1/18/2023 7:46:19 AM
|
Project Closed
|
1/18/2023 7:46:19 AM
|
Project Approved: 1/18/2023
|
1/13/2023 11:49:39 AM
|
Request for Review Comments returned by EPC Health Department
|
1/4/2023 12:20:18 PM
|
Project Manager Assigned: Planning Manager Justin Kilgore
|
12/12/2022 10:45:39 AM
|
Project Manager Assigned: Kari Parsons
|
11/30/2022 7:57:41 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/28/2022 3:41:04 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/14/2022 4:03:37 PM
|
Request for Review Comments returned by EPC Parks Department
|
11/9/2022 1:01:52 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by on behalf of EPC Parks Department
|
11/9/2022 1:01:50 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Catherine McGarvy on behalf of EPC Health Department
|
11/9/2022 1:01:34 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/9/2022 1:00:51 PM
|
Request for Review Comments sent for Project EMPRISE STORAGE Rezone for review by Kylie Bagley on behalf of PCD Project Manager
|
11/9/2022 12:52:06 PM
|
Submission Triaged
|
11/9/2022 9:10:08 AM
|
Submission received from Applicant
|
11/9/2022 7:43:28 AM
|
Submission request sent to Applicant
|
11/8/2022 2:47:40 PM
|
Submission request sent to Applicant
|
11/8/2022 9:05:25 AM
|
Submission request sent to Applicant
|
10/25/2022 8:13:35 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
10/21/2022 3:59:43 PM
|
Request for Review Comments returned by EPC Health Department
|
10/20/2022 7:43:00 AM
|
Submission request sent to Applicant
|
10/19/2022 8:13:49 AM
|
Submission request sent to Applicant
|
10/19/2022 8:12:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/17/2022 11:27:27 AM
|
Project Manager Assigned: Kylie Bagley
|
10/17/2022 11:02:56 AM
|
Request for Review Comments returned by EPC Parks Department
|
10/13/2022 8:27:55 AM
|
Request for Review Comments email resent for Project EMPRISE STORAGE Rezone for review by on behalf of EPC Parks Department
|
10/12/2022 3:20:11 PM
|
Request for Review Comments returned by Parks Advisory Board
|
10/11/2022 9:08:45 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
10/11/2022 8:21:59 AM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
10/11/2022 8:21:58 AM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
10/10/2022 4:49:46 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
10/10/2022 8:13:28 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/9/2022 8:31:38 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/3/2022 6:14:43 PM
|
Request for Review Comments returned by EPC Parks Department
|
10/3/2022 5:14:19 PM
|
Request for Review Comments email resent for Project EMPRISE STORAGE Rezone for review by on behalf of EPC Parks Department
|
10/3/2022 1:33:56 PM
|
Request for Review Comments returned by EPC Environmental Services
|
10/3/2022 8:15:44 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/26/2022 4:27:54 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/26/2022 8:07:29 AM
|
Request for Review Comments returned by EPC Parks Department
|
9/25/2022 5:32:19 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
9/24/2022 4:22:23 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
9/22/2022 3:05:13 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
9/21/2022 3:36:47 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/21/2022 3:36:46 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Richard Cromwell on behalf of Ellicott Utilities (does area that was Sunset Metro)
|
9/21/2022 3:36:45 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Lisa Johnson on behalf of Ellicott Town Center Metropolitan District
|
9/21/2022 3:36:44 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Chris Smith on behalf of Ellicott SD 22
|
9/21/2022 3:36:43 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Danny Gillis on behalf of Ellicott Plaza
|
9/21/2022 3:36:41 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Bookkeeper Peggy Current on behalf of Ellicott Metro
|
9/21/2022 3:36:40 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Michael Henley on behalf of Ellicott Fire Protection District
|
9/21/2022 3:36:39 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Dave Sanger on behalf of Ellicott Elementary/Senior High School
|
9/21/2022 3:36:38 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
9/21/2022 3:36:37 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
9/21/2022 3:36:36 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
9/21/2022 3:36:35 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by CDOT Permits Program Mgr Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
9/21/2022 3:36:33 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by on behalf of Parks Advisory Board
|
9/21/2022 3:36:32 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by on behalf of EPC Parks Department
|
9/21/2022 3:36:31 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Catherine McGarvy on behalf of EPC Health Department
|
9/21/2022 3:36:28 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/21/2022 3:36:27 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Mindy Madden on behalf of EPC Code Enforcement
|
9/21/2022 3:36:26 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Lori Seago on behalf of County Attorney - Development Review
|
9/21/2022 3:36:24 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
9/21/2022 3:36:23 PM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/20/2022 1:42:05 PM
|
Request for Review Comments returned by County Attorney - Water
|
9/20/2022 8:10:57 AM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Edi Anderson on behalf of County Attorney - Water
|
9/20/2022 8:10:53 AM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
9/20/2022 8:10:52 AM
|
Request for Review Comments email sent for Project EMPRISE STORAGE Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/16/2022 2:07:07 PM
|
Fees paid: 9/16/2022 (Receipt: 1006935)
|
9/13/2022 9:03:28 AM
|
Project Manager Assigned: Matthew Fitzsimmons
|
9/13/2022 9:02:47 AM
|
File # Assigned: CS222
|
9/13/2022 8:55:42 AM
|
Submission Triaged
|
9/12/2022 4:59:23 PM
|
Submission received from Applicant
|
12/22/2021 1:38:20 PM
|
Submission request sent to Applicant
|
12/16/2021 3:53:42 PM
|
Project Manager Assigned: John Green
|
12/16/2021 3:53:42 PM
|
EA Assigned: EA21226
|
12/16/2021 3:53:42 PM
|
Project Created
|