9/26/2024 12:08:59 PM
|
Project Closed
|
9/26/2024 12:08:59 PM
|
Project Approved: 9/26/2024
|
8/27/2024 11:55:49 AM
|
Project reopened for Approval requests
|
8/27/2024 11:55:36 AM
|
Project Closed
|
8/27/2024 11:55:36 AM
|
Project Approved: 8/27/2024
|
8/23/2024 3:27:27 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
8/6/2024 3:31:21 PM
|
Request for Review Comments returned by Falcon School District 49
|
8/6/2024 11:06:02 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
8/6/2024 10:53:49 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
8/6/2024 8:29:03 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
8/6/2024 8:13:59 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
7/30/2024 11:31:28 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
7/29/2024 11:27:18 AM
|
Submission request canceled
|
7/29/2024 11:26:03 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
7/29/2024 11:26:01 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/29/2024 11:25:59 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/29/2024 11:25:57 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
7/29/2024 11:25:55 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
7/29/2024 11:25:53 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
7/29/2024 11:25:51 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
7/29/2024 11:25:49 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
7/29/2024 11:25:47 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
7/29/2024 11:24:36 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by PJ Langmaid on behalf of Black Forest Fire Protection District
|
7/29/2024 11:24:34 AM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Black Forest Fire Chief on behalf of Black Forest Fire Protection District
|
7/23/2024 10:16:25 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
7/23/2024 8:05:58 AM
|
Submission request sent to Applicant
|
7/23/2024 8:05:17 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/21/2024 4:31:02 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
7/18/2024 3:21:40 PM
|
Request for Review Comments returned by EPC Parks Department
|
7/18/2024 1:52:42 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/17/2024 2:53:37 PM
|
Request for Review Comments returned by EPC Environmental Services
|
7/16/2024 5:10:02 PM
|
Submission Triaged
|
7/16/2024 5:02:38 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/16/2024 4:56:16 PM
|
Submission received from Applicant
|
7/16/2024 4:53:23 PM
|
Submission request sent to Applicant
|
7/16/2024 4:44:56 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Shanna Smith on behalf of EPC Finance
|
7/16/2024 4:44:54 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Nikki Simmons on behalf of EPC Finance
|
7/16/2024 2:39:41 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
7/16/2024 2:39:39 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Evelyn galanephillips on behalf of Falcon School District 49
|
7/16/2024 2:39:37 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:35 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:33 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Katie Miller on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:31 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Erica Carter on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:29 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:27 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:25 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Billy Richard on behalf of El Paso County Conservation Dist
|
7/16/2024 2:39:23 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:21 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Rae Carlson on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:19 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Patrick Morris on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:17 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:16 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jonathan Scherer on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:14 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Joel Metzker on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:12 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Joel Dagnillo on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:10 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jeff Bailey on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:08 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Erin Powers on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:06 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by General Email on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:04 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Dana Davison on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:02 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Brian Shevock on behalf of Colorado Springs Public Works
|
7/16/2024 2:39:00 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
7/16/2024 2:38:58 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kevin Brown on behalf of Cherokee Metro Dist
|
7/16/2024 2:38:56 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jeff Munger on behalf of Cherokee Metro Dist
|
7/16/2024 2:38:54 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by CONNIE HUGHES on behalf of Cherokee Metro Dist
|
7/16/2024 2:38:52 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Brandon Zembles on behalf of Cherokee Metro Dist
|
7/16/2024 2:38:50 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
7/16/2024 2:38:48 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
7/16/2024 2:38:46 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by on behalf of EPC Parks Department
|
7/16/2024 2:38:44 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kathy Andrew on behalf of EPC Environmental Services
|
7/16/2024 2:38:42 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Lori Seago on behalf of County Attorney - Development Review
|
7/16/2024 2:38:40 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Erika Keech on behalf of County Attorney - Development Review
|
7/16/2024 2:38:38 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by April Willie on behalf of County Attorney - Development Review
|
7/16/2024 2:38:36 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kari Parsons on behalf of PCD Project Manager
|
7/16/2024 2:38:34 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/16/2024 2:38:32 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Engineering Manager on behalf of PCD Engineering Division
|
7/16/2024 2:34:57 PM
|
Submission Triaged
|
7/16/2024 2:03:24 PM
|
Submission received from Applicant
|
7/16/2024 1:48:24 PM
|
Submission request sent to Applicant
|
7/16/2024 1:32:02 PM
|
Submission request sent to Applicant
|
7/16/2024 12:20:01 PM
|
Submission request sent to Applicant
|
6/20/2024 1:39:03 PM
|
Request for Review Comments returned by EPC Parks Department
|
6/11/2024 10:54:39 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/9/2024 7:16:15 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
6/7/2024 11:48:00 AM
|
Request for Review Comments returned by Falcon School District 49
|
6/6/2024 12:40:08 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/5/2024 11:46:11 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/5/2024 8:07:33 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
6/4/2024 8:20:25 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
5/21/2024 1:40:03 PM
|
Request for Review Comments returned by EPC Environmental Services
|
5/20/2024 4:08:41 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/17/2024 10:10:16 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
5/17/2024 9:42:43 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
5/15/2024 3:23:16 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
5/15/2024 3:23:14 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/15/2024 3:23:12 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Evelyn galanephillips on behalf of Falcon School District 49
|
5/15/2024 3:23:10 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
5/15/2024 3:23:08 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Katie Miller on behalf of El Paso County Conservation Dist
|
5/15/2024 3:23:06 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
5/15/2024 3:23:04 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/15/2024 3:23:02 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/15/2024 3:23:00 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:58 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Rae Carlson on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:57 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Patrick Morris on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:55 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:53 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jonathan Scherer on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:51 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Joel Metzker on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:49 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Joel Dagnillo on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:47 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jeff Bailey on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:46 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Erin Powers on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:44 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by General Email on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:42 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Dana Davison on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:40 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Brian Shevock on behalf of Colorado Springs Public Works
|
5/15/2024 3:22:38 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
5/15/2024 3:22:36 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kevin Brown on behalf of Cherokee Metro Dist
|
5/15/2024 3:22:34 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Jeff Munger on behalf of Cherokee Metro Dist
|
5/15/2024 3:22:32 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by CONNIE HUGHES on behalf of Cherokee Metro Dist
|
5/15/2024 3:22:30 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Brandon Zembles on behalf of Cherokee Metro Dist
|
5/15/2024 3:22:28 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
5/15/2024 3:22:26 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
5/15/2024 3:22:24 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
5/15/2024 3:22:22 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
5/15/2024 3:22:20 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
5/15/2024 3:22:19 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
5/15/2024 3:22:17 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
5/15/2024 3:22:15 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
5/15/2024 3:22:13 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
5/15/2024 3:22:11 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by on behalf of EPC Parks Department
|
5/15/2024 3:22:09 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Shanna Smith on behalf of EPC Finance
|
5/15/2024 3:22:07 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Nikki Simmons on behalf of EPC Finance
|
5/15/2024 3:22:05 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/15/2024 3:22:03 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Lori Seago on behalf of County Attorney - Development Review
|
5/15/2024 3:22:01 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Erika Keech on behalf of County Attorney - Development Review
|
5/15/2024 3:21:59 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by April Willie on behalf of County Attorney - Development Review
|
5/15/2024 3:21:57 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Kari Parsons on behalf of PCD Project Manager
|
5/15/2024 3:21:55 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/15/2024 3:21:53 PM
|
Request for Review Comments email sent for Project Prairie Ridge Metropolitan Districts Nos. 1-3 for review by Engineering Manager on behalf of PCD Engineering Division
|
5/15/2024 2:53:52 PM
|
Fees paid: 5/15/2024 (Receipt: 1009144)
|
5/15/2024 11:55:06 AM
|
Payment Request sent: 5/15/2024
|
5/15/2024 11:55:06 AM
|
File # Assigned: ID243
|
5/15/2024 11:54:57 AM
|
Submission Triaged
|
5/15/2024 11:12:11 AM
|
Submission received from Applicant
|
5/2/2024 2:11:47 PM
|
Submission request sent to Applicant
|
5/2/2024 2:09:46 PM
|
Project Manager Assigned: Kari Parsons
|
5/2/2024 2:09:46 PM
|
Project Created
|