| 1/23/2025 1:07:00 PM | Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 1/21/2025 3:36:10 PM | Submission request sent to Applicant | 
                
                    | 1/21/2025 3:31:26 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 1/16/2025 5:30:20 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 1/16/2025 1:01:18 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 1/14/2025 1:04:54 PM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 1/7/2025 8:24:16 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 1/7/2025 8:24:15 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by  on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 1/7/2025 8:24:14 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 1/7/2025 8:24:13 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 1/7/2025 8:24:12 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 1/7/2025 8:24:11 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 1/7/2025 8:24:09 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 1/7/2025 8:24:07 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 1/7/2025 8:24:05 AM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 1/7/2025 8:11:59 AM | Submission Triaged | 
                
                    | 1/3/2025 2:13:02 PM | Submission received from Applicant | 
                
                    | 11/22/2024 6:47:02 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 11/13/2024 11:17:18 AM | Submission request sent to Applicant | 
                
                    | 11/13/2024 11:12:50 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 11/13/2024 10:47:55 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 11/13/2024 9:25:57 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 11/13/2024 9:17:57 AM | Request for Review Comments email resent for Project Owl Marketplace - Starbucks Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 11/12/2024 5:30:32 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 11/12/2024 1:21:38 PM | Request for Review Comments returned by Upper Black Squirrel Creek GWMD | 
                
                    | 11/12/2024 12:44:50 PM | Request for Review Comments returned by Falcon Fire Protection District | 
                
                    | 11/11/2024 9:55:08 AM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 11/8/2024 2:46:10 PM | Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 11/1/2024 9:31:16 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 10/31/2024 12:00:49 PM | Request for Review Comments returned by Falcon School District 49 | 
                
                    | 10/28/2024 1:10:19 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 10/28/2024 1:10:17 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49 | 
                
                    | 10/28/2024 1:10:15 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District | 
                
                    | 10/28/2024 1:10:13 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Curtis Kauffman on behalf of Falcon Fire Protection District | 
                
                    | 10/28/2024 1:10:11 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 10/28/2024 1:10:09 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by  on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources) | 
                
                    | 10/28/2024 1:10:07 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD | 
                
                    | 10/28/2024 1:10:05 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 10/28/2024 1:10:03 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 10/28/2024 1:10:01 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 10/28/2024 1:09:59 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 10/28/2024 1:09:57 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department | 
                
                    | 10/28/2024 1:09:55 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 10/28/2024 1:09:53 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department | 
                
                    | 10/28/2024 1:09:50 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 10/28/2024 1:09:48 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 10/28/2024 1:09:46 PM | Request for Review Comments email sent for Project Owl Marketplace - Starbucks Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 10/25/2024 2:44:54 PM | Fees paid: 10/25/2024 (Receipt: 1009764) | 
                
                    | 10/24/2024 12:06:53 PM | Payment Request sent: 10/24/2024 | 
                
                    | 10/24/2024 12:06:53 PM | File # Assigned: PPR2439 | 
                
                    | 10/24/2024 12:06:46 PM | Submission Triaged | 
                
                    | 10/24/2024 8:47:07 AM | Submission received from Applicant | 
                
                    | 5/16/2024 1:42:15 PM | Submission request sent to Applicant | 
                
                    | 5/16/2024 12:14:17 PM | Project Manager Assigned: Lacey Dean | 
                
                    | 5/16/2024 12:14:17 PM | EA Assigned: EA2453 | 
                
                    | 5/16/2024 12:14:17 PM | Project Created |