10/18/2022 3:07:02 PM
|
Project Closed
|
10/18/2022 3:07:02 PM
|
Project Approved: 10/18/2022
|
10/18/2022 3:06:36 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/18/2022 12:50:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/11/2022 8:59:57 AM
|
Submission Triaged
|
10/11/2022 8:32:31 AM
|
Submission received from Applicant
|
10/11/2022 7:41:41 AM
|
Submission request sent to Applicant
|
10/7/2022 10:18:42 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
10/6/2022 1:48:27 PM
|
Request for Review Comments email sent for Project High View Estates for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/6/2022 1:48:26 PM
|
Request for Review Comments email sent for Project High View Estates for review by Kylie Bagley on behalf of PCD Project Manager
|
10/6/2022 1:48:23 PM
|
Request for Review Comments email sent for Project High View Estates for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/2/2022 11:14:15 AM
|
Request for Review Comments returned by EPC Health Department
|
9/28/2022 8:05:19 AM
|
Request for Review Comments email sent for Project High View Estates for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
9/28/2022 8:05:17 AM
|
Request for Review Comments email sent for Project High View Estates for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/28/2022 8:05:16 AM
|
Request for Review Comments email sent for Project High View Estates for review by Kylie Bagley on behalf of PCD Project Manager
|
9/28/2022 8:05:12 AM
|
Request for Review Comments email sent for Project High View Estates for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/28/2022 7:56:48 AM
|
Submission Triaged
|
9/27/2022 3:48:24 PM
|
Submission received from Applicant
|
9/15/2022 9:09:33 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/8/2022 10:26:40 AM
|
Submission request sent to Applicant
|
9/8/2022 10:25:08 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/8/2022 10:21:40 AM
|
Request for Review Comments email resent for Project High View Estates for review by Kylie Bagley on behalf of PCD Project Manager
|
9/7/2022 3:32:32 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/7/2022 12:26:41 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
9/7/2022 10:27:32 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
9/6/2022 11:48:01 AM
|
Submission request sent to Applicant
|
9/6/2022 11:47:21 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/6/2022 11:07:00 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/2/2022 11:17:31 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/2/2022 8:51:45 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/30/2022 10:41:42 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
8/29/2022 2:43:29 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/22/2022 7:48:40 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
8/19/2022 10:09:59 AM
|
Request for Review Comments returned by EPC Parks Department
|
8/18/2022 10:21:29 AM
|
Request for Review Comments returned by EPC Environmental Services
|
8/17/2022 8:53:44 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
8/16/2022 3:12:42 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
8/16/2022 11:02:32 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
8/15/2022 2:21:48 PM
|
Request for Review Comments returned by County Attorney - Water
|
8/15/2022 2:16:23 PM
|
Request for Review Comments email sent for Project High View Estates for review by General Email on behalf of Mountain View Electric Association, Inc.
|
8/15/2022 2:16:22 PM
|
Request for Review Comments email sent for Project High View Estates for review by Vicki Wood on behalf of Lewis Palmer 38
|
8/15/2022 2:16:21 PM
|
Request for Review Comments email sent for Project High View Estates for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
8/15/2022 2:16:20 PM
|
Request for Review Comments email sent for Project High View Estates for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
8/15/2022 2:16:18 PM
|
Request for Review Comments email sent for Project High View Estates for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
8/15/2022 2:16:17 PM
|
Request for Review Comments email sent for Project High View Estates for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
8/15/2022 2:16:16 PM
|
Request for Review Comments email sent for Project High View Estates for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
8/15/2022 2:16:15 PM
|
Request for Review Comments email sent for Project High View Estates for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
8/15/2022 2:16:05 PM
|
Request for Review Comments email sent for Project High View Estates for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
8/15/2022 2:16:04 PM
|
Request for Review Comments email sent for Project High View Estates for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
8/15/2022 2:16:02 PM
|
Request for Review Comments email sent for Project High View Estates for review by on behalf of Parks Advisory Board
|
8/15/2022 2:16:01 PM
|
Request for Review Comments email sent for Project High View Estates for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/15/2022 2:15:58 PM
|
Request for Review Comments email sent for Project High View Estates for review by Bill Elder on behalf of EPC Sheriff's Department
|
8/15/2022 2:15:57 PM
|
Request for Review Comments email sent for Project High View Estates for review by Bill Elder on behalf of EPC Sheriff's Department
|
8/15/2022 2:15:56 PM
|
Request for Review Comments email sent for Project High View Estates for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
8/15/2022 2:15:55 PM
|
Request for Review Comments email sent for Project High View Estates for review by on behalf of EPC Parks Department
|
8/15/2022 2:15:53 PM
|
Request for Review Comments email sent for Project High View Estates for review by Catherine McGarvy on behalf of EPC Health Department
|
8/15/2022 2:15:50 PM
|
Request for Review Comments email sent for Project High View Estates for review by Kathy Andrew on behalf of EPC Environmental Services
|
8/15/2022 2:15:49 PM
|
Request for Review Comments email sent for Project High View Estates for review by Edi Anderson on behalf of County Attorney - Water
|
8/15/2022 2:15:45 PM
|
Request for Review Comments email sent for Project High View Estates for review by Lori Seago on behalf of County Attorney - Development Review
|
8/15/2022 2:15:42 PM
|
Request for Review Comments email sent for Project High View Estates for review by Steve Schleiker on behalf of Assessor's Office
|
8/15/2022 2:15:41 PM
|
Request for Review Comments email sent for Project High View Estates for review by Kylie Bagley on behalf of PCD Project Manager
|
8/15/2022 2:15:40 PM
|
Request for Review Comments email sent for Project High View Estates for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/13/2022 10:20:54 AM
|
Fees paid: 8/13/2022 (Receipt: 1006777)
|
8/13/2022 10:12:46 AM
|
Payment Request sent: 8/13/2022
|
8/13/2022 10:12:41 AM
|
Submission Triaged
|
8/12/2022 9:54:39 AM
|
Submission received from Applicant
|
8/12/2022 8:07:45 AM
|
File # Assigned: SF2227
|
8/11/2022 5:07:33 PM
|
Submission request sent to Applicant
|
8/11/2022 5:05:48 PM
|
Submission request sent to Applicant
|
8/11/2022 5:01:53 PM
|
Submission Triaged
|
8/11/2022 10:47:08 AM
|
Submission received from Applicant
|
7/20/2022 1:57:05 PM
|
Submission request sent to Applicant
|
7/19/2022 4:00:07 PM
|
Project Manager Assigned: Kylie Bagley
|
7/19/2022 4:00:07 PM
|
EA Assigned: EA2199
|
7/19/2022 4:00:07 PM
|
Project Created
|