10/2/2024 2:38:16 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
10/2/2024 2:38:14 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Glenn Reese on behalf of EPC Stormwater Review
|
10/2/2024 2:38:12 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Christina Prete on behalf of EPC Stormwater Review
|
10/2/2024 2:38:10 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by on behalf of EPC Parks Department
|
10/2/2024 2:38:08 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Mike McCarthy on behalf of EPC Health Department
|
10/2/2024 2:38:06 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Catherine McGarvy on behalf of EPC Health Department
|
10/2/2024 2:38:04 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by HEAEH LandUse on behalf of EPC Health Department
|
10/2/2024 2:38:02 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/2/2024 2:37:58 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Kari Parsons on behalf of PCD Project Manager
|
10/2/2024 2:37:56 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Gilbert LaForce on behalf of PCD Engineering Division
|
10/2/2024 2:37:54 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church for review by Engineering Manager on behalf of PCD Engineering Division
|
9/30/2024 9:58:29 AM
|
Project Manager Assigned: Kari Parsons
|
9/30/2024 9:03:49 AM
|
Fees paid: 9/30/2024 (Receipt: 1009637)
|
9/29/2024 7:10:41 PM
|
Payment Request sent: 9/29/2024
|
9/29/2024 7:10:41 PM
|
File # Assigned: PPR2436
|
9/29/2024 7:10:39 PM
|
Submission Triaged
|
9/27/2024 4:42:11 PM
|
Submission received from Applicant
|
8/23/2024 2:58:14 PM
|
Submission request sent to Applicant
|
8/23/2024 2:53:56 PM
|
Project Created
|