4/17/2025 10:58:12 AM
|
Project Closed
|
4/17/2025 10:58:12 AM
|
Project Approved: 4/17/2025
|
2/21/2025 2:48:20 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/14/2025 2:11:08 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/13/2025 9:17:01 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/31/2025 11:10:22 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Lori Seago on behalf of County Attorney - Development Review
|
1/31/2025 11:10:21 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Erika Keech on behalf of County Attorney - Development Review
|
1/31/2025 11:10:20 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by April Willie on behalf of County Attorney - Development Review
|
1/31/2025 11:10:18 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/31/2025 11:10:17 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/31/2025 11:09:20 AM
|
Submission Triaged
|
1/31/2025 9:56:38 AM
|
Submission received from Applicant
|
1/15/2025 4:54:45 PM
|
Submission request sent to Applicant
|
1/15/2025 4:48:01 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/15/2025 4:03:46 PM
|
Request for Review Comments email resent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/15/2025 1:16:15 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/15/2025 11:48:34 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/15/2025 10:44:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/14/2025 2:57:37 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/2/2025 11:13:55 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Lori Seago on behalf of County Attorney - Development Review
|
1/2/2025 11:13:53 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Erika Keech on behalf of County Attorney - Development Review
|
1/2/2025 11:13:51 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by April Willie on behalf of County Attorney - Development Review
|
1/2/2025 11:13:12 AM
|
Submission Triaged
|
1/2/2025 10:19:15 AM
|
Submission received from Applicant
|
12/31/2024 12:31:36 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/31/2024 12:31:34 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/31/2024 12:31:32 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Christina Prete on behalf of EPC Stormwater Review
|
12/31/2024 12:31:29 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Justin Kilgore on behalf of PCD Project Manager
|
12/31/2024 12:31:26 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/31/2024 12:31:25 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
12/26/2024 9:32:09 AM
|
Submission request sent to Applicant
|
12/26/2024 9:31:29 AM
|
Submission request sent to Applicant
|
12/26/2024 9:31:14 AM
|
Submission Triaged
|
12/20/2024 5:22:52 PM
|
Submission received from Applicant
|
12/13/2024 11:19:41 AM
|
Submission request sent to Applicant
|
11/15/2024 7:26:27 AM
|
Submission request sent to Applicant
|
11/6/2024 10:30:34 AM
|
Submission request sent to Applicant
|
11/6/2024 10:30:00 AM
|
Submission request sent to Applicant
|
4/2/2024 4:16:37 PM
|
Fees paid: 4/2/2024 (Receipt: 1008954)
|
4/2/2024 7:33:08 AM
|
Submission request sent to Applicant
|
2/16/2024 9:17:04 AM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
2/12/2024 5:13:42 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/7/2024 3:17:19 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/31/2024 4:30:08 PM
|
Payment Request sent: 1/31/2024
|
1/31/2024 1:59:19 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Mark Stanwood on behalf of Ellicott Fire Protection District
|
1/31/2024 1:59:17 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Michael Henley on behalf of Ellicott Fire Protection District
|
1/31/2024 1:59:13 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/31/2024 1:59:11 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/31/2024 1:54:28 PM
|
Submission Triaged
|
1/30/2024 2:57:21 PM
|
Submission received from Applicant
|
1/24/2024 3:22:44 PM
|
Submission request sent to Applicant
|
1/23/2024 5:47:43 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/19/2024 1:27:45 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
1/19/2024 11:13:58 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/9/2024 7:44:07 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/9/2024 7:44:04 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/9/2024 7:42:38 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Mark Stanwood on behalf of Ellicott Fire Protection District
|
1/9/2024 7:42:35 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Michael Henley on behalf of Ellicott Fire Protection District
|
1/9/2024 7:42:30 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/9/2024 7:42:25 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/9/2024 7:40:46 AM
|
Submission Triaged
|
1/8/2024 8:21:14 AM
|
Submission received from Applicant
|
11/21/2023 9:49:41 AM
|
Request for Review Comments returned by County Attorney - Water
|
11/8/2023 12:02:24 PM
|
Submission request sent to Applicant
|
11/8/2023 12:00:08 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/8/2023 7:56:57 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/8/2023 7:34:48 AM
|
Request for Review Comments email resent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
11/7/2023 5:27:47 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/24/2023 12:48:31 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by April Willie on behalf of County Attorney - Water
|
10/24/2023 12:48:26 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Ryan Howser on behalf of PCD Project Manager
|
10/24/2023 12:48:18 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
10/24/2023 12:48:16 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
10/24/2023 12:47:20 PM
|
Submission Triaged
|
10/24/2023 11:57:49 AM
|
Submission received from Applicant
|
10/24/2023 11:19:03 AM
|
Submission request sent to Applicant
|
10/24/2023 11:18:14 AM
|
Submission Triaged
|
10/24/2023 10:28:20 AM
|
Submission received from Applicant
|
10/17/2023 3:43:57 PM
|
Request for Review Comments returned by County Attorney - Water
|
10/3/2023 8:00:40 AM
|
Submission request sent to Applicant
|
10/2/2023 5:14:34 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/2/2023 5:13:27 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/29/2023 2:54:11 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/20/2023 2:28:01 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
8/31/2023 4:05:25 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Permits Program Manager Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
8/31/2023 4:05:20 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/31/2023 4:05:17 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by April Willie on behalf of County Attorney - Water
|
8/31/2023 4:05:16 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Lori Seago on behalf of County Attorney - Development Review
|
8/31/2023 4:05:14 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Ryan Howser on behalf of PCD Project Manager
|
8/31/2023 4:05:10 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
8/31/2023 4:05:10 PM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Engineering Manager on behalf of PCD Engineering Division
|
8/31/2023 3:58:05 PM
|
Submission Triaged
|
8/31/2023 9:39:48 AM
|
Submission received from Applicant
|
8/28/2023 12:48:39 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
7/21/2023 1:22:33 PM
|
Request for Review Comments returned by EPC Health Department
|
7/12/2023 4:01:34 PM
|
Request for Review Comments returned by Parks Advisory Board
|
7/10/2023 8:32:11 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
7/10/2023 11:55:52 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/30/2023 4:53:39 PM
|
Submission request sent to Applicant
|
6/30/2023 4:27:28 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/30/2023 4:09:05 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/30/2023 4:08:05 PM
|
Request for Review Comments email resent for Project Mayberry Filing No. 4 for review by Ryan Howser on behalf of PCD Project Manager
|
6/30/2023 4:05:17 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/29/2023 2:11:01 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/29/2023 9:13:11 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
6/28/2023 11:09:48 AM
|
Request for Review Comments returned by EPC Parks Department
|
6/27/2023 9:20:31 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/22/2023 2:20:41 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/22/2023 8:20:44 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
6/12/2023 1:32:00 PM
|
Request for Review Comments returned by County Attorney - Water
|
6/12/2023 9:41:25 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
6/8/2023 3:07:26 PM
|
Request for Review Comments returned by EPC Environmental Services
|
6/7/2023 8:25:35 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Paul Poppert on behalf of Schriever AFB
|
6/7/2023 8:25:34 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/7/2023 8:25:33 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Chris Smith on behalf of Ellicott SD 22
|
6/7/2023 8:25:32 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Bookkeeper Peggy Current on behalf of Ellicott Metro
|
6/7/2023 8:25:31 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Michael Henley on behalf of Ellicott Fire Protection District
|
6/7/2023 8:25:28 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
6/7/2023 8:25:27 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
6/7/2023 8:25:26 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/7/2023 8:25:25 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
6/7/2023 8:25:24 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
6/7/2023 8:25:16 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
6/7/2023 8:25:15 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
6/7/2023 8:25:13 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Permits Program Manager Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
6/7/2023 8:25:06 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by on behalf of Parks Advisory Board
|
6/7/2023 8:25:05 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
6/7/2023 8:25:01 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Bill Elder on behalf of EPC Sheriff's Department
|
6/7/2023 8:25:00 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Bill Elder on behalf of EPC Sheriff's Department
|
6/7/2023 8:24:58 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
6/7/2023 8:24:57 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by on behalf of EPC Parks Department
|
6/7/2023 8:24:56 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Catherine McGarvy on behalf of EPC Health Department
|
6/7/2023 8:24:53 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Kathy Andrew on behalf of EPC Environmental Services
|
6/7/2023 8:24:52 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by April Willie on behalf of County Attorney - Water
|
6/7/2023 8:24:50 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Lori Seago on behalf of County Attorney - Development Review
|
6/7/2023 8:24:49 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Ryan Howser on behalf of PCD Project Manager
|
6/7/2023 8:24:48 AM
|
Request for Review Comments email sent for Project Mayberry Filing No. 4 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/6/2023 3:57:50 PM
|
Fees paid: 6/6/2023 (Receipt: 1007961)
|
5/24/2023 4:12:16 PM
|
Payment Request sent: 5/24/2023
|
5/24/2023 4:12:16 PM
|
File # Assigned: SF2317
|
5/24/2023 4:12:11 PM
|
Submission Triaged
|
5/24/2023 1:59:01 PM
|
Submission received from Applicant
|
12/8/2022 3:00:43 PM
|
Submission request sent to Applicant
|
12/8/2022 2:58:14 PM
|
Project Manager Assigned: Ryan Howser
|
12/8/2022 2:58:14 PM
|
EA Assigned: EA2216
|
12/8/2022 2:58:14 PM
|
Project Created
|