Project Details

Search


File Number
CDR2323
Project Name
Peterson / HWY 24 Roundabout Project
Description
Construction Drawing Review for City-initiated roadway improvement project to install a roundabout at the intersection of Peterson Road and HWY 24.
Applicant
Basis Partners
Chris Jennings ( chris.jennings@basisp.com )
(719) 733-3519
Chris Jennings ( chris.jennings@basisp.com )
(719) 733-3519
File Prefix
CDR - Construction Drawing Review
Year
2023
Project Manager
Ryan Howser
Status
Closed
Created
12/26/2023 1:06:14 PM

View: Review Comments



Review Documents (2)

Link Document Date
View Construction Drawings (Plans/Profiles) 12/29/2023 1:19:10 PM
View Preliminary Drainage Report 12/29/2023 9:54:54 AM



Events (56)

Date Comment
1/21/2025 2:35:49 PM Project Closed
1/21/2025 2:35:49 PM Project Approved: 1/21/2025
2/7/2024 1:41:29 PM Request for Review Comments returned by Cimarron Hills Fire
1/25/2024 4:08:54 PM Request for Review Comments returned by EPC Parks Department
1/18/2024 4:50:55 PM Submission request sent to Applicant
1/18/2024 4:40:58 PM Request for Review Comments returned by EPC Stormwater Review
1/18/2024 9:22:04 AM Request for Review Comments returned by PCD Engineering Division
1/18/2024 8:52:12 AM Request for Review Comments returned by PCD Project Manager
1/18/2024 8:14:48 AM Request for Review Comments returned by Colorado Springs Public Works
1/12/2024 3:52:15 PM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/9/2024 12:35:31 PM Request for Review Comments returned by Colorado Springs Planning & Community Development
1/4/2024 7:32:12 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Tim Thomas on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:10 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Paul Clifton on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:08 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:06 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Gary Rust on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:04 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Caelen Went on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:02 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/4/2024 7:32:00 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
1/4/2024 7:31:58 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Rae Carlson on behalf of Colorado Springs Public Works
1/4/2024 7:31:56 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Patrick Morris on behalf of Colorado Springs Public Works
1/4/2024 7:31:54 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by LaShunda Simpson on behalf of Colorado Springs Public Works
1/4/2024 7:31:53 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Jonathan Scherer on behalf of Colorado Springs Public Works
1/4/2024 7:31:50 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Joel Metzker on behalf of Colorado Springs Public Works
1/4/2024 7:31:48 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Joel Dagnillo on behalf of Colorado Springs Public Works
1/4/2024 7:31:46 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Jeff Bailey on behalf of Colorado Springs Public Works
1/4/2024 7:31:44 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Erin Powers on behalf of Colorado Springs Public Works
1/4/2024 7:31:42 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by General Email on behalf of Colorado Springs Public Works
1/4/2024 7:31:39 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Dana Davison on behalf of Colorado Springs Public Works
1/4/2024 7:31:36 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Brian Shevock on behalf of Colorado Springs Public Works
1/4/2024 7:31:32 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
1/4/2024 7:31:29 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Stefan Manning on behalf of Colorado Springs Fire Department
1/4/2024 7:31:27 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Steve Smith on behalf of Colorado Springs Fire Department
1/4/2024 7:31:25 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Tom Joyce on behalf of Cimarron Hills Fire
1/4/2024 7:31:23 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by John McLeod on behalf of Cimarron Hills Fire
1/4/2024 7:31:21 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
1/4/2024 7:31:19 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
1/4/2024 7:31:17 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
1/4/2024 7:31:15 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
1/4/2024 7:31:13 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
1/4/2024 7:31:11 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Mikayla Hartford on behalf of EPC Stormwater Review
1/4/2024 7:31:09 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Glenn Reese on behalf of EPC Stormwater Review
1/4/2024 7:31:07 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Christina Prete on behalf of EPC Stormwater Review
1/4/2024 7:31:05 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by on behalf of EPC Public Works, County Engineer
1/4/2024 7:31:03 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by on behalf of EPC Public Works, County Engineer
1/4/2024 7:31:01 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by on behalf of EPC Parks Department
1/4/2024 7:30:56 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Gilbert LaForce on behalf of PCD Engineering Division
1/4/2024 7:30:54 AM Request for Review Comments email sent for Project Peterson / HWY 24 Roundabout Project for review by Engineering Manager on behalf of PCD Engineering Division
1/3/2024 2:12:42 PM Fees waived: 1/3/2024 by Justin Kilgore (justinkilgore@elpasoco.com)
12/29/2023 1:21:36 PM Payment Request sent: 12/29/2023
12/29/2023 1:21:35 PM File # Assigned: CDR2323
12/29/2023 1:21:30 PM Submission Triaged
12/29/2023 1:19:40 PM Submission received from Applicant
12/29/2023 1:02:25 PM Submission request sent to Applicant
12/26/2023 1:07:23 PM Submission request sent to Applicant
12/26/2023 1:06:17 PM Project Manager Assigned: Ryan Howser
12/26/2023 1:06:17 PM Project Created