11/15/2022 10:59:01 AM
|
Project Closed
|
11/15/2022 10:59:01 AM
|
Project Approved: 11/15/2022
|
10/18/2022 10:28:06 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
10/17/2022 2:21:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/16/2022 9:44:42 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/21/2022 10:37:08 AM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/21/2022 10:37:06 AM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/21/2022 10:36:49 AM
|
Submission Triaged
|
9/21/2022 9:24:11 AM
|
Submission received from Applicant
|
9/21/2022 8:47:50 AM
|
Submission request sent to Applicant
|
9/8/2022 12:44:05 PM
|
Submission request sent to Applicant
|
9/8/2022 12:00:39 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/8/2022 11:25:40 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/2/2022 2:39:50 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/31/2022 4:38:07 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/31/2022 4:38:05 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/12/2022 4:32:44 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/12/2022 4:32:41 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
8/12/2022 4:32:40 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Catherine McGarvy on behalf of EPC Health Department
|
8/12/2022 4:32:38 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Ryan Howser on behalf of PCD Project Manager
|
8/12/2022 4:32:37 PM
|
Request for Review Comments email sent for Project Wirenut Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/12/2022 4:26:52 PM
|
Fees paid: 8/12/2022 (Receipt: 1006776)
|
8/12/2022 4:17:17 PM
|
Project Manager Assigned: Ryan Howser
|
8/12/2022 4:16:43 PM
|
Payment Request sent: 8/12/2022
|
8/12/2022 4:16:43 PM
|
File # Assigned: CDR2214
|
8/12/2022 4:16:41 PM
|
Submission Triaged
|
8/12/2022 10:46:08 AM
|
Submission received from Applicant
|
8/11/2022 3:38:13 PM
|
Submission request sent to Applicant
|
8/11/2022 3:38:01 PM
|
Submission Triaged
|
8/9/2022 4:46:02 PM
|
Submission received from Applicant
|
7/15/2022 12:58:27 PM
|
Submission request sent to Applicant
|
7/15/2022 12:54:06 PM
|
EA Assigned: EA21110
|
7/15/2022 12:54:06 PM
|
Project Created
|