Project Details

Search


File Number
SKP242
Project Name
Flying Horse East Phase 1 Sketch Plan
Description
Approximately 1800 acres (final boundary and acreage not determined at this time) Mix of low, medium and high density residential with Business Park, Commercial uses, with a potential school complex and hotel site. Densities and total unit count is not final at this time but estimated to be 2000-3000 units
Parcels
4400000360 4400000360 4400000374 4400000374 4400000438 4400000438
Applicant
HR Green Inc.
Phil Stuepfert ( pstuepfert@hrgreen.com )
(630) 220-7936
Phil Stuepfert ( pstuepfert@hrgreen.com )
(630) 220-7936
EA Number
EA2425
File Prefix
SKP - Sketch Plan
Year
2024
Project Manager
Ryan Howser
Status
Closed
Created
2/29/2024 3:33:14 PM

View: Review Comments


Approved Documents (3)

Link Document
View Sketch Plan Drawing(s)
View Traffic Impact Study
View Master Development Drainage Plan (MDDP)


Additional Documents (29)

Link Document Comment
View Notice of Application Notice of Application letters were mailed to surrounding property owners on 02/05/2025. JM
View Mailing Labels Mailing Labels for the 35 surrounding property owners that received notices. Cost = $24.15. JM
View Selected Range Selected Range was 500 feet. JM
View Hearing Notice & Vicinity Map Hearing Notice for the Planning Commission hearing on 06/19/2025. JM
View Mailing Labels - Hearing Notice Mailing Labels for the 36 surrounding property owners that received notices. PCD mailed the letters on 06/05/2025. Cost = $24.84. JM
View Selected Range - Hearing Notice Selected Range was 500 feet. JM
View PC Poster Poster for the Planning Commission hearing on 06/19/2025. JM
View PC Hearing Agenda Hearing Agenda for the Planning Commission hearing on 06/19/2025. JM
View Notarized Affidavit for Notice of Public Hearing
View Posters on Property
View SPace Base Delta 1 Letter Dated May 21, 2025
View PC Staff Report - final with attachments Staff Report for the Planning Commission hearing on 06/19/2025. JM
View Returned Notice - 6/16/25
View Signed PC Resolution Recommendation from the Planning Commission hearing on 06/19/2025. JM
View Shelstad, D - Opposition
View FHE - Schriever Correspondence_07-11-2025
View Adopted PC Minutes Adopted Minutes from the Planning Commission hearing on 06/19/2025. JM
View Hearing Notice & Vicinity Map Hearing Notice for the Board of County Commissioners hearing on 08/28/2025. JM
View Mailing Labels - Hearing Notice Mailing Labels for the 36 surrounding property owners that received notices. PCD mailed the letters on 08/07/2025. Cost = $26.64. JM
View Selected Range - Hearing Notice Selected Range was 500 feet. JM
View BOCC Poster Poster for the Board of County Commissioners hearing on 08/28/2025. JM
View Notarized Affidavit for Notice of Public Hearing
View Posters on Property
View PC Staff Presentation
View PC Applicant Presentation
View BOCC Staff Report - final with attachments Staff Report for the Board of County Commissioners hearing on 08/28/2025. JM
View BOCC Hearing Agenda Hearing Agenda for the Board of County Commissioners hearing on 08/28/2025. JM
View Returned Notices Returned Notice - Received 08/25/2025 (1)
View Recorded BOCC Resolution SKP242 RECORDED BOCC RESOLUTION - 25-246


Review Documents (28)

Link Document Date
View Application/Petition Form 12/20/2024 9:59:42 AM
View Legal Description (MS WORD Version required) 12/20/2024 9:38:58 AM
View Letter of Intent 4/23/2025 3:30:19 PM
View Title Commitment (Current within 30 days of submittal) 12/20/2024 12:21:41 PM
View Mineral Rights Certification 12/20/2024 12:06:28 PM
View Sketch Plan Drawing(s) 10/9/2025 3:57:12 PM
View Commitment letter from waste water service provider 12/20/2024 1:23:26 PM
View Commitment letter from water service provider 12/20/2024 9:38:57 AM
View Electric Provider Commitment Letter 12/20/2024 9:38:58 AM
View Natural Gas Commitment Letter 12/20/2024 12:11:53 PM
View Natural Features Report 12/20/2024 9:38:59 AM
View Soils & Geology Report 12/20/2024 1:23:27 PM
View Traffic Impact Study 10/9/2025 3:57:11 PM
View Wastewater Disposal Report 4/23/2025 2:50:53 PM
View Water Resources Report 4/27/2025 8:55:28 PM
View Water Supply Information Summary 4/23/2025 5:35:58 PM
View CDOT response to comments 12/20/2024 5:48:11 PM
View Impact Identification Statement 4/23/2025 2:42:45 PM
View Master Development Drainage Plan (MDDP) 4/23/2025 5:18:41 PM
View New mineral rights certificate 3/14/2025 8:31:36 AM
View Response to CDOT comments 3/14/2025 8:31:35 AM
View Response to Colorado Parks and Wildlife comments 3/14/2025 2:12:58 PM
View Response to MDDP comments 4/23/2025 5:18:48 PM
View Response to Schriever Air Force Base comments 3/16/2025 5:07:32 PM
View Response to Sketch Plan comments 4/23/2025 2:42:48 PM
View Response to TIS comments 4/23/2025 2:42:47 PM
View Response to wastewater report comments 4/23/2025 2:50:54 PM
View Response to water report comments 4/24/2025 2:22:24 PM



Events (156)

Date Comment
11/7/2025 7:45:31 AM Project Closed
11/7/2025 7:45:31 AM Project Approved: 11/7/2025
10/24/2025 2:09:51 PM Request for Review Comments returned by PCD Engineering Division
10/10/2025 8:06:26 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
10/10/2025 8:06:25 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division
10/10/2025 8:05:48 AM Submission Triaged
10/9/2025 3:58:40 PM Submission received from Applicant
9/18/2025 3:49:07 PM Submission request sent to Applicant
8/12/2025 11:47:22 AM Fees paid: 8/12/2025 (Receipt: 1010909)
8/12/2025 9:21:34 AM Payment Request sent: 8/12/2025
6/13/2025 2:32:56 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
6/13/2025 2:27:01 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
6/13/2025 2:27:00 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
6/13/2025 2:26:59 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
6/6/2025 9:13:08 AM Fees paid: 6/6/2025 (Receipt: 1010635)
6/5/2025 4:16:05 PM Payment Request sent: 6/5/2025
5/16/2025 1:40:39 PM Submission request sent to Applicant
5/16/2025 12:19:47 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
5/16/2025 12:00:03 PM Request for Review Comments returned by Schriever AFB
5/16/2025 9:27:25 AM Submission request sent to Applicant
5/14/2025 3:16:57 PM Request for Review Comments returned by PCD Engineering Division
5/14/2025 3:00:16 PM Request for Review Comments email resent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division
5/14/2025 2:24:03 PM Request for Review Comments returned by PCD Engineering Division
5/12/2025 1:34:53 PM Request for Review Comments returned by Colorado Springs Planning & Community Development
5/9/2025 3:03:28 PM Request for Review Comments returned by PCD Project Manager
5/7/2025 1:26:02 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
5/7/2025 1:26:01 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Drew Fox on behalf of Colorado Springs Planning & Community Development
5/7/2025 10:04:24 AM Request for Review Comments returned by EPC Environmental Services
4/30/2025 2:20:32 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
4/30/2025 2:20:31 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
4/30/2025 2:20:30 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
4/30/2025 2:20:29 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services
4/30/2025 2:20:27 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager
4/30/2025 2:20:26 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
4/30/2025 2:20:25 PM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division
4/30/2025 2:18:52 PM Submission Triaged
4/27/2025 9:13:10 PM Submission received from Applicant
4/25/2025 12:19:08 PM Submission request sent to Applicant
4/25/2025 12:18:53 PM Submission Triaged
4/24/2025 2:22:30 PM Submission received from Applicant
4/14/2025 3:27:59 PM Request for Review Comments returned by Colorado Division of Water Resources
4/8/2025 4:56:23 PM Submission request sent to Applicant
4/8/2025 4:54:53 PM Request for Review Comments returned by PCD Project Manager
4/8/2025 4:08:25 PM Request for Review Comments returned by PCD Engineering Division
4/8/2025 6:05:23 AM Request for Review Comments returned by EPC Stormwater Review
4/2/2025 12:44:27 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
3/24/2025 2:45:21 PM Request for Review Comments returned by EPC Parks Department
3/19/2025 12:22:45 PM Request for Review Comments returned by EPC Environmental Services
3/19/2025 9:51:27 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
3/18/2025 9:03:00 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Darren Horstmeier on behalf of Schriever AFB
3/18/2025 9:02:59 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michael Henley on behalf of Ellicott Fire Protection District
3/18/2025 9:02:58 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Norma Houghton on behalf of Ellicott Fire Protection District
3/18/2025 9:02:57 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
3/18/2025 9:02:56 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
3/18/2025 9:02:54 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
3/18/2025 9:02:53 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
3/18/2025 9:02:51 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
3/18/2025 9:02:50 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
3/18/2025 9:02:49 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
3/18/2025 9:02:48 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
3/18/2025 9:02:47 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn Reese on behalf of EPC Stormwater Review
3/18/2025 9:02:46 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christina Prete on behalf of EPC Stormwater Review
3/18/2025 9:02:45 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of EPC Parks Department
3/18/2025 9:02:44 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services
3/18/2025 9:02:42 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager
3/18/2025 9:02:40 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
3/18/2025 9:02:39 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division
3/18/2025 9:00:25 AM Submission Triaged
3/16/2025 5:07:38 PM Submission received from Applicant
2/12/2025 4:10:25 PM Request for Review Comments returned by Parks Advisory Board
2/10/2025 1:54:48 PM Fees paid: 2/10/2025 (Receipt: 1010149)
2/10/2025 1:48:59 PM Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
2/7/2025 12:10:45 PM Request for Review Comments returned by Ellicott Fire Protection District
2/5/2025 4:09:39 PM Payment Request sent: 2/5/2025
2/5/2025 4:01:18 PM Request for Review Comments returned by PCD Administrative Notice
2/3/2025 2:52:36 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
1/31/2025 3:11:27 PM Request for Review Comments sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of PCD Administrative Notice
1/31/2025 7:38:32 AM Submission request sent to Applicant
1/30/2025 10:35:19 PM Request for Review Comments returned by PCD Engineering Division
1/30/2025 4:56:11 PM Request for Review Comments returned by PCD Project Manager
1/30/2025 4:04:38 PM Request for Review Comments returned by Schriever AFB
1/30/2025 3:30:51 PM Request for Review Comments returned by EPC Stormwater Review
1/26/2025 5:19:20 PM Request for Review Comments returned by Colorado Parks and Wildlife
1/24/2025 11:12:15 AM Request for Review Comments returned by EPC Parks Department
1/24/2025 9:35:04 AM Request for Review Comments returned by Colorado Division of Water Resources
1/22/2025 11:46:45 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
1/22/2025 11:46:44 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
1/22/2025 10:51:02 AM Request for Review Comments returned by Pikes Peak Regional Building Department
1/22/2025 9:13:00 AM Request for Review Comments returned by Colorado Geological Survey
1/19/2025 5:19:52 PM Request for Review Comments returned by EPC Health Department
1/15/2025 11:51:43 AM Request for Review Comments returned by County Attorney - Development Review
1/9/2025 1:20:07 PM Request for Review Comments returned by 911 Authority - El Paso/Teller County
1/9/2025 10:16:35 AM Request for Review Comments returned by EPC Environmental Services
1/6/2025 9:26:45 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
1/2/2025 2:01:00 PM Request for Review Comments returned by County Attorney - Water
1/2/2025 7:28:14 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Darren Horstmeier on behalf of Schriever AFB
1/2/2025 7:28:12 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Rob MacDonald on behalf of Pikes Peak Area Council of Governments
1/2/2025 7:28:10 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
1/2/2025 7:28:08 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Chris Smith on behalf of Ellicott SD 22
1/2/2025 7:28:06 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Peggy Current on behalf of Ellicott Metro
1/2/2025 7:28:04 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michael Henley on behalf of Ellicott Fire Protection District
1/2/2025 7:28:02 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Norma Houghton on behalf of Ellicott Fire Protection District
1/2/2025 7:28:00 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
1/2/2025 7:27:58 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
1/2/2025 7:27:56 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
1/2/2025 7:27:54 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
1/2/2025 7:27:52 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of Pikes Peak Regional Building Department
1/2/2025 7:27:50 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
1/2/2025 7:27:48 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
1/2/2025 7:27:46 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Travis Sauder on behalf of Colorado Parks and Wildlife
1/2/2025 7:27:45 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
1/2/2025 7:27:43 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Karen Voltura on behalf of Colorado Parks and Wildlife
1/2/2025 7:27:41 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
1/2/2025 7:27:39 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey
1/2/2025 7:27:37 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
1/2/2025 7:27:35 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
1/2/2025 7:27:33 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
1/2/2025 7:27:31 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
1/2/2025 7:27:29 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
1/2/2025 7:27:27 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of Colorado Department of Public Health and Environment
1/2/2025 7:27:25 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Brendan Cicione on behalf of Colorado Department of Public Health and Environment
1/2/2025 7:27:23 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of Parks Advisory Board
1/2/2025 7:27:21 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
1/2/2025 7:27:19 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn Reese on behalf of EPC Stormwater Review
1/2/2025 7:27:18 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christina Prete on behalf of EPC Stormwater Review
1/2/2025 7:27:16 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Jeff Kramer on behalf of EPC Sheriff's Department
1/2/2025 7:27:14 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
1/2/2025 7:27:12 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Andrew Prehm on behalf of EPC Sheriff's Department
1/2/2025 7:27:10 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of EPC Public Works, County Engineer
1/2/2025 7:27:08 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of EPC Public Works, County Engineer
1/2/2025 7:27:06 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by on behalf of EPC Parks Department
1/2/2025 7:27:04 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mike McCarthy on behalf of EPC Health Department
1/2/2025 7:27:02 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Catherine McGarvy on behalf of EPC Health Department
1/2/2025 7:27:00 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by HEAEH LandUse on behalf of EPC Health Department
1/2/2025 7:26:58 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services
1/2/2025 7:26:56 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Lori Seago on behalf of County Attorney - Water
1/2/2025 7:26:54 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Erika Keech on behalf of County Attorney - Water
1/2/2025 7:26:52 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by April Willie on behalf of County Attorney - Water
1/2/2025 7:26:50 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Lori Seago on behalf of County Attorney - Development Review
1/2/2025 7:26:48 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Erika Keech on behalf of County Attorney - Development Review
1/2/2025 7:26:46 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by April Willie on behalf of County Attorney - Development Review
1/2/2025 7:26:43 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager
1/2/2025 7:26:41 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
1/2/2025 7:26:39 AM Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division
1/1/2025 11:39:35 AM Fees paid: 1/1/2025 (Receipt: 1010005)
12/31/2024 2:32:35 PM Payment Request sent: 12/31/2024
12/31/2024 2:32:35 PM File # Assigned: SKP242
12/31/2024 2:32:22 PM Submission Triaged
12/31/2024 2:04:37 PM Submission received from Applicant
12/20/2024 9:23:38 AM Submission request sent to Applicant
12/17/2024 12:22:02 PM Submission request sent to Applicant
10/24/2024 9:17:07 AM Submission request sent to Applicant
3/6/2024 5:28:30 PM Submission request sent to Applicant
2/29/2024 3:33:20 PM Project Manager Assigned: Ryan Howser
2/29/2024 3:33:20 PM EA Assigned: EA2425
2/29/2024 3:33:20 PM Project Created