11/14/2024 11:50:19 AM
|
Project Closed
|
11/14/2024 11:50:19 AM
|
Project Approved: 11/14/2024
|
8/12/2024 5:29:37 PM
|
Project reopened for Approval requests
|
8/12/2024 5:29:20 PM
|
Project Closed
|
8/12/2024 5:29:20 PM
|
Project Approved: 8/12/2024
|
8/12/2024 1:46:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/8/2024 4:00:30 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/29/2024 3:58:22 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Kari Parsons on behalf of PCD Project Manager
|
7/29/2024 3:58:18 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/29/2024 3:58:15 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Engineering Manager on behalf of PCD Engineering Division
|
7/29/2024 3:57:01 PM
|
Submission Triaged
|
7/29/2024 3:55:54 PM
|
Submission received from Applicant
|
5/21/2024 7:52:19 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/21/2024 7:37:36 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Kari Parsons on behalf of PCD Project Manager
|
5/20/2024 12:50:36 PM
|
Request for Review Comments returned by EPC Parks Department
|
5/15/2024 3:04:54 PM
|
Request for Review Comments returned by EPC Sheriff's Department
|
5/14/2024 3:24:41 PM
|
Submission request sent to Applicant
|
5/14/2024 3:24:18 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/14/2024 9:22:25 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/9/2024 12:02:18 PM
|
Fees paid: 5/9/2024 (Receipt: 1009104)
|
5/8/2024 2:51:28 PM
|
Payment Request sent: 5/8/2024
|
5/8/2024 2:27:44 PM
|
Request for Review Comments returned by PCD Administrative
|
5/2/2024 11:28:03 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/2/2024 9:52:53 AM
|
Request for Review Comments email resent for Project Settlers Ranch Fil 3 Rezone for review by on behalf of Pikes Peak Regional Building Department
|
5/2/2024 9:25:03 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/1/2024 3:49:15 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Tracey Garcia on behalf of PCD Administrative
|
5/1/2024 3:49:13 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Admin on behalf of PCD Administrative
|
5/1/2024 3:49:11 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Elena Krebs on behalf of PCD Administrative
|
5/1/2024 3:32:10 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
4/25/2024 1:37:54 PM
|
Request for Review Comments returned by EPC Environmental Services
|
4/24/2024 7:13:11 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
4/23/2024 1:52:23 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/23/2024 11:57:37 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
4/23/2024 10:51:58 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
4/23/2024 10:51:56 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
4/23/2024 10:51:54 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/23/2024 10:51:52 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Vicki Wood on behalf of Lewis Palmer 38
|
4/23/2024 10:51:50 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Melissa Andrews on behalf of Lewis Palmer 38
|
4/23/2024 10:51:48 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Brett Ridgway on behalf of Lewis Palmer 38
|
4/23/2024 10:51:46 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
4/23/2024 10:51:44 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
4/23/2024 10:51:42 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
4/23/2024 10:51:39 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
4/23/2024 10:51:37 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
4/23/2024 10:51:35 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
4/23/2024 10:51:33 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
4/23/2024 10:51:31 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
4/23/2024 10:51:29 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
4/23/2024 10:51:27 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by on behalf of Pikes Peak Regional Building Department
|
4/23/2024 10:51:25 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
4/23/2024 10:51:23 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
4/23/2024 10:51:21 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
4/23/2024 10:51:19 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by on behalf of EPC Parks Department
|
4/23/2024 10:51:17 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Mike McCarthy on behalf of EPC Health Department
|
4/23/2024 10:51:15 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Catherine McGarvy on behalf of EPC Health Department
|
4/23/2024 10:51:13 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by HEAEH LandUse on behalf of EPC Health Department
|
4/23/2024 10:51:11 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
4/23/2024 10:51:08 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Kari Parsons on behalf of PCD Project Manager
|
4/23/2024 10:51:04 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/23/2024 10:51:00 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 3 Rezone for review by Engineering Manager on behalf of PCD Engineering Division
|
4/23/2024 10:48:06 AM
|
Submission Triaged
|
4/23/2024 7:27:42 AM
|
Submission received from Applicant
|
2/1/2024 2:57:54 PM
|
Submission request sent to Applicant
|
12/18/2023 11:40:45 AM
|
Submission request sent to Applicant
|
12/18/2023 11:11:55 AM
|
Submission request sent to Applicant
|
11/27/2023 2:10:32 PM
|
Submission request sent to Applicant
|
11/27/2023 2:04:33 PM
|
Submission request sent to Applicant
|
11/27/2023 2:01:42 PM
|
Submission request sent to Applicant
|
11/27/2023 1:56:57 PM
|
Set Applicant to JPS Engineering, Inc.
|
1/13/2023 2:37:43 PM
|
Request for Review Comments returned by EPC Health Department
|
1/11/2023 3:24:14 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
12/22/2022 4:33:09 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
12/21/2022 1:54:23 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
12/7/2022 7:05:40 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
12/6/2022 3:01:48 PM
|
Submission request sent to Applicant
|
12/6/2022 3:01:26 PM
|
Submission request sent to Applicant
|
12/6/2022 3:00:09 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/6/2022 11:46:25 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2022 10:55:32 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
12/6/2022 10:55:31 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
12/6/2022 10:55:29 AM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
12/5/2022 4:04:24 PM
|
Project Manager Assigned: Kari Parsons
|
12/1/2022 4:28:14 PM
|
Request for Review Comments returned by EPC Parks Department
|
11/30/2022 9:42:54 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/17/2022 2:00:37 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/16/2022 4:41:27 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/16/2022 3:41:59 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
11/16/2022 3:41:58 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
|
11/16/2022 3:41:57 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Vicki Wood on behalf of Lewis Palmer 38
|
11/16/2022 3:41:56 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
11/16/2022 3:41:54 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
11/16/2022 3:41:53 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Bill Elder on behalf of EPC Sheriff's Department
|
11/16/2022 3:41:52 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Bill Elder on behalf of EPC Sheriff's Department
|
11/16/2022 3:41:51 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by on behalf of EPC Parks Department
|
11/16/2022 3:41:50 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Catherine McGarvy on behalf of EPC Health Department
|
11/16/2022 3:41:46 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/16/2022 3:41:45 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Kylie Bagley on behalf of PCD Project Manager
|
11/16/2022 3:41:44 PM
|
Request for Review Comments email sent for Project Settlers Ranch Fil 2D Phase 4 Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/7/2022 2:15:49 PM
|
Fees paid: 11/7/2022 (Receipt: 1007168)
|
11/7/2022 7:26:47 AM
|
Payment Request sent: 11/7/2022
|
11/7/2022 7:26:46 AM
|
File # Assigned: P2223
|
11/7/2022 7:26:44 AM
|
Submission Triaged
|
11/5/2022 3:11:24 PM
|
Submission received from Applicant
|
7/7/2022 3:57:35 PM
|
Submission request sent to Applicant
|
6/8/2022 10:35:21 AM
|
Project Manager Assigned: Kylie Bagley
|
6/8/2022 10:35:21 AM
|
EA Assigned: EA2291
|
6/8/2022 10:35:21 AM
|
Project Created
|