9/16/2025 8:57:45 AM
|
Request for Review Comments returned by EPC Parks Department
|
9/15/2025 5:41:34 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49
|
9/15/2025 5:41:33 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
|
9/15/2025 5:41:32 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
9/15/2025 5:41:31 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:30 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:29 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Katie Miller on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:28 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Erica Carter on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:27 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:26 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:25 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:24 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Billy Richard on behalf of El Paso County Conservation Dist
|
9/15/2025 5:41:23 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/15/2025 5:41:22 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/15/2025 5:41:20 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
|
9/15/2025 5:41:19 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/15/2025 5:41:18 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
9/15/2025 5:41:17 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
9/15/2025 5:41:16 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
9/15/2025 5:41:15 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
9/15/2025 5:41:14 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by on behalf of EPC Parks Department
|
9/15/2025 5:41:13 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
|
9/15/2025 5:41:12 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
9/15/2025 5:41:11 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
|
9/15/2025 5:41:10 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/15/2025 5:41:08 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
9/15/2025 5:41:07 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/15/2025 5:41:06 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
9/15/2025 5:41:05 PM
|
Request for Review Comments email sent for Project Utah-Nevada Lane Site Development Plan for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
|
9/15/2025 12:59:36 PM
|
Project Manager Assigned: Lacey Dean
|
9/15/2025 12:01:53 PM
|
Fees paid: 9/15/2025 (Receipt: 1011048)
|
9/15/2025 7:40:17 AM
|
Payment Request sent: 9/15/2025
|
9/15/2025 7:39:47 AM
|
File # Assigned: PPR2526
|
9/15/2025 7:37:16 AM
|
Submission Triaged
|
9/11/2025 2:07:50 PM
|
Submission received from Applicant
|
7/14/2025 1:18:22 PM
|
Submission request sent to Applicant
|
5/8/2025 1:34:42 PM
|
Submission request sent to Applicant
|
5/1/2025 2:49:11 PM
|
Submission request sent to Applicant
|
5/1/2025 2:49:02 PM
|
Project reopened for Review Comments
|
7/28/2024 12:00:00 AM
|
Project Closed
|
7/28/2024 12:00:00 AM
|
Project Expired one year after 07/28/2023 Submission Request 07/28/2024
|
7/28/2023 2:52:13 PM
|
Submission request sent to Applicant
|
5/4/2023 11:15:33 AM
|
Submission request sent to Applicant
|
5/4/2023 10:23:29 AM
|
Project Manager Assigned: Kylie Bagley
|
5/4/2023 10:23:29 AM
|
EA Assigned: EA2333
|
5/4/2023 10:23:29 AM
|
Project Created
|