4/24/2024 9:18:14 AM
|
Project Closed
|
4/24/2024 9:18:14 AM
|
Project Approved: 4/24/2024
|
4/9/2024 3:52:28 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
4/9/2024 3:51:42 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/4/2024 8:57:15 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/28/2024 8:29:52 AM
|
Request for Review Comments email sent for Project OAR: Calhan Commons for review by on behalf of EPC Public Works, County Engineer
|
3/28/2024 8:29:50 AM
|
Request for Review Comments email sent for Project OAR: Calhan Commons for review by on behalf of EPC Public Works, County Engineer
|
3/28/2024 8:29:48 AM
|
Request for Review Comments email sent for Project OAR: Calhan Commons for review by Kari Parsons on behalf of PCD Project Manager
|
3/28/2024 8:29:44 AM
|
Request for Review Comments email sent for Project OAR: Calhan Commons for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/28/2024 8:29:42 AM
|
Request for Review Comments email sent for Project OAR: Calhan Commons for review by Engineering Manager on behalf of PCD Engineering Division
|
3/27/2024 2:17:57 PM
|
No Fees
|
3/27/2024 2:17:57 PM
|
File # Assigned: OAR2414
|
3/27/2024 2:17:57 PM
|
Project Manager Assigned: Ashlyn Mathy
|
3/27/2024 2:17:57 PM
|
Project Created
|