7/21/2022 4:48:51 PM
|
Project Closed
|
7/21/2022 4:48:51 PM
|
Project Approved: 7/21/2022
|
7/21/2022 12:08:42 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
7/21/2022 12:08:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/19/2022 7:25:07 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Ryan Howser on behalf of PCD Project Manager
|
7/19/2022 7:24:45 AM
|
Submission Triaged
|
7/17/2022 5:21:18 PM
|
Submission received from Applicant
|
7/12/2022 4:44:27 PM
|
Submission request sent to Applicant
|
7/12/2022 4:12:42 PM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Ryan Howser on behalf of PCD Project Manager
|
7/12/2022 4:12:41 PM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/12/2022 4:10:46 PM
|
Submission Triaged
|
7/12/2022 1:42:44 PM
|
Submission received from Applicant
|
7/6/2022 3:09:06 PM
|
Submission request sent to Applicant
|
7/6/2022 2:35:38 PM
|
Submission request sent to Applicant
|
7/6/2022 10:10:49 AM
|
Submission request sent to Applicant
|
7/6/2022 10:09:37 AM
|
Submission request sent to Applicant
|
7/6/2022 7:47:45 AM
|
Project Manager Assigned: Ryan Howser
|
6/3/2022 2:29:29 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
6/1/2022 11:46:24 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/26/2022 8:29:47 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/16/2022 1:36:06 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/10/2022 2:19:51 PM
|
Project Manager Assigned: HR Green EPC Consultant
|
5/10/2022 10:23:03 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/6/2022 10:01:58 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
5/6/2022 10:01:57 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/6/2022 10:01:56 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/6/2022 10:01:55 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Kylie Bagley on behalf of PCD Project Manager
|
5/6/2022 10:01:53 AM
|
Request for Review Comments email sent for Project 17997 Sierra Way Tower for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/5/2022 2:20:34 PM
|
Fees paid: 5/5/2022 (Receipt: 1006268)
|
5/5/2022 12:53:55 PM
|
Payment Request sent: 5/5/2022
|
5/5/2022 12:53:54 PM
|
File # Assigned: PPR2226
|
5/5/2022 12:53:52 PM
|
Submission Triaged
|
5/5/2022 11:26:09 AM
|
Submission received from Applicant
|
5/5/2022 10:17:26 AM
|
Submission request sent to Applicant
|
5/5/2022 10:17:17 AM
|
Submission Triaged
|
5/5/2022 9:57:06 AM
|
Submission received from Applicant
|
4/15/2022 3:44:07 PM
|
Submission request sent to Applicant
|
4/15/2022 3:40:24 PM
|
Project Manager Assigned: Kylie Bagley
|
4/15/2022 3:40:24 PM
|
Project Created
|