3/15/2024 9:54:55 AM
|
Project Closed
|
3/15/2024 9:54:55 AM
|
Project Approved: 3/15/2024
|
2/21/2024 11:38:29 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/21/2024 11:31:39 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/13/2024 2:38:51 PM
|
Submission Triaged
|
2/13/2024 2:36:35 PM
|
Submission received from Applicant
|
2/7/2024 10:09:40 AM
|
Submission request sent to Applicant
|
2/7/2024 10:08:51 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/6/2024 3:41:35 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/25/2024 2:29:45 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-145(AR) - Plat for review by on behalf of Pikes Peak Regional Building Department
|
1/24/2024 11:50:19 AM
|
Fees paid: 1/24/2024 (Receipt: 1008730)
|
1/24/2024 8:30:59 AM
|
Payment Request sent: 1/24/2024
|
1/24/2024 8:30:59 AM
|
File # Assigned: SF243
|
1/24/2024 8:30:47 AM
|
Submission Triaged
|
1/23/2024 4:52:24 PM
|
Submission received from Applicant
|
11/14/2023 11:51:10 AM
|
Submission request sent to Applicant
|
11/14/2023 11:42:32 AM
|
Project Manager Assigned: Ashlyn Mathy
|
11/14/2023 11:42:32 AM
|
Project Created
|