| 10/24/2025 2:09:51 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 10/10/2025 8:06:26 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 10/10/2025 8:06:25 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 10/10/2025 8:05:48 AM | Submission Triaged | 
                
                    | 10/9/2025 3:58:40 PM | Submission received from Applicant | 
                
                    | 9/18/2025 3:49:07 PM | Submission request sent to Applicant | 
                
                    | 8/12/2025 11:47:22 AM | Fees paid: 8/12/2025 (Receipt: 1010909) | 
                
                    | 8/12/2025 9:21:34 AM | Payment Request sent: 8/12/2025 | 
                
                    | 6/13/2025 2:32:56 PM | Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office | 
                
                    | 6/13/2025 2:27:01 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 6/13/2025 2:27:00 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 6/13/2025 2:26:59 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 6/6/2025 9:13:08 AM | Fees paid: 6/6/2025 (Receipt: 1010635) | 
                
                    | 6/5/2025 4:16:05 PM | Payment Request sent: 6/5/2025 | 
                
                    | 5/16/2025 1:40:39 PM | Submission request sent to Applicant | 
                
                    | 5/16/2025 12:19:47 PM | Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/16/2025 12:00:03 PM | Request for Review Comments returned by Schriever AFB | 
                
                    | 5/16/2025 9:27:25 AM | Submission request sent to Applicant | 
                
                    | 5/14/2025 3:16:57 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 5/14/2025 3:00:16 PM | Request for Review Comments email resent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 5/14/2025 2:24:03 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 5/12/2025 1:34:53 PM | Request for Review Comments returned by Colorado Springs Planning & Community Development | 
                
                    | 5/9/2025 3:03:28 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 5/7/2025 1:26:02 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development | 
                
                    | 5/7/2025 1:26:01 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Drew Fox on behalf of Colorado Springs Planning & Community Development | 
                
                    | 5/7/2025 10:04:24 AM | Request for Review Comments returned by EPC Environmental Services | 
                
                    | 4/30/2025 2:20:32 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 4/30/2025 2:20:31 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 4/30/2025 2:20:30 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 4/30/2025 2:20:29 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services | 
                
                    | 4/30/2025 2:20:27 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 4/30/2025 2:20:26 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 4/30/2025 2:20:25 PM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 4/30/2025 2:18:52 PM | Submission Triaged | 
                
                    | 4/27/2025 9:13:10 PM | Submission received from Applicant | 
                
                    | 4/25/2025 12:19:08 PM | Submission request sent to Applicant | 
                
                    | 4/25/2025 12:18:53 PM | Submission Triaged | 
                
                    | 4/24/2025 2:22:30 PM | Submission received from Applicant | 
                
                    | 4/14/2025 3:27:59 PM | Request for Review Comments returned by Colorado Division of Water Resources | 
                
                    | 4/8/2025 4:56:23 PM | Submission request sent to Applicant | 
                
                    | 4/8/2025 4:54:53 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 4/8/2025 4:08:25 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 4/8/2025 6:05:23 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 4/2/2025 12:44:27 PM | Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office | 
                
                    | 3/24/2025 2:45:21 PM | Request for Review Comments returned by EPC Parks Department | 
                
                    | 3/19/2025 12:22:45 PM | Request for Review Comments returned by EPC Environmental Services | 
                
                    | 3/19/2025 9:51:27 AM | Request for Review Comments returned by 911 Authority - El Paso/Teller County | 
                
                    | 3/18/2025 9:03:00 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Darren Horstmeier on behalf of Schriever AFB | 
                
                    | 3/18/2025 9:02:59 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michael Henley on behalf of Ellicott Fire Protection District | 
                
                    | 3/18/2025 9:02:58 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Norma Houghton on behalf of Ellicott Fire Protection District | 
                
                    | 3/18/2025 9:02:57 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County | 
                
                    | 3/18/2025 9:02:56 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County | 
                
                    | 3/18/2025 9:02:54 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources | 
                
                    | 3/18/2025 9:02:53 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources | 
                
                    | 3/18/2025 9:02:51 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 3/18/2025 9:02:50 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 3/18/2025 9:02:49 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 3/18/2025 9:02:48 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 3/18/2025 9:02:47 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 3/18/2025 9:02:46 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 3/18/2025 9:02:45 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of EPC Parks Department | 
                
                    | 3/18/2025 9:02:44 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services | 
                
                    | 3/18/2025 9:02:42 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 3/18/2025 9:02:40 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 3/18/2025 9:02:39 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 3/18/2025 9:00:25 AM | Submission Triaged | 
                
                    | 3/16/2025 5:07:38 PM | Submission received from Applicant | 
                
                    | 2/12/2025 4:10:25 PM | Request for Review Comments returned by Parks Advisory Board | 
                
                    | 2/10/2025 1:54:48 PM | Fees paid: 2/10/2025 (Receipt: 1010149) | 
                
                    | 2/10/2025 1:48:59 PM | Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.) | 
                
                    | 2/7/2025 12:10:45 PM | Request for Review Comments returned by Ellicott Fire Protection District | 
                
                    | 2/5/2025 4:09:39 PM | Payment Request sent: 2/5/2025 | 
                
                    | 2/5/2025 4:01:18 PM | Request for Review Comments returned by PCD Administrative Notice | 
                
                    | 2/3/2025 2:52:36 PM | Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office | 
                
                    | 1/31/2025 3:11:27 PM | Request for Review Comments sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of PCD Administrative Notice | 
                
                    | 1/31/2025 7:38:32 AM | Submission request sent to Applicant | 
                
                    | 1/30/2025 10:35:19 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 1/30/2025 4:56:11 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 1/30/2025 4:04:38 PM | Request for Review Comments returned by Schriever AFB | 
                
                    | 1/30/2025 3:30:51 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 1/26/2025 5:19:20 PM | Request for Review Comments returned by Colorado Parks and Wildlife | 
                
                    | 1/24/2025 11:12:15 AM | Request for Review Comments returned by EPC Parks Department | 
                
                    | 1/24/2025 9:35:04 AM | Request for Review Comments returned by Colorado Division of Water Resources | 
                
                    | 1/22/2025 11:46:45 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.) | 
                
                    | 1/22/2025 11:46:44 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.) | 
                
                    | 1/22/2025 10:51:02 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 1/22/2025 9:13:00 AM | Request for Review Comments returned by Colorado Geological Survey | 
                
                    | 1/19/2025 5:19:52 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 1/15/2025 11:51:43 AM | Request for Review Comments returned by County Attorney - Development Review | 
                
                    | 1/9/2025 1:20:07 PM | Request for Review Comments returned by 911 Authority - El Paso/Teller County | 
                
                    | 1/9/2025 10:16:35 AM | Request for Review Comments returned by EPC Environmental Services | 
                
                    | 1/6/2025 9:26:45 AM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 1/2/2025 2:01:00 PM | Request for Review Comments returned by County Attorney - Water | 
                
                    | 1/2/2025 7:28:14 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Darren Horstmeier on behalf of Schriever AFB | 
                
                    | 1/2/2025 7:28:12 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Rob MacDonald on behalf of Pikes Peak Area Council of Governments | 
                
                    | 1/2/2025 7:28:10 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 1/2/2025 7:28:08 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Chris Smith on behalf of Ellicott SD 22 | 
                
                    | 1/2/2025 7:28:06 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Peggy Current on behalf of Ellicott Metro | 
                
                    | 1/2/2025 7:28:04 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michael Henley on behalf of Ellicott Fire Protection District | 
                
                    | 1/2/2025 7:28:02 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Norma Houghton on behalf of Ellicott Fire Protection District | 
                
                    | 1/2/2025 7:28:00 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila | 
                
                    | 1/2/2025 7:27:58 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila | 
                
                    | 1/2/2025 7:27:56 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila | 
                
                    | 1/2/2025 7:27:54 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD | 
                
                    | 1/2/2025 7:27:52 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 1/2/2025 7:27:50 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County | 
                
                    | 1/2/2025 7:27:48 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County | 
                
                    | 1/2/2025 7:27:46 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Travis Sauder on behalf of Colorado Parks and Wildlife | 
                
                    | 1/2/2025 7:27:45 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife | 
                
                    | 1/2/2025 7:27:43 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Karen Voltura on behalf of Colorado Parks and Wildlife | 
                
                    | 1/2/2025 7:27:41 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife | 
                
                    | 1/2/2025 7:27:39 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey | 
                
                    | 1/2/2025 7:27:37 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources | 
                
                    | 1/2/2025 7:27:35 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources | 
                
                    | 1/2/2025 7:27:33 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 1/2/2025 7:27:31 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 1/2/2025 7:27:29 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 1/2/2025 7:27:27 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of Colorado Department of Public Health and Environment | 
                
                    | 1/2/2025 7:27:25 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Brendan Cicione on behalf of Colorado Department of Public Health and Environment | 
                
                    | 1/2/2025 7:27:23 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of Parks Advisory Board | 
                
                    | 1/2/2025 7:27:21 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 1/2/2025 7:27:19 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 1/2/2025 7:27:18 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 1/2/2025 7:27:16 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Jeff Kramer on behalf of EPC Sheriff's Department | 
                
                    | 1/2/2025 7:27:14 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Christopher Gonzalez on behalf of EPC Sheriff's Department | 
                
                    | 1/2/2025 7:27:12 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Andrew Prehm on behalf of EPC Sheriff's Department | 
                
                    | 1/2/2025 7:27:10 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 1/2/2025 7:27:08 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 1/2/2025 7:27:06 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by  on behalf of EPC Parks Department | 
                
                    | 1/2/2025 7:27:04 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Mike McCarthy on behalf of EPC Health Department | 
                
                    | 1/2/2025 7:27:02 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 1/2/2025 7:27:00 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by HEAEH LandUse on behalf of EPC Health Department | 
                
                    | 1/2/2025 7:26:58 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Kathy Andrew on behalf of EPC Environmental Services | 
                
                    | 1/2/2025 7:26:56 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Lori Seago on behalf of County Attorney - Water | 
                
                    | 1/2/2025 7:26:54 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Erika Keech on behalf of County Attorney - Water | 
                
                    | 1/2/2025 7:26:52 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by April Willie on behalf of County Attorney - Water | 
                
                    | 1/2/2025 7:26:50 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Lori Seago on behalf of County Attorney - Development Review | 
                
                    | 1/2/2025 7:26:48 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Erika Keech on behalf of County Attorney - Development Review | 
                
                    | 1/2/2025 7:26:46 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by April Willie on behalf of County Attorney - Development Review | 
                
                    | 1/2/2025 7:26:43 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 1/2/2025 7:26:41 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 1/2/2025 7:26:39 AM | Request for Review Comments email sent for Project Flying Horse East Phase 1 Sketch Plan for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 1/1/2025 11:39:35 AM | Fees paid: 1/1/2025 (Receipt: 1010005) | 
                
                    | 12/31/2024 2:32:35 PM | Payment Request sent: 12/31/2024 | 
                
                    | 12/31/2024 2:32:35 PM | File # Assigned: SKP242 | 
                
                    | 12/31/2024 2:32:22 PM | Submission Triaged | 
                
                    | 12/31/2024 2:04:37 PM | Submission received from Applicant | 
                
                    | 12/20/2024 9:23:38 AM | Submission request sent to Applicant | 
                
                    | 12/17/2024 12:22:02 PM | Submission request sent to Applicant | 
                
                    | 10/24/2024 9:17:07 AM | Submission request sent to Applicant | 
                
                    | 3/6/2024 5:28:30 PM | Submission request sent to Applicant | 
                
                    | 2/29/2024 3:33:20 PM | Project Manager Assigned: Ryan Howser | 
                
                    | 2/29/2024 3:33:20 PM | EA Assigned: EA2425 | 
                
                    | 2/29/2024 3:33:20 PM | Project Created |