5/20/2024 1:07:35 PM
|
Project Closed
|
5/20/2024 1:07:35 PM
|
Project Approved: 5/20/2024
|
5/17/2024 10:32:13 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/17/2024 10:32:11 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
5/17/2024 10:31:27 AM
|
Submission Triaged
|
5/16/2024 6:04:40 PM
|
Submission received from Applicant
|
5/14/2024 9:10:36 AM
|
Submission request sent to Applicant
|
5/6/2024 10:24:16 AM
|
Submission request sent to Applicant
|
5/2/2024 7:09:09 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/24/2024 2:14:21 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/24/2024 2:14:19 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
4/24/2024 2:13:17 PM
|
Submission Triaged
|
4/19/2024 12:13:16 PM
|
Submission received from Applicant
|
4/1/2024 11:22:35 AM
|
Submission request sent to Applicant
|
3/25/2024 8:07:28 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
3/20/2024 12:20:55 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/20/2024 11:50:26 AM
|
Request for Review Comments email resent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
3/19/2024 8:46:41 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/11/2024 1:29:40 PM
|
Request for Review Comments sent for Project CDR HWY.105/JCP for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
3/8/2024 9:10:18 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/8/2024 9:10:15 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
3/8/2024 9:09:11 AM
|
Submission Triaged
|
3/4/2024 8:58:03 AM
|
Submission received from Applicant
|
2/13/2024 10:41:38 AM
|
Submission request sent to Applicant
|
2/13/2024 9:10:16 AM
|
Request for Review Comments returned by PCD Engineering Division
|
1/26/2024 3:25:34 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/26/2024 3:25:33 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
1/26/2024 3:24:29 PM
|
Submission Triaged
|
1/25/2024 4:31:51 PM
|
Submission received from Applicant
|
1/25/2024 3:51:46 PM
|
Submission request sent to Applicant
|
12/12/2023 3:49:44 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
12/7/2023 9:10:18 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
11/15/2023 12:31:14 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
11/15/2023 10:41:00 AM
|
Submission request sent to Applicant
|
11/15/2023 10:22:07 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/15/2023 9:30:02 AM
|
Request for Review Comments email resent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
11/15/2023 9:27:40 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/14/2023 3:57:21 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/14/2023 1:25:10 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/13/2023 11:03:04 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/7/2023 9:08:30 AM
|
Project Manager Assigned: Kylie Bagley
|
11/7/2023 8:48:29 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
11/7/2023 8:48:27 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Jessie Shaffer on behalf of Woodmoor Water and Sanitation District
|
11/7/2023 8:48:25 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
11/7/2023 8:48:22 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Theresa Rust on behalf of Monument
|
11/7/2023 8:48:20 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Steve Sheffield on behalf of Monument
|
11/7/2023 8:48:18 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Shelia Booth on behalf of Monument
|
11/7/2023 8:48:16 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by on behalf of Monument
|
11/7/2023 8:48:14 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Luke Kerr on behalf of Monument
|
11/7/2023 8:48:12 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Jeffrey Liljegren on behalf of Monument
|
11/7/2023 8:48:10 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Vicki Wood on behalf of Lewis Palmer 38
|
11/7/2023 8:48:08 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Chris Coulter on behalf of Lewis Palmer 38
|
11/7/2023 8:48:06 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
11/7/2023 8:48:04 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
11/7/2023 8:48:02 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
11/7/2023 8:47:59 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/7/2023 8:47:57 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/7/2023 8:47:55 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
11/7/2023 8:47:53 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
11/7/2023 8:47:51 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
11/7/2023 8:47:49 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
11/7/2023 8:47:45 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
11/7/2023 8:47:40 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/7/2023 8:47:38 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/7/2023 8:47:36 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Christina Prete on behalf of EPC Stormwater Review
|
11/7/2023 8:47:34 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by on behalf of EPC Public Works, County Engineer
|
11/7/2023 8:47:32 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by on behalf of EPC Public Works, County Engineer
|
11/7/2023 8:47:30 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Lupe Packman on behalf of PCD Engineering Division
|
11/7/2023 8:47:28 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/7/2023 8:47:26 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/7/2023 8:47:24 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Edward Schoenheit on behalf of PCD Engineering Division
|
11/7/2023 8:47:22 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Engineering Manager on behalf of PCD Engineering Division
|
11/7/2023 8:47:20 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Charlene Durham on behalf of PCD Engineering Division
|
11/7/2023 8:47:18 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
11/7/2023 8:45:46 AM
|
Submission Triaged
|
11/6/2023 9:51:49 AM
|
Submission received from Applicant
|
8/28/2023 12:06:40 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
8/23/2023 12:33:56 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
8/22/2023 1:26:53 PM
|
Submission request sent to Applicant
|
8/22/2023 1:24:20 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/22/2023 1:07:22 PM
|
Request for Review Comments email resent for Project CDR HWY.105/JCP for review by Lekishia Bellamy on behalf of PCD Project Manager
|
8/22/2023 8:42:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/15/2023 8:17:12 AM
|
Request for Review Comments returned by PCD Engineering Division
|
8/14/2023 4:31:53 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/7/2023 8:32:14 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/24/2023 9:10:02 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
7/24/2023 9:10:00 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
7/24/2023 9:09:59 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Shelia Booth on behalf of Monument
|
7/24/2023 9:09:58 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Vicki Wood on behalf of Lewis Palmer 38
|
7/24/2023 9:09:57 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Supervisor Bob Swatek on behalf of Black Hills Energy-Aquila
|
7/24/2023 9:09:56 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/24/2023 9:09:55 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
7/24/2023 9:09:49 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Permits Program Manager Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
7/24/2023 9:09:48 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/24/2023 9:09:45 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by County Engineer on behalf of EPC Public Works, County Engineer
|
7/24/2023 9:09:44 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by County Engineer on behalf of EPC Public Works, County Engineer
|
7/24/2023 9:09:43 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Lekishia Bellamy on behalf of PCD Project Manager
|
7/24/2023 9:09:41 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/24/2023 7:25:38 AM
|
Submission Triaged
|
7/20/2023 5:01:49 PM
|
Submission received from Applicant
|
4/7/2023 12:39:05 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
4/6/2023 7:21:48 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/6/2023 7:19:55 AM
|
Request for Review Comments email resent for Project CDR HWY.105/JCP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/5/2023 3:01:05 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
4/5/2023 12:26:19 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/5/2023 12:25:44 PM
|
Submission request sent to Applicant
|
4/5/2023 11:36:09 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/3/2023 5:25:12 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/29/2023 2:30:20 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Lekishia Bellamy on behalf of PCD Project Manager
|
3/29/2023 2:30:17 PM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/29/2023 1:16:54 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/8/2023 11:15:25 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
3/8/2023 11:15:24 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
3/8/2023 11:15:22 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Shelia Booth on behalf of Monument
|
3/8/2023 11:15:21 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Vicki Wood on behalf of Lewis Palmer 38
|
3/8/2023 11:15:20 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Supervisor Bob Swatek on behalf of Black Hills Energy-Aquila
|
3/8/2023 11:15:19 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
3/8/2023 11:15:18 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
3/8/2023 11:15:16 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by CDOT Access Mgr Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
3/8/2023 11:15:10 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/8/2023 11:15:05 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by County Engineer on behalf of EPC Public Works, County Engineer
|
3/8/2023 11:15:04 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by County Engineer on behalf of EPC Public Works, County Engineer
|
3/8/2023 11:15:03 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Lekishia Bellamy on behalf of PCD Project Manager
|
3/8/2023 11:15:02 AM
|
Request for Review Comments email sent for Project CDR HWY.105/JCP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/3/2023 3:04:12 PM
|
Fees paid: 3/3/2023 (Receipt: 1007554)
|
2/27/2023 5:24:29 PM
|
Payment Request sent: 2/27/2023
|
2/27/2023 5:24:24 PM
|
File # Assigned: CDR237
|
2/27/2023 5:23:31 PM
|
Submission Triaged
|
2/27/2023 3:12:50 PM
|
Submission received from Applicant
|
2/23/2023 2:35:13 PM
|
Submission request sent to Applicant
|
2/23/2023 2:27:03 PM
|
Project Manager Assigned: Lekishia Bellamy
|
2/23/2023 2:27:03 PM
|
Project Created
|