| 3/1/2023 12:46:15 PM | Project Closed | 
                
                    | 3/1/2023 12:46:15 PM | Project Approved: 3/1/2023 | 
                
                    | 3/1/2023 9:39:59 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 2/22/2023 8:12:05 AM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department | 
                
                    | 2/21/2023 2:32:32 PM | Submission Triaged | 
                
                    | 2/21/2023 2:26:30 PM | Submission received from Applicant | 
                
                    | 2/17/2023 3:05:30 PM | Submission request sent to Applicant | 
                
                    | 2/10/2023 2:50:59 PM | Project Manager Assigned: Cristel Madden | 
                
                    | 1/30/2023 7:19:22 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 1/4/2023 8:01:49 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 1/4/2023 11:01:26 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 1/4/2023 8:44:53 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 12/14/2022 5:29:56 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department | 
                
                    | 12/14/2022 5:29:54 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 12/14/2022 5:29:50 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by HR Green EPC Consultant on behalf of PCD Project Manager | 
                
                    | 12/14/2022 5:29:48 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 12/14/2022 4:36:42 PM | Submission Triaged | 
                
                    | 12/9/2022 9:26:11 AM | Submission received from Applicant | 
                
                    | 10/3/2022 8:48:52 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 9/6/2022 9:52:47 PM | Submission request sent to Applicant | 
                
                    | 9/6/2022 9:50:39 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 9/6/2022 2:22:52 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 9/2/2022 9:32:12 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 8/31/2022 7:43:12 AM | Request for Review Comments returned by Lewis Palmer 38 | 
                
                    | 8/30/2022 5:45:37 PM | Request for Review Comments email resent for Project Fall Mountain Farm  for review by Executive Director of Operations Chris Coulter on behalf of Lewis Palmer 38 | 
                
                    | 8/30/2022 3:32:59 PM | Request for Review Comments returned by Lewis Palmer 38 | 
                
                    | 8/29/2022 4:59:01 PM | Request for Review Comments email resent for Project Fall Mountain Farm  for review by Executive Director of Operations Chris Coulter on behalf of Lewis Palmer 38 | 
                
                    | 8/29/2022 3:45:27 PM | Request for Review Comments returned by Lewis Palmer 38 | 
                
                    | 8/29/2022 12:47:30 PM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 8/16/2022 9:29:12 AM | Request for Review Comments email resent for Project Fall Mountain Farm  for review by Executive Director of Operations Chris Coulter on behalf of Lewis Palmer 38 | 
                
                    | 8/16/2022 8:47:09 AM | Project Manager Assigned: HR Green EPC Consultant | 
                
                    | 8/16/2022 7:59:00 AM | Request for Review Comments returned by Lewis Palmer 38 | 
                
                    | 8/15/2022 2:46:28 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District | 
                
                    | 8/15/2022 2:46:26 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 8/15/2022 2:46:25 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Vicki Wood on behalf of Lewis Palmer 38 | 
                
                    | 8/15/2022 2:46:24 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department | 
                
                    | 8/15/2022 2:46:23 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 8/15/2022 2:46:19 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Kylie Bagley on behalf of PCD Project Manager | 
                
                    | 8/15/2022 2:46:18 PM | Request for Review Comments email sent for Project Fall Mountain Farm  for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 8/3/2022 6:15:42 PM | Fees paid: 8/3/2022 (Receipt: 1006730) | 
                
                    | 8/1/2022 10:59:15 AM | Payment Request sent: 8/1/2022 | 
                
                    | 8/1/2022 10:59:14 AM | File # Assigned: PPR2246 | 
                
                    | 8/1/2022 10:59:07 AM | Submission Triaged | 
                
                    | 7/29/2022 5:22:15 PM | Submission received from Applicant | 
                
                    | 6/10/2022 7:56:48 AM | Submission request sent to Applicant | 
                
                    | 3/1/2022 9:15:50 AM | Submission request sent to Applicant | 
                
                    | 1/21/2022 9:37:47 AM | Project Manager Assigned: Kylie Bagley | 
                
                    | 1/21/2022 9:37:47 AM | Project Created |