Project Details

Search


File Number
PPR2440
Project Name
I68 Training Facility Phase 1 Site Development Plan
Description
Site development plan for outdoor shooting range. Special use approval AL249. Phase 1 includes ranges and parking areas, but no structures.
Parcels
1300000712 1300000712
Applicant
M.V.E., Inc.
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
EA Number
EA2462
File Prefix
PPR - Plot Plan Review
Year
2024
Project Manager
Lacey Dean
Status
Closed
Created
5/17/2024 3:57:12 PM

View: Review Comments


Approved Documents (8)

Link Document
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Financial Assurance Forms
View PBMP Applicability Form
View Grading & Erosion Control Plan
View Site Development Plan
View Storm Water Management Plan (SWMP)
View Drainage Report - Final
View Traffic Memo


Additional Documents (2)

Link Document Comment
View Comment from EPC Sherriffs Office
View Signed ESQ


Review Documents (17)

Link Document Date
View Application/Petition Form 10/31/2024 5:16:40 PM
View Grading & Erosion Control checklist 12/9/2024 12:26:43 PM
View Legal Description (MS WORD Version required) 10/31/2024 5:16:43 PM
View Letter of Intent 2/17/2025 2:36:36 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 2/17/2025 2:36:37 PM
View Financial Assurance Forms 2/17/2025 2:36:33 PM
View PBMP Applicability Form 12/9/2024 12:26:44 PM
View SWMP checklist 12/9/2024 12:26:43 PM
View Grading & Erosion Control Plan 3/16/2025 9:58:17 PM
View Landscape Plan drawings 2/17/2025 2:36:36 PM
View Site Development Plan 2/17/2025 2:36:38 PM
View Storm Water Management Plan (SWMP) 12/9/2024 12:26:41 PM
View Soils Report Pursuant to Appendix C of the ECM 10/31/2024 5:16:49 PM
View Deviation Request 2/17/2025 2:36:39 PM
View Drainage Report - Final 3/21/2025 10:31:46 AM
View Traffic Memo 2/17/2025 2:36:37 PM
View Traffic study Comment Responses 1/21/2025 9:43:37 AM



Events (106)

Date Comment
4/9/2025 4:11:05 PM Project Closed
4/9/2025 4:11:05 PM Project Approved: 4/9/2025
4/1/2025 12:40:49 PM Project Ready for Approval requests. Review Comment period is complete.
4/1/2025 10:32:00 AM Submission Triaged
4/1/2025 9:55:09 AM Submission received from Applicant
3/27/2025 4:45:08 PM Submission request sent to Applicant
3/27/2025 1:56:38 PM Request for Review Comments returned by PCD Engineering Division
3/26/2025 4:07:18 PM Request for Review Comments returned by EPC Stormwater Review
3/24/2025 10:46:51 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
3/24/2025 10:46:50 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
3/24/2025 10:46:49 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
3/24/2025 10:46:47 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
3/24/2025 10:46:46 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
3/24/2025 10:44:51 AM Submission Triaged
3/21/2025 10:32:49 AM Submission received from Applicant
3/20/2025 12:55:06 PM Request for Review Comments returned by Pikes Peak Regional Building Department
3/20/2025 7:59:24 AM Submission request sent to Applicant
3/19/2025 5:27:10 PM Request for Review Comments returned by PCD Engineering Division
3/19/2025 5:25:17 PM Request for Review Comments returned by EPC Stormwater Review
3/18/2025 8:10:46 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
3/18/2025 8:10:45 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
3/18/2025 8:10:44 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
3/18/2025 8:10:43 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
3/18/2025 8:10:41 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
3/18/2025 8:10:40 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
3/18/2025 8:09:33 AM Submission Triaged
3/16/2025 9:59:17 PM Submission received from Applicant
3/10/2025 5:33:57 PM Submission request sent to Applicant
3/10/2025 5:28:55 PM Request for Review Comments returned by PCD Engineering Division
3/5/2025 5:48:22 PM Request for Review Comments returned by PCD Project Manager
3/4/2025 2:43:22 PM Request for Review Comments returned by EPC Stormwater Review
2/18/2025 10:20:04 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/18/2025 10:20:03 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
2/18/2025 10:20:02 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
2/18/2025 10:20:00 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
2/18/2025 10:19:58 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
2/18/2025 10:19:57 AM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
2/18/2025 10:15:01 AM Submission Triaged
2/17/2025 2:37:44 PM Submission received from Applicant
2/6/2025 5:50:04 PM Submission request sent to Applicant
2/6/2025 5:46:55 PM Request for Review Comments returned by PCD Project Manager
2/6/2025 5:32:31 PM Request for Review Comments returned by PCD Engineering Division
2/3/2025 12:50:42 PM Request for Review Comments returned by EPC Stormwater Review
1/21/2025 12:35:15 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
1/21/2025 12:35:14 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
1/21/2025 12:35:13 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
1/21/2025 12:35:11 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
1/21/2025 12:35:09 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
1/21/2025 12:35:08 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
1/21/2025 12:21:43 PM Submission Triaged
1/21/2025 9:51:24 AM Submission received from Applicant
12/23/2024 4:21:08 PM Submission request sent to Applicant
12/23/2024 9:43:21 AM Request for Review Comments returned by PCD Project Manager
12/19/2024 3:59:48 PM Request for Review Comments returned by PCD Engineering Division
12/19/2024 3:51:50 PM Request for Review Comments email resent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
12/19/2024 10:49:09 AM Request for Review Comments returned by PCD Engineering Division
12/16/2024 10:20:39 AM Request for Review Comments returned by EPC Stormwater Review
12/11/2024 4:20:50 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Jeff Kramer on behalf of EPC Sheriff's Department
12/11/2024 4:20:48 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
12/11/2024 4:20:47 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Andrew Prehm on behalf of EPC Sheriff's Department
12/9/2024 2:40:13 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
12/9/2024 2:40:11 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
12/9/2024 2:40:09 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
12/9/2024 2:40:06 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
12/9/2024 2:40:00 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
12/9/2024 2:39:59 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
12/9/2024 2:17:35 PM Submission Triaged
12/9/2024 12:27:19 PM Submission received from Applicant
12/6/2024 11:54:34 AM Request for Review Comments returned by EPC Health Department
11/21/2024 7:24:07 AM Submission request sent to Applicant
11/20/2024 10:17:17 PM Request for Review Comments returned by PCD Engineering Division
11/20/2024 5:28:46 PM Request for Review Comments returned by PCD Project Manager
11/20/2024 5:22:14 PM Request for Review Comments returned by EPC Stormwater Review
11/18/2024 2:31:22 PM Request for Review Comments returned by Pikes Peak Regional Building Department
11/18/2024 10:40:22 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
11/12/2024 1:26:53 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
11/5/2024 3:50:23 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
11/5/2024 3:50:21 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Linda Miller on behalf of Calhan SD RJ1
11/5/2024 3:50:19 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Shane Gattis on behalf of Calhan Fire Protection District
11/5/2024 3:50:17 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
11/5/2024 3:50:15 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
11/5/2024 3:50:13 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
11/5/2024 3:50:11 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
11/5/2024 3:50:09 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
11/5/2024 3:50:07 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
11/5/2024 3:50:05 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
11/5/2024 3:50:03 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
11/5/2024 3:50:01 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
11/5/2024 3:49:59 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
11/5/2024 3:49:57 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
11/5/2024 3:49:54 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
11/5/2024 3:49:51 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
11/5/2024 3:49:49 PM Request for Review Comments email sent for Project I68 Training Facility Phase 1 Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
11/5/2024 3:48:25 PM Project Manager Assigned: Lacey Dean
11/5/2024 11:49:17 AM Fees paid: 11/5/2024 (Receipt: 1009802)
11/5/2024 11:18:19 AM Payment Request sent: 11/5/2024
11/4/2024 12:22:33 PM Payment Request sent: 11/4/2024
11/4/2024 12:22:32 PM File # Assigned: PPR2440
11/4/2024 12:22:22 PM Submission Triaged
10/31/2024 5:17:13 PM Submission received from Applicant
8/22/2024 11:00:36 AM Set Applicant to M.V.E., Inc.
5/30/2024 11:21:37 AM Submission request sent to Applicant
5/29/2024 2:58:28 PM Submission request sent to Applicant
5/17/2024 3:57:17 PM Project Manager Assigned: Ryan Howser
5/17/2024 3:57:17 PM EA Assigned: EA2462
5/17/2024 3:57:17 PM Project Created