5/18/2022 11:17:05 AM
|
Project Closed
|
5/18/2022 11:17:05 AM
|
Project Approved: 5/18/2022
|
5/18/2022 11:16:47 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
5/9/2022 9:06:18 AM
|
Submission Triaged
|
5/5/2022 2:40:21 PM
|
Submission received from Applicant
|
5/5/2022 2:24:31 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/4/2022 4:26:15 PM
|
Submission request sent to Applicant
|
5/4/2022 2:10:04 PM
|
Submission Triaged
|
4/29/2022 6:06:31 PM
|
Submission received from Applicant
|
4/29/2022 3:40:20 PM
|
Submission request sent to Applicant
|
4/29/2022 3:39:43 PM
|
Submission Triaged
|
4/26/2022 3:56:10 PM
|
Submission received from Applicant
|
4/26/2022 10:46:51 AM
|
Submission request sent to Applicant
|
4/26/2022 10:45:02 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/25/2022 3:30:20 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/25/2022 1:39:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/21/2022 2:08:29 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
4/21/2022 10:43:12 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
4/15/2022 2:23:30 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Ashlyn Mathy on behalf of PCD Project Manager
|
4/15/2022 2:23:29 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/15/2022 2:21:11 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/15/2022 2:21:10 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Melissa Andrews on behalf of Falcon School District 49
|
4/15/2022 2:21:09 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
4/15/2022 2:21:08 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
4/15/2022 2:20:56 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
4/15/2022 2:20:55 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
4/15/2022 2:20:54 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Catherine McGarvy on behalf of EPC Health Department
|
4/15/2022 2:20:46 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Ashlyn Mathy on behalf of PCD Project Manager
|
4/15/2022 2:20:44 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/15/2022 2:20:43 PM
|
Request for Review Comments email sent for Project 12643 Fulford Ct ALQ for review by Elena Krebs on behalf of PCD Administrative Notice
|
4/15/2022 7:53:21 AM
|
Fees paid: 4/15/2022 (Receipt: 1006167)
|
4/14/2022 9:32:53 PM
|
Payment Request sent: 4/14/2022
|
4/14/2022 9:32:49 PM
|
File # Assigned: AL226
|
4/14/2022 9:32:34 PM
|
Project Manager Assigned: Ashlyn Mathy
|
4/14/2022 9:32:12 PM
|
Submission Triaged
|
4/13/2022 6:41:05 PM
|
Submission received from Applicant
|
4/8/2022 3:36:33 PM
|
Submission request sent to Applicant
|
4/8/2022 3:35:28 PM
|
Project Manager Assigned: Kylie Bagley
|
4/8/2022 3:35:28 PM
|
Project Created
|