10/25/2022 2:59:16 PM
|
Submission received from Applicant
|
10/25/2022 2:27:06 PM
|
Submission request sent to Applicant
|
10/17/2022 10:36:56 AM
|
Project Closed
|
10/17/2022 10:36:56 AM
|
Project Approved: 10/17/2022
|
10/17/2022 8:06:03 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/13/2022 2:33:37 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
10/13/2022 2:33:35 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/13/2022 2:32:34 PM
|
Submission Triaged
|
10/13/2022 9:45:05 AM
|
Submission received from Applicant
|
10/10/2022 2:12:01 PM
|
Submission request sent to Applicant
|
9/20/2022 11:30:54 AM
|
Submission Triaged
|
9/12/2022 3:25:53 PM
|
Submission received from Applicant
|
8/30/2022 12:34:11 PM
|
Submission request sent to Applicant
|
8/16/2022 9:33:17 AM
|
Request for Review Comments returned by PCD Engineering Division
|
8/16/2022 8:44:58 AM
|
Project reopened for Approval requests
|
8/16/2022 8:44:36 AM
|
Project Closed
|
8/16/2022 8:44:36 AM
|
Project Approved: 8/16/2022
|
8/16/2022 8:44:09 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/8/2022 4:15:05 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
8/8/2022 4:15:03 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by on behalf of Security Fire Protection District
|
8/8/2022 4:15:02 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
8/8/2022 4:15:00 PM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/8/2022 2:15:21 PM
|
Submission Triaged
|
8/7/2022 5:49:23 PM
|
Submission received from Applicant
|
8/5/2022 3:36:13 PM
|
Submission request sent to Applicant
|
7/8/2022 8:30:58 AM
|
Submission request sent to Applicant
|
7/5/2022 1:06:21 PM
|
Submission Triaged
|
6/29/2022 10:02:18 PM
|
Submission received from Applicant
|
6/13/2022 8:09:44 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/10/2022 11:58:23 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
6/2/2022 7:42:35 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/2/2022 3:55:16 PM
|
Submission request sent to Applicant
|
6/2/2022 3:52:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/2/2022 3:49:32 PM
|
Request for Review Comments email resent for Project 520 Empress Street Board of Adjustment for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
5/31/2022 3:25:18 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/25/2022 2:13:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/24/2022 3:31:39 PM
|
Request for Review Comments returned by Widefield SD 3
|
5/23/2022 11:12:42 AM
|
Request for Review Comments returned by Fountain
|
5/23/2022 8:01:49 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by COO Dave Gish on behalf of Widefield SD 3
|
5/23/2022 8:01:47 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
5/23/2022 8:01:46 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by on behalf of Security Fire Protection District
|
5/23/2022 8:01:45 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Kristy Martinez on behalf of Fountain
|
5/23/2022 8:01:44 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
5/23/2022 8:01:43 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Airport Planner Tyler Hardman on behalf of Colorado Springs Airport Advisory Commission
|
5/23/2022 8:01:41 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/23/2022 8:01:40 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
5/23/2022 8:01:39 AM
|
Request for Review Comments email sent for Project 520 Empress Street Board of Adjustment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/20/2022 12:18:11 PM
|
Fees paid: 5/20/2022 (Receipt: 1006368)
|
5/20/2022 11:32:55 AM
|
Project Manager Assigned: Matthew Fitzsimmons
|
5/20/2022 11:30:16 AM
|
Payment Request sent: 5/20/2022
|
5/20/2022 11:30:15 AM
|
File # Assigned: BOA228
|
5/20/2022 11:30:13 AM
|
Submission Triaged
|
5/20/2022 10:20:18 AM
|
Submission received from Applicant
|
5/2/2022 2:21:55 PM
|
Submission request sent to Applicant
|
5/2/2022 2:14:57 PM
|
Project Manager Assigned: Kylie Bagley
|
5/2/2022 2:14:57 PM
|
Project Created
|