Project Details

Search | All Active Projects


File Number
AG2222
Description
(Overall Dimension is 54'X70') Livestock Barn: (caring for, training, and raising horses and possibly other farm animals) with covered shelter stalls on either side of breezeway. Breezeway: (Dimension is 30'x70") For airflow to the barn/stalls, storage for tools/lawnmower, tractor & implement storage (snow plow, spreader), tack/saddle prep, before taking horses to the on-site training arena and/or section 16/Open Space. Access is by (14'x14') Rollup door needed to access the livestock. Each enclosed covered easement (12'X70'): should allow for @ 5 - 8'x12' stalls, leaving a (4') wide access way in front of the stalls to move livestock. Access through a normal door or through the cutouts from the breezeway. The stall arrangement leaves a hefty (10' X 12') Feed storage area at both easement ends. 3 Large (11'X11') cutouts in both interior walls provide airflow to the livestock stalls. This also allows for easy access by tractor to the stalls and/or the Feed areas.
Parcels
5204010022 5204010022
Project Address
13750 New Discovery Rd
COLORADO SPRINGS, CO 80908
Applicant
Rick Trinkle
Rick Trinkle ( rick.trinkle@gmail.com )
(719) 465-4354
Rick Trinkle ( rick.trinkle@gmail.com )
(719) 465-4354
File Prefix
AG - Agricultural Structure
Year
2022
Number of Structures
1
New Construction?
Yes
Estimated date of Completion
9/30/2022
Square Footage
3780
# Design Features
4
Exterior Appearance
Appropriately sized doors to allow for livestock and/or agricultural implements and machinery to enter and exit the structure (REQUIRED); Barn Breezeway; Shelter Overhang; Appropriate siding material for weather exposure; Finished wood panels, vinyl siding, brick or stone veneer siding, stuco, etc.;
Use of the Structure
Shelter for livestock (including hen chickens) or for the storage of the feed and equipment relating to the care, training, raising, and/or maintenance of the livestock (including hen chickens);
Project Manager
Joe Letke
Status
Active
Created
7/15/2022 12:17:13 PM

View: Review Comments




Project Approvals (2)

The Project needs to be approved by these Agencies.

Project pending final approval.

Status Approver Reviewer Date
Approved PCD Site Plans Petra Rangel (petrarangel@elpasoco.com) 7/21/2022
EPC Code Enforcement

Approved Documents (1)

Project pending final approval. Some approved documents are available prior to the overall Approval.

Link Document
View Site Plan Drawing


Review Documents (2)

Link Document Date
View Site Plan Drawing 7/15/2022 12:17:17 PM
View Trinkle Barn Drawing 7/15/2022 12:17:17 PM