6/27/2025 2:56:19 PM
|
Project Closed
|
6/27/2025 2:56:19 PM
|
Project Approved: 6/27/2025
|
6/27/2025 2:56:07 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
5/28/2025 9:13:50 AM
|
Fees paid: 5/28/2025 (Receipt: 1010575)
|
5/23/2025 11:29:47 AM
|
Payment Request sent: 5/23/2025
|
4/22/2025 11:57:06 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
4/22/2025 10:26:51 AM
|
Request for Review Comments returned by County Attorney - Water
|
4/17/2025 1:30:37 PM
|
Request for Review Comments returned by EPC Environmental Services
|
4/17/2025 11:59:51 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
4/17/2025 11:59:50 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
4/17/2025 11:59:49 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
4/17/2025 11:59:48 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
|
4/17/2025 11:59:47 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
4/17/2025 11:14:46 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Stefan Manning on behalf of Colorado Springs Fire Department
|
4/17/2025 11:14:45 AM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Steve Smith on behalf of Colorado Springs Fire Department
|
4/7/2025 3:08:43 PM
|
Request for Review Comments sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by April Willie on behalf of County Attorney - Water
|
4/7/2025 1:54:18 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/2/2025 2:42:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/31/2025 3:15:29 PM
|
Request for Review Comments returned by County Attorney - Water
|
3/19/2025 2:58:31 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
3/19/2025 2:58:29 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/19/2025 2:58:28 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
|
3/19/2025 2:58:27 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
|
3/19/2025 2:58:26 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by April Willie on behalf of County Attorney - Water
|
3/19/2025 2:58:24 PM
|
Request for Review Comments email sent for Project Rising Moon Filing 1 & 2 Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
3/19/2025 2:57:28 PM
|
Submission Triaged
|
3/18/2025 12:46:26 PM
|
Submission received from Applicant
|
3/11/2025 3:02:57 PM
|
Submission request sent to Applicant
|
3/11/2025 2:38:53 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
2/27/2025 9:07:35 AM
|
Request for Review Comments returned by PCD Engineering Division
|
2/20/2025 3:47:11 PM
|
Request for Review Comments sent for Project Habitat for Humanity Prelim Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
2/20/2025 11:00:58 AM
|
Request for Review Comments returned by County Attorney - Water
|
2/13/2025 10:15:55 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Lori Seago on behalf of County Attorney - Water
|
2/13/2025 10:15:54 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Erika Keech on behalf of County Attorney - Water
|
2/13/2025 10:15:53 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by April Willie on behalf of County Attorney - Water
|
2/13/2025 10:15:52 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/13/2025 10:15:51 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
2/13/2025 9:36:23 AM
|
Submission Triaged
|
2/13/2025 8:00:08 AM
|
Submission received from Applicant
|
2/4/2025 3:03:04 PM
|
Submission request sent to Applicant
|
2/4/2025 3:02:31 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/31/2025 2:01:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/28/2025 2:33:27 PM
|
Request for Review Comments returned by County Attorney - Water
|
1/21/2025 12:47:06 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Lori Seago on behalf of County Attorney - Water
|
1/21/2025 12:47:06 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Erika Keech on behalf of County Attorney - Water
|
1/21/2025 12:47:05 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by April Willie on behalf of County Attorney - Water
|
1/21/2025 12:47:02 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
1/21/2025 12:47:00 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/21/2025 12:46:59 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
1/21/2025 12:42:12 PM
|
Submission Triaged
|
1/18/2025 1:57:32 PM
|
Submission received from Applicant
|
12/3/2024 10:56:58 AM
|
Project Manager Assigned: Kylie Bagley
|
11/21/2024 4:22:19 PM
|
Submission request sent to Applicant
|
11/21/2024 3:30:26 PM
|
Submission request sent to Applicant
|
10/9/2024 1:28:08 PM
|
Submission request sent to Applicant
|
10/9/2024 1:23:45 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/9/2024 1:13:44 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
10/9/2024 1:13:40 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Kari Parsons on behalf of PCD Project Manager
|
10/8/2024 5:13:38 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/8/2024 4:08:58 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/8/2024 4:06:03 PM
|
Request for Review Comments email resent for Project Habitat for Humanity Prelim Plan for review by Kari Parsons on behalf of PCD Project Manager
|
10/8/2024 3:48:36 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/7/2024 3:11:11 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/4/2024 2:00:22 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/4/2024 8:26:36 AM
|
Request for Review Comments returned by County Attorney - Water
|
9/30/2024 2:37:17 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/26/2024 3:17:04 PM
|
Request for Review Comments returned by EPC Parks Department
|
9/25/2024 4:17:07 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/25/2024 4:17:05 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/25/2024 4:17:04 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/25/2024 4:17:02 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Cindy Moore on behalf of Colorado Centre Metro(includes Cuchares Ranch sub.)
|
9/25/2024 4:17:00 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Al Testa on behalf of Colorado Centre Metro(includes Cuchares Ranch sub.)
|
9/25/2024 4:16:58 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by on behalf of Pikes Peak Regional Building Department
|
9/25/2024 4:16:56 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
9/25/2024 4:16:54 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
9/25/2024 4:16:52 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
9/25/2024 4:16:50 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by on behalf of EPC Parks Department
|
9/25/2024 4:16:48 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Lori Seago on behalf of County Attorney - Water
|
9/25/2024 4:16:46 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Erika Keech on behalf of County Attorney - Water
|
9/25/2024 4:16:44 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by April Willie on behalf of County Attorney - Water
|
9/25/2024 4:16:40 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Kari Parsons on behalf of PCD Project Manager
|
9/25/2024 4:16:38 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/25/2024 4:16:36 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
9/25/2024 4:08:46 PM
|
Submission Triaged
|
9/25/2024 2:49:19 PM
|
Submission received from Applicant
|
8/14/2024 2:10:51 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
7/29/2024 1:32:54 PM
|
Request for Review Comments returned by County Attorney - Water
|
7/28/2024 6:41:56 PM
|
Request for Review Comments returned by EPC Health Department
|
7/24/2024 10:28:36 AM
|
Submission request sent to Applicant
|
7/24/2024 10:21:21 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/18/2024 3:35:21 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
7/18/2024 3:35:19 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
7/18/2024 3:35:17 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Lori Seago on behalf of County Attorney - Water
|
7/18/2024 3:35:16 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by Erika Keech on behalf of County Attorney - Water
|
7/18/2024 3:35:14 PM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plan for review by April Willie on behalf of County Attorney - Water
|
7/18/2024 1:22:44 PM
|
Submission request canceled
|
7/18/2024 1:22:13 PM
|
Request for Review Comments email resent for Project Habitat for Humanity Prelim Plan for review by Kari Parsons on behalf of PCD Project Manager
|
7/15/2024 11:59:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/15/2024 11:54:14 AM
|
Request for Review Comments email resent for Project Habitat for Humanity Prelim Plat for review by Kari Parsons on behalf of PCD Project Manager
|
7/10/2024 3:08:23 PM
|
Submission request sent to Applicant
|
7/10/2024 12:20:38 PM
|
Submission request sent to Applicant
|
7/9/2024 5:09:36 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/9/2024 2:55:55 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
7/9/2024 11:00:46 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/8/2024 1:41:41 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/8/2024 11:16:36 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/8/2024 9:08:17 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
7/2/2024 3:18:27 PM
|
Request for Review Comments returned by Widefield SD 3
|
7/2/2024 3:04:11 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/28/2024 2:54:02 PM
|
Request for Review Comments sent for Project Habitat for Humanity Prelim Plat for review by on behalf of PCD Administrative Notice
|
6/27/2024 2:12:15 PM
|
Request for Review Comments returned by EPC Parks Department
|
6/26/2024 10:11:16 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/24/2024 12:52:39 PM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
6/21/2024 2:14:54 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/18/2024 11:12:54 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Dave Gish on behalf of Widefield SD 3
|
6/18/2024 11:12:52 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
6/18/2024 11:12:50 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/18/2024 11:12:48 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
6/18/2024 11:12:46 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Katie Miller on behalf of El Paso County Conservation Dist
|
6/18/2024 11:12:44 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
6/18/2024 11:12:42 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/18/2024 11:12:40 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/18/2024 11:12:38 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
6/18/2024 11:12:36 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Cindy Moore on behalf of Colorado Centre Metro(includes Cuchares Ranch sub.)
|
6/18/2024 11:12:34 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Al Testa on behalf of Colorado Centre Metro(includes Cuchares Ranch sub.)
|
6/18/2024 11:12:32 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by on behalf of Pikes Peak Regional Building Department
|
6/18/2024 11:12:30 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
6/18/2024 11:12:28 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
6/18/2024 11:12:26 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
6/18/2024 11:12:24 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Glenn Reese on behalf of EPC Stormwater Review
|
6/18/2024 11:12:22 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Christina Prete on behalf of EPC Stormwater Review
|
6/18/2024 11:12:20 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
6/18/2024 11:12:18 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
6/18/2024 11:12:16 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
6/18/2024 11:12:14 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by on behalf of EPC Parks Department
|
6/18/2024 11:12:12 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Mike McCarthy on behalf of EPC Health Department
|
6/18/2024 11:12:10 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Catherine McGarvy on behalf of EPC Health Department
|
6/18/2024 11:12:08 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by HEAEH LandUse on behalf of EPC Health Department
|
6/18/2024 11:12:04 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Kari Parsons on behalf of PCD Project Manager
|
6/18/2024 11:12:02 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/18/2024 11:12:00 AM
|
Request for Review Comments email sent for Project Habitat for Humanity Prelim Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
6/17/2024 2:45:56 PM
|
Project Manager Assigned: Scott Weeks
|
6/17/2024 2:07:43 PM
|
Fees paid: 6/17/2024 (Receipt: 1009249)
|
6/10/2024 5:02:07 PM
|
Payment Request sent: 6/10/2024
|
6/10/2024 5:02:07 PM
|
File # Assigned: SP243
|
6/10/2024 5:01:55 PM
|
Submission Triaged
|
6/10/2024 2:46:04 PM
|
Submission received from Applicant
|
8/25/2023 8:03:44 AM
|
Submission request sent to Applicant
|
8/23/2023 9:03:15 AM
|
Project Manager Assigned: Kylie Bagley
|
8/23/2023 9:03:15 AM
|
EA Assigned: EA2380
|
8/23/2023 9:03:15 AM
|
Project Created
|